New product introduction Gantt chart template: design to first shipment

An editable Gantt chart for introducing a new physical product: requirements, design freeze, prototype and test, tooling, pilot run, qualification and a go-live decision, with dependencies and milestones.

Use this template

What the new product introduction gantt chart template: design to first shipment process is

Introducing a physical product is slower than designing it, because the design is only one of the things that has to be finished. Parts need suppliers, tooling needs ordering weeks before it is needed, and a pilot run cannot happen until both the design and the tools are ready. A flowchart shows the order of these steps; a Gantt chart shows how long the order takes, which is what a launch date depends on.

This template follows one product from frozen requirements to a go-live decision. The design track runs from "Freeze product requirements" through "Concept design" and "Design for manufacture review" to the milestone "Design freeze". The prototype is built and tested after the freeze, and "Fix issues and update the design" closes that loop. Beside it, "Select and quote suppliers" starts two working days after the manufacturing review starts, so supplier work overlaps the last of the design instead of waiting for the freeze, and "Order tooling" waits for both the freeze and the supplier selection.

The two tracks meet at "Pilot production run", which waits for the fixed design and for the tooling. Turn on the critical path in the View menu and you will see that tooling, not the prototype, usually sets the date: a 15-day tooling lead time is easy to start late. After the pilot, "Product qualified" is a milestone, "Ship first stock to the warehouse" follows it, and "Go-live decision" waits for the stock, the training and the sales and support material. Durations are illustrative working days (Monday to Friday); replace them with your own.

This is the plan for the product itself. For the marketing side of a release, see the [product launch Gantt chart template](/templates/product-launch-gantt-chart). It does not track part costs or supplier quality, and it does not compare a plan with what actually happened: there are no baselines. What it gives you is the schedule and the chain that sets it.

What this flowchart covers

In this template

  • Four groups, Design, Prototype and test, Supply and production and Launch, with 15 tasks and three milestones: "Design freeze", "Product qualified" and "Go-live decision".
  • Supply work that starts early: "Select and quote suppliers" begins two working days after "Design for manufacture review" begins.
  • A long lead time: "Order tooling" takes 15 working days and waits for both "Design freeze" and "Select and quote suppliers".
  • A meeting of two tracks: "Pilot production run" waits for both "Fix issues and update the design" and "Order tooling".
  • A final gate: "Go-live decision" waits for "Ship first stock to the warehouse", "Train production and service staff" and "Prepare sales and support material".

When to use this template

  • You are bringing a new physical product to production and need to see which wait sets the launch date.
  • Design, suppliers and tooling are managed by different people and you want one shared timeline.
  • You need to show a manager why a late design change moves the first shipment.
  • You want a starting plan for a prototype-to-pilot project that you can edit rather than draw from nothing.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Freeze product requirementsDesign5
2Concept designDesign81
3Design for manufacture reviewDesign42
4Design freezeDesignMilestone3
5Build prototypePrototype and test104
6Test prototypePrototype and test85
7Fix issues and update the designPrototype and test66
8Select and quote suppliersSupply and production103SS+2
9Order toolingSupply and production154, 8
10Pilot production runSupply and production57, 9
11Product qualifiedPrototype and testMilestone10
12Train production and service staffLaunch510
13Prepare sales and support materialLaunch87
14Ship first stock to the warehouseLaunch511
15Go-live decisionLaunchMilestone12, 13, 14

How it works

  1. Replace the tasks with your own

    Rename the 15 tasks and the four groups. Keep the groups to the tracks that really run separately, such as design, test, supply and launch.

  2. Set the lead times honestly

    Tooling, samples and shipping usually take longer than the work around them. Enter the supplier's quoted lead time as the task's length in working days.

  3. Mark the design freeze as a milestone

    A zero-length task. Make everything that depends on a fixed design wait for it, and keep early supplier work as a start-to-start link so it can overlap.

  4. Check the tracks meet where they should

    The pilot run should wait for the design and the tooling. If a task is missing a dependency, it will start too early and the plan will look shorter than it is.

  5. Turn on the critical path

    Use View, then Critical path, to see the chain of tasks that sets the go-live date. Shortening anything off that chain will not move the date.

  6. Update progress and share

    Set each task's progress as work completes and share the chart as a link or export a PDF for the launch review.

Frequently asked questions

What is a new product introduction Gantt chart?

A Gantt chart that lays out the tasks needed to take a new product from requirements to first shipment: design, prototype and test, supplier selection, tooling, pilot production and the go-live decision, with the dependencies between them.

Does this template track costs or parts?

No. It schedules tasks, dependencies and milestones only. There is no cost tracking and no bill of materials, and no baseline to compare the plan against.

Why does supplier selection overlap the design?

Because waiting for the design freeze to start looking for suppliers adds weeks. A start-to-start link with a two-day lag lets supplier work begin once the manufacturing review starts.

Are the durations realistic?

They are illustrative working days. Replace them with your own lead times, especially for tooling and shipping.

How is this different from the product launch template?

The product launch template plans the marketing and sales side of a release. This one plans the work of getting the product itself designed, tested, tooled and ready to ship.

Part of

QueryChart features for this process

Use this template

More in Product and engineering process templates

Browse all Product and engineering process templates

New product introduction Gantt chart template: Design → Prototype and test → Supply and production → Launch
New product introduction Gantt chart template: design to first shipment