Veterinary theatre fit-out Gantt chart template: equipment lead times
An editable Gantt chart for fitting out a veterinary surgical theatre or imaging room: design, equipment delivery waits, building work, safety checks, commissioning, staff training and first supervised cases.
What the veterinary theatre fit-out gantt chart template: equipment lead times process is
The hard part of fitting out a theatre or an imaging room is that the room and the equipment arrive on different clocks. The room is a sequence of trades. The equipment is an order and a long wait. A timeline helps because it shows which of the two is holding the install, and whether the wait is a reason to order sooner or to stop worrying about the building.
This template has five groups: Design and approvals, Equipment, Building work, Safety and commissioning, and Staff and first cases. It has 23 tasks and 4 milestones, and in the illustrative numbers the project takes 56 working days. **Agree clinical needs and budget** (3) leads to **Draw the theatre and imaging layout** (5) and the milestone **Layout approved**. That milestone releases four paths at once: the two equipment orders, the room preparation and the protocols.
The equipment path is made of waits. **Order table, lights and anaesthesia machine** (2) is followed by **Wait for theatre equipment delivery** (25), and **Order the imaging unit** (1) by **Wait for imaging unit delivery** (30). Supplier lead times vary, so these durations are illustrative and you replace them with the dates your suppliers confirm. Meanwhile **Strip out and prepare the room** leads to **Fit flooring, walls and ventilation**, and **Run electrical and medical gas supply** starts 3 working days into that task with a start-to-start link so the trades overlap. **Fit imaging room shielding** runs alongside, and **Room ready for equipment** waits for all three.
The two paths join at the installs. **Install theatre equipment** needs the room and the theatre delivery, and **Install the imaging unit** needs the room and the imaging delivery. In the illustrative numbers the imaging unit's wait is the longer one, so the delivery sets the finish and the building work has slack. Then **Safety checks on gas, electrics and ventilation** and **Imaging room safety survey** lead to **Commission and test all equipment**. **Train staff on the new equipment** starts 2 working days into commissioning, and **Run a mock procedure** waits for training, "Equipment commissioned" and **Write theatre protocols and checklists**. **Run the first supervised cases** leads to **Theatre in full use**.
A timeline schedules the work. It does not say which safety checks, surveys or registrations your country or your insurer requires, and it does not make equipment safe to use. Keep those requirements as tasks or notes with their own owners and give the plan your own durations. For related plans, see /templates/equipment-installation-gantt for the install on its own and /templates/clinic-opening-gantt-chart for a whole new site. The flowchart for what the theatre is used for starts at /templates/veterinary-surgical-patient-pathway-process.
What this flowchart covers
In this template
- Five groups, Design and approvals, Equipment, Building work, Safety and commissioning and Staff and first cases, with 23 tasks and 4 milestones: "Layout approved", "Room ready for equipment", "Equipment commissioned" and "Theatre in full use".
- Two equipment lead times as plain waits: "Wait for theatre equipment delivery" (25 working days) and "Wait for imaging unit delivery" (30), each started by its own order.
- Overlapping trades: "Run electrical and medical gas supply" starts 3 working days into "Fit flooring, walls and ventilation", and "Fit imaging room shielding" runs beside them.
- Joins where the room meets the equipment: "Install theatre equipment" and "Install the imaging unit" each wait for "Room ready for equipment" and their own delivery.
- A people path from "Write theatre protocols and checklists" and "Train staff on the new equipment" to "Run a mock procedure" and "Run the first supervised cases".
When to use this template
- You are adding a surgical theatre or an imaging room and want to see whether the building or the deliveries decide the opening.
- You are about to place equipment orders and need to know how late they can be before the install slips.
- Several trades work in the same room and you want to see where they overlap and where one has to finish first.
- You need a plan to share with a builder, a supplier and the clinical team who will first use the room.
The plan, task by task
Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.
| # | Task | Group | Working days | Depends on |
|---|---|---|---|---|
| 1 | Agree clinical needs and budget | Design and approvals | 3 | |
| 2 | Draw the theatre and imaging layout | Design and approvals | 5 | 1 |
| 3 | Layout approved | Design and approvals | Milestone | 2 |
| 4 | Order table, lights and anaesthesia machine | Equipment | 2 | 3 |
| 5 | Wait for theatre equipment delivery | Equipment | 25 | 4 |
| 6 | Order the imaging unit | Equipment | 1 | 3 |
| 7 | Wait for imaging unit delivery | Equipment | 30 | 6 |
| 8 | Strip out and prepare the room | Building work | 6 | 3 |
| 9 | Fit flooring, walls and ventilation | Building work | 8 | 8 |
| 10 | Run electrical and medical gas supply | Building work | 5 | 9SS+3 |
| 11 | Fit imaging room shielding | Building work | 4 | 8 |
| 12 | Room ready for equipment | Building work | Milestone | 9, 10, 11 |
| 13 | Install theatre equipment | Building work | 3 | 5, 12 |
| 14 | Install the imaging unit | Building work | 2 | 7, 12 |
| 15 | Safety checks on gas, electrics and ventilation | Safety and commissioning | 3 | 13 |
| 16 | Imaging room safety survey | Safety and commissioning | 3 | 14 |
| 17 | Commission and test all equipment | Safety and commissioning | 3 | 15, 16 |
| 18 | Equipment commissioned | Safety and commissioning | Milestone | 17 |
| 19 | Write theatre protocols and checklists | Staff and first cases | 4 | 3 |
| 20 | Train staff on the new equipment | Staff and first cases | 4 | 17SS+2 |
| 21 | Run a mock procedure | Staff and first cases | 1 | 18, 19, 20 |
| 22 | Run the first supervised cases | Staff and first cases | 5 | 21 |
| 23 | Theatre in full use | Staff and first cases | Milestone | 22 |
How it works
Replace the delivery waits
Set "Wait for theatre equipment delivery" and "Wait for imaging unit delivery" to the lead times your suppliers confirm in writing. They are plain waits, so lengthening one moves its install and everything after it.
Fix the dates that are real
Give "Agree clinical needs and budget" a fixed Start on the day work begins, and give "Run the first supervised cases" a fixed Start on the day you want to operate. The plan is scheduled forward, so a conflict flag on that task tells you the earliest date its dependencies allow.
Resize the building work
Set "Strip out and prepare the room", "Fit flooring, walls and ventilation" and "Run electrical and medical gas supply" from your builder's programme, and adjust the 3-day overlap between the last two to match.
Put in the checks you need
Set "Safety checks on gas, electrics and ventilation" and "Imaging room safety survey" to the checks your country and insurer require, and add a task for any registration or sign-off they ask for. These differ by country, so the plan holds your own durations.
Plan the people side
Set "Train staff on the new equipment" from the supplier's training offer, and decide how many cases "Run the first supervised cases" should cover.
Add owners, share and export
Put the person responsible for each task in People, share the chart as a link with the builder and suppliers, and export a PDF or PNG for the project file.
Frequently asked questions
Which should I order first, the building work or the equipment?
The chart shows which wait is longer. In the illustrative plan "Wait for imaging unit delivery" is the longest path, so ordering the unit sooner moves the whole finish. Enter your suppliers' real lead times and compare.
Does the plan tell me which safety checks are required?
No. It schedules "Safety checks on gas, electrics and ventilation" and "Imaging room safety survey" with the durations you enter. Which checks are required, and how often, differs by country and by insurer.
What if a delivery is late?
Lengthen the delivery wait and see which dates move. The install, the checks, "Equipment commissioned" and "Theatre in full use" move because they follow it, while the building work does not. See /guides/gantt-chart-delays for reading a delay through a plan.
Can I use it for imaging only, without a theatre?
Yes. Remove the theatre equipment tasks and the theatre safety checks, and keep "Order the imaging unit", "Fit imaging room shielding", "Install the imaging unit" and "Imaging room safety survey".
Can the chart schedule the supplier's engineers?
It schedules the durations you give it, so you can add a task for an engineer visit and set its length. It does not book engineers or level resources.