New clinician onboarding Gantt chart template: supervised cases and sign-off
An editable Gantt chart for a new vet or nurse's first 90 working days: induction, a supervised case ramp and three competence sign-off gates, with dependencies, milestones and a feedback track that runs alongside.
What the new clinician onboarding gantt chart template: supervised cases and sign-off process is
A general onboarding plan counts days: week one is induction, week two is training, and so on. A clinical onboarding plan has a different shape, because the length of each stage depends on how many cases the new vet or nurse has handled with the mentor and when the mentor is satisfied. The stages therefore end in gates, and the next stage cannot start until the gate is passed. A timeline shows how those gates push the date of independent practice, and what a slow first stage costs the rest.
This template has five groups: Before day one, Induction, Supervised cases, Competence sign-off and Review. It has 22 tasks and five milestones, and a total length of 82 working days in the illustrative numbers. Before the start, **Confirm start date and registration checks** (3 working days) leads to **Set up logins, drug room access and rota** (4) and **Name a clinical mentor and plan the first weeks** (2), and both lead to the milestone **First day**. Induction is short: **Welcome and practice tour** (1), then **Clinical system and records training** (3) and **Safety and equipment induction** (3) side by side, ending at **Induction complete**.
The case ramp is the long part. **Shadow consultations** (5) comes first, then **Supervised consultations with the mentor in the room** (15), then **Mentor reviews consulting case log** (2) and the first gate, **Consulting sign-off**. After that gate two tracks open. **Supervised procedures and dispensing checks** (15) starts, and **Supervised anaesthetic and surgical cases** (20) starts 6 working days into it with a start-to-start link, so the first procedures overlap. **Shadow the out-of-hours rota** (5) runs on its own. **Mentor reviews procedure and anaesthetic log** (3) leads to the second gate, **Procedure sign-off**, and only then do **First on-call shifts with backup** (10) begin.
Running along the whole ramp is **Fortnightly feedback meetings** (60 working days), linked to start 5 working days into the supervised consultations. It is also the track that ends last in the illustrative numbers: **90 day review meeting** (1) waits for both **Collect case logs and colleague feedback** (3) and the feedback meetings, so the final gate, **Independent practice sign-off**, lands at working day 82. If a gate is delayed, the dates after it move and this track shows how much room is left. All durations are illustrative. Replace them with the case numbers and review times your clinical lead expects.
A timeline schedules the work. It does not decide that someone is competent, and it does not replace your professional body's requirements, your insurer's terms or your own competence framework. What counts as enough cases, and who may sign a gate, differs by role, by country and by practice, so keep those rules as notes on the gates. For related plans, see /templates/employee-onboarding-gantt-chart for a general first-90-days plan, /templates/veterinary-surgical-patient-pathway-process for the surgical flow a new vet will learn, and /guides/gantt-chart-milestones for how to use gates in a plan.
What this flowchart covers
In this template
- Five groups, Before day one, Induction, Supervised cases, Competence sign-off and Review, with 22 tasks and five milestones: "First day", "Induction complete", "Consulting sign-off", "Procedure sign-off" and "Independent practice sign-off".
- A supervised case ramp in two stages: "Supervised consultations with the mentor in the room" ends at a gate, then "Supervised procedures and dispensing checks" and "Supervised anaesthetic and surgical cases" overlap by a start-to-start link.
- Three gates that each follow a mentor review task: "Mentor reviews consulting case log", "Mentor reviews procedure and anaesthetic log" and "90 day review meeting".
- A track that runs beside the ramp: "Fortnightly feedback meetings" starts 5 working days into the first supervised stage and must finish before the final review.
- Out-of-hours preparation that is separate from the procedure stage: "Shadow the out-of-hours rota" and "First on-call shifts with backup", which waits for "Procedure sign-off".
When to use this template
- A new vet or nurse is joining and you want the supervised case ramp and its sign-off gates in one plan.
- You want to see how a slow first stage moves the date of the first on-call shift.
- You onboard several clinicians a year and want the same gates for each, with durations that vary by role.
- A mentor needs to see when review time must be booked in their own diary.
The plan, task by task
Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.
| # | Task | Group | Working days | Depends on |
|---|---|---|---|---|
| 1 | Confirm start date and registration checks | Before day one | 3 | |
| 2 | Set up logins, drug room access and rota | Before day one | 4 | 1 |
| 3 | Name a clinical mentor and plan the first weeks | Before day one | 2 | 1 |
| 4 | First day | Before day one | Milestone | 2, 3 |
| 5 | Welcome and practice tour | Induction | 1 | 4 |
| 6 | Clinical system and records training | Induction | 3 | 5 |
| 7 | Safety and equipment induction | Induction | 3 | 5 |
| 8 | Induction complete | Induction | Milestone | 6, 7 |
| 9 | Shadow consultations | Supervised cases | 5 | 6 |
| 10 | Supervised consultations with the mentor in the room | Supervised cases | 15 | 8, 9 |
| 11 | Fortnightly feedback meetings | Review | 60 | 10SS+5 |
| 12 | Mentor reviews consulting case log | Competence sign-off | 2 | 10 |
| 13 | Consulting sign-off | Competence sign-off | Milestone | 12 |
| 14 | Supervised procedures and dispensing checks | Supervised cases | 15 | 13 |
| 15 | Supervised anaesthetic and surgical cases | Supervised cases | 20 | 14SS+6 |
| 16 | Shadow the out-of-hours rota | Supervised cases | 5 | 13 |
| 17 | Mentor reviews procedure and anaesthetic log | Competence sign-off | 3 | 14, 15 |
| 18 | Procedure sign-off | Competence sign-off | Milestone | 17 |
| 19 | First on-call shifts with backup | Supervised cases | 10 | 16, 18 |
| 20 | Collect case logs and colleague feedback | Review | 3 | 19 |
| 21 | 90 day review meeting | Review | 1 | 11, 20 |
| 22 | Independent practice sign-off | Competence sign-off | Milestone | 21 |
How it works
Set the start
Give "First day" a fixed Start on the clinician's first working day. The plan is scheduled forward from the earliest fixed Start, and every date after it follows from the durations you enter.
Size the case ramp
Set "Supervised consultations with the mentor in the room", "Supervised procedures and dispensing checks" and "Supervised anaesthetic and surgical cases" from the number of cases your clinical lead expects, divided by the cases the clinic can offer each day. Adjust the 6-day start-to-start link to when the first procedures can begin.
Make each gate a real review
Set the three mentor review tasks to the time the reviewer actually needs. Use the milestones as the point where the sign-off is recorded, and write the practice's own criteria for each gate in the task notes.
Adjust the feedback track
Set "Fortnightly feedback meetings" to the number of working days between the first supervised case and the review. Check that it does not end after "Collect case logs and colleague feedback" unless you mean it to.
Remove what does not apply
A nurse may not need "Supervised anaesthetic and surgical cases" and a locum may not need the out-of-hours tasks. Delete them and check that nothing is left without a dependency.
Add owners, share and export
Put the clinician, the mentor and the practice manager in People, share the chart as a link, and export a PDF or PNG for the training file.
Frequently asked questions
How does this differ from a general onboarding plan?
A general plan moves through fixed weeks. This one moves through supervised case stages that end in sign-off gates, so the dates after a gate depend on when it is passed. See /templates/employee-onboarding-gantt-chart for the general version.
Can the chart tell me when a clinician is competent?
No. It shows the dates that follow from the durations you enter. Competence is a judgement made by the mentor and the clinical lead against your own framework, and the chart only holds the time reserved for it.
What if a gate is not passed on the first review?
Make the review task longer, or add a task for extra supervised cases before it, and the later dates move. The chart does not model a retry loop, so the extra time is entered as a task.
Does it cover registration or insurance requirements?
It has one task for registration checks before the start. What is required differs by country and by role, so check it with the relevant body and keep the details as notes on that task.
Can I use it for a nurse or a locum?
Yes. Shorten or remove the surgical and out-of-hours tasks, resize the supervised stages and keep the gates that apply to the role. For the clinical flows they will learn, see /templates/veterinary-medicine-dispensing-process.