Podcast launch Gantt chart template: batch recording and directory review

An editable podcast launch Gantt chart: concept and format, batch-recorded launch episodes, cover art, hosting and feed, the directory review wait, buffer episodes and launch day, with dependencies and milestones.

Use this template

What the podcast launch gantt chart template: batch recording and directory review process is

A podcast is a recurring show, so launching one is different from releasing a single piece of work. On day one listeners expect a trailer and several episodes, and a weekly schedule that does not stop after the first week. That means the work that decides the date is not the release itself but what must already exist: finished, approved episodes, a feed that directories have accepted and a few more episodes in hand. A timeline shows which of these is the slowest and what the rest can do while it runs.

This template has four groups: Concept and format, Recording and editing, Hosting and listings, and Launch and promotion. It has 21 tasks and four milestones. "Define the show concept and audience" (3 working days) is the only starting task, and "Plan the season and episode outlines" (4) leads to "Format locked". That gate comes before everything that is expensive to redo: booking guests, setting up the recording space, designing the cover art, writing the description and choosing the hosting service. Changing the format after recording starts means re-recording, not re-editing.

Recording is done in a batch. "Record launch episodes in a batch" (6) waits for "Book guests and recording slots" (4) and for "Set up recording space and equipment" (3), and "Record the trailer" (1) is done on the same set-up. Editing does not wait for the last session: "Edit and mix the launch episodes" (8) starts 2 working days after the batch starts, with a start-to-start link, so early episodes are edited while later ones are still being recorded. It still ends 4 days after the recording does, because the last episode can only be edited once it exists. "Review and approve the launch episodes" (3) leads to "Launch episodes approved", the gate for the feed.

In the illustrative numbers the date is set by the approved episodes and the directory wait together. "Upload episodes and build the feed" (2) needs the approved episodes, the trailer, the cover art, the description and the hosting service, and the trailer, cover art, description and hosting service are all ready long before the approved episodes. After "Submit the feed to directories" (1) comes "Directory review wait" (5), which is time you cannot shorten by working harder, and then "Directory listings live". "Prepare launch promotion and clips" (4) starts as soon as the episodes are approved and has 4 days to spare. "Record and edit buffer episodes" (6) follows the batch and is ready 9 working days before "Launch day", which is 32 working days into the plan. "Release episode 4 on the weekly schedule" ends the plan, so the second week is already covered. All durations are illustrative: replace them with your own pace and with what each directory tells you about its review.

A timeline schedules the work. It does not clear music, agree guest releases or make any rights or contract valid, so keep those as tasks with their own owners. For related plans, see /templates/content-calendar-gantt-chart for the weekly schedule after launch, /templates/video-production-gantt-chart for a plan where picture, not audio, is the long edit, and /templates/marketing-campaign-gantt-chart if the launch is part of a bigger campaign. For how review rounds and fixed release dates work in this kind of plan, see /guides/review-rounds-gantt-chart and /guides/release-date-lead-times-gantt-chart.

What this flowchart covers

In this template

  • Four groups, Concept and format, Recording and editing, Hosting and listings and Launch and promotion, with 21 tasks and four milestones: "Format locked", "Launch episodes approved", "Directory listings live" and "Launch day".
  • A format gate: guests, the recording space, cover art, the description and the hosting service all follow "Format locked", so nothing expensive starts on a format that may still change.
  • Batch recording with editing that overlaps it: "Edit and mix the launch episodes" starts 2 working days after "Record launch episodes in a batch" and ends 4 days after it.
  • A feed that waits for everything: "Upload episodes and build the feed" needs the approved episodes, "Record the trailer", the cover art, the description and the hosting service.
  • A directory wait and a cushion: "Directory review wait" in front of "Directory listings live", and "Record and edit buffer episodes" so "Release episode 4 on the weekly schedule" is ready on time.

When to use this template

  • You are launching a new show and need to know how many episodes must be finished, and approved, before the feed is submitted.
  • You want to see whether editing, the approval round or the directory wait decides the day you can announce the show.
  • The launch is tied to a date, such as a season start or an event, and you want to check that the preparation fits before it.
  • You run more than one show and want a standard launch plan to resize for each.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Define the show concept and audienceConcept and format3
2Plan the season and episode outlinesConcept and format41
3Format lockedConcept and formatMilestone2
4Book guests and recording slotsConcept and format43
5Set up recording space and equipmentRecording and editing33
6Record the trailerRecording and editing15
7Record launch episodes in a batchRecording and editing64, 5
8Edit and mix the launch episodesRecording and editing87SS+2
9Review and approve the launch episodesRecording and editing38
10Launch episodes approvedRecording and editingMilestone9
11Design cover art and show brandingHosting and listings53
12Write show description and episode notesHosting and listings33
13Choose and set up the hosting serviceHosting and listings23
14Upload episodes and build the feedHosting and listings26, 10, 11, 12, 13
15Submit the feed to directoriesHosting and listings114
16Directory review waitHosting and listings515
17Directory listings liveHosting and listingsMilestone16
18Prepare launch promotion and clipsLaunch and promotion410
19Record and edit buffer episodesRecording and editing67
20Launch dayLaunch and promotionMilestone17, 18
21Release episode 4 on the weekly scheduleLaunch and promotion119, 20

How it works

  1. Lock the format first

    Keep "Format locked" as the gate that guests, equipment, artwork and hosting follow. If the format is already decided, shorten "Define the show concept and audience" and "Plan the season and episode outlines" to a few days.

  2. Set the size of the batch

    Decide how many episodes you want ready on day one, then set "Record launch episodes in a batch" and "Edit and mix the launch episodes" from your own pace. A longer batch moves "Launch episodes approved" later.

  3. Check the editing overlap

    The 2-day start-to-start link lets editing begin while recording continues. Increase it if your first episodes need re-recording or a longer set-up before editing is worth starting.

  4. Replace the directory wait

    Set "Directory review wait" from what each directory tells you. These waits vary, and in the template this one sits between the feed and "Directory listings live".

  5. Build the buffer

    Set "Record and edit buffer episodes" to cover your first weeks of releases, and check that it ends before "Launch day". If you fall behind on it, the weekly schedule is the first thing to break.

  6. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with co-hosts and editors, and export a PDF or PNG for the team.

Frequently asked questions

How many episodes should be ready before launch?

That is your decision, and the chart does not set it. The template batch-records the launch episodes and adds a separate "Record and edit buffer episodes" task, so the show has a weekly rhythm beyond day one. Change the durations to match the number you plan to have in hand.

My launch has a fixed date. Can the chart check it?

Yes. Give "Define the show concept and audience" a fixed Start on the day you begin, then give "Launch day" a fixed Start on the date you announced. The plan starts on the earliest fixed Start and is scheduled forward: if the approved episodes and the directory wait cannot be done by then, "Launch day" is flagged with a conflict naming the earliest date its dependencies allow.

Does the chart know when a directory accepts the show?

No. It shows when you plan to submit the feed and how long you plan to wait. It does not contact any directory or know the outcome. When you hear, change the duration of "Directory review wait" and the dates after it move.

Why does editing start before recording ends?

Because each episode can be edited once it is recorded. The 2-day start-to-start link on "Edit and mix the launch episodes" lets editing begin early, but the task still ends after the last episode has been recorded and edited. See /guides/gantt-chart-overlapping-tasks for how overlap is drawn.

Can I use it for a podcast that already has episodes?

Yes. Remove the tasks you have done and resize the rest. If you only need the weekly schedule, start from /templates/content-calendar-gantt-chart instead.

Part of

QueryChart features for this process

Use this template

More in Operations process templates

Browse all Operations process templates