Construction Gantt chart template: design to handover

An editable construction schedule Gantt chart: design, permits, procurement, site preparation, structure, building services, finishes, inspection and handover, with dependencies and milestones.

Use this template

What the construction gantt chart template: design to handover process is

A construction schedule is a sequence of trades, and the trades overlap in specific ways. The frame cannot start before the foundations are cured. The services cannot be installed before the frame is up. Finishes cannot begin until the building is weathertight. Those constraints are what a Gantt chart is for, and a plan that ignores them gives a date that no one believes.

This template follows a generic building from design to handover in five phases: Design and approvals, Procurement, Site and structure, Services and finishes, and Completion. It includes the things that tend to set the real date: the permit approval, which depends on the authority and not the contractor, and long-lead items such as steel or switchgear, which are ordered early so they are on site when the frame needs them. "Weathertight" is a milestone because it is the point at which interior work becomes safe from the weather.

Treat every duration as an example. Real durations depend on the size and type of the building, the site, the season and the contractor, and approval times vary widely between authorities and jurisdictions. The chart is a way to see how those uncertainties combine. Change "Permit application and approval" from 30 days to 60 and see what moves.

This is a planning aid, not an engineering or contractual programme. A contractor's programme, with resource levelling and weather allowances, belongs in dedicated scheduling software. The chart does not track cost.

What this flowchart covers

In this template

  • Five phases, Design and approvals, Procurement, Site and structure, Services and finishes and Completion, with 19 tasks and four milestones: "Permits granted", "Weathertight", "Completion certificate" and the handover that follows.
  • Permits as a dependency outside the contractor's control: "Mobilise site" waits for both "Permits granted" and "Tender and contractor selection".
  • Long-lead items ordered early: "Order long-lead items" follows the tender and is needed by "Structural frame".
  • Trades that overlap: "Mechanical, electrical and plumbing first fix" starts five days after the frame, and "MEP second fix and commissioning" starts ten days into "Internal finishes".
  • A sequence to completion: "Inspections and snagging", "Completion certificate" and "Handover and documentation".

When to use this template

  • You need a rough programme for a building project before a contractor provides one.
  • A client asks how long the project takes and what the date depends on.
  • A permit or a delivery is late and you want to see its effect on later trades.
  • You are comparing how the schedule changes if the design takes longer.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Concept and briefDesign and approvals10
2Detailed designDesign and approvals251
3Permit application and approvalDesign and approvals302
4Permits grantedDesign and approvalsMilestone3
5Tender and contractor selectionProcurement152
6Order long-lead itemsProcurement55
7Mobilise siteSite and structure54, 5
8Site preparation and groundworkSite and structure107
9FoundationsSite and structure158
10Structural frameSite and structure256, 9
11Roof and envelopeSite and structure1510
12WeathertightSite and structureMilestone11
13Mechanical, electrical and plumbing first fixServices and finishes2010+5
14Internal finishesServices and finishes2512, 13
15MEP second fix and commissioningServices and finishes1014SS+10
16External worksServices and finishes1511
17Inspections and snaggingCompletion814, 15, 16
18Completion certificateCompletionMilestone17
19Handover and documentationCompletion518

How it works

  1. Replace the phases with your project's

    Keep the order: design, approvals, procurement, site and structure, services and finishes, completion. Rename and add trades as your project needs.

  2. Use realistic durations

    Replace the sample durations with those from similar projects or from your contractor. Remember that these are working days, so a calendar month is about 20.

  3. Treat approvals and deliveries as tasks

    Give the permit and each long-lead item their own tasks. They are the dependencies you do not control, so they should be visible.

  4. Overlap trades with a lag

    Where one trade follows another with a gap or overlap, use a lag, or a start-to-start link, rather than finishing one before starting the next.

  5. Mark the physical milestones

    Keep "Weathertight" and the completion certificate. They tell everyone when conditions change.

  6. Check the critical path

    Switch it on in the View menu. In most buildings it runs through approvals, structure and finishes; delays there move handover.

Frequently asked questions

How do I make a construction Gantt chart?

List the phases and trades in building order, give each task a length in working days and link each to what it depends on. This template does that for a generic building. Edit it and the schedule is recalculated.

Is this a replacement for a contractor's programme?

No. It is a planning chart to understand sequence and sensitivity. A contractor's programme includes resources, weather and contract-specific constraints that this chart does not model.

Why are some trades linked start-to-start?

Because they really overlap. Second-fix services begin partway through finishes, not after them. A start-to-start link with a lag shows that overlap.

Are the durations realistic?

They are illustrative. Real durations depend on the building, the site, the season, the contractor and the local authority, and permit times in particular vary widely.

Part of

QueryChart features for this process

Use this template

More in Project management process templates

Browse all Project management process templates

Construction Gantt chart: Design and approvals → Procurement → Site and structure → Services and finishes → Completion
Construction Gantt chart template: design to handover