Veterinary practice integration Gantt chart template: completion and overlap

An editable Gantt chart for acquiring a veterinary practice and bringing it into your group: due diligence, staff transfer notice wait, records migration with parallel running, stock count and branding, with dependencies.

Use this template

What the veterinary practice integration gantt chart template: completion and overlap process is

A practice acquisition has a fixed centre. Everything before completion exists to make that day safe, and everything after it exists to make the practice look and run like part of the group. A timeline shows how much of the work can be prepared in advance and how much can only start once ownership has changed. This template is built around that split, and it adds a second shape that is easy to forget: a period when two systems have to run at the same time.

The template has five groups: Due diligence, People, Systems and records, Drug store and stock, and Brand and clients. It has 23 tasks and 3 milestones, and in the illustrative numbers the whole integration takes 34 working days. **Agree integration scope and lead** (2) opens two checks that run side by side, **Review contracts, leases and equipment lists** (5) and **Check clinical records and drug register** (4). Both feed **Due diligence cleared**, and after **Exchange contracts and fix completion date** (3) the plan splits into the work that needs ownership and the work that does not.

The staff path is a wait. **Send staff transfer notices** (1) is a one-day task, and **Wait out the staff notice period** (10) is the time that has to pass before **Completion** can happen. How long that wait is differs by country and by the contracts involved, so the 10 days here are illustrative and you replace them with your own. While it runs, **Plan the records migration**, **Make a test copy of client records**, **Book the drug register and stock count** and **Prepare client letters and signage** all move forward, because none of them needs the practice to be yours yet.

After completion the plan changes character. **Copy final records on completion day** needs both "Completion" and the test copy. Then **Run old and new systems side by side** (10) is the overlap: **Train staff on the new system** starts 1 working day into it with a start-to-start link, and **Switch off the old system** waits for both. On the stock side, **Count stock and drug register at completion** leads to **Reconcile counts and move to one supplier account**. On the brand side, **Send the client announcement** and **Change signage and branding** both wait for completion. **Integration complete** closes the plan when staff, systems, stock and clients are all done.

A timeline schedules the work. It does not carry out a transfer of employment, decide who must be told, or check a drug register for you. Notice periods, controlled drug rules and record retention differ by country, so keep those as tasks or notes with their own owners and put your own durations in the plan. For related plans, see /templates/merger-acquisition-integration-gantt-chart for a larger integration, /templates/data-migration-gantt for the records move on its own, and /templates/clinic-opening-gantt-chart for a new site. The flowchart for the daily work the new team will inherit starts at /templates/veterinary-patient-admission-and-consent-process, and /guides/practice-integration-gantt-chart explains the completion date and the overlap in more detail.

What this flowchart covers

In this template

  • Five groups, Due diligence, People, Systems and records, Drug store and stock and Brand and clients, with 23 tasks and 3 milestones: "Due diligence cleared", "Completion" and "Integration complete".
  • A staff notice wait in front of completion: "Send staff transfer notices" and "Wait out the staff notice period" must both be finished before "Completion".
  • Preparation that needs no ownership: "Plan the records migration", "Make a test copy of client records" and "Prepare client letters and signage" run before completion.
  • A parallel-running overlap: "Train staff on the new system" starts 1 working day into "Run old and new systems side by side", and "Switch off the old system" waits for both.
  • A stock and drug register path from "Book the drug register and stock count" to "Reconcile counts and move to one supplier account", and a client path from letters to "Change signage and branding".

When to use this template

  • You are buying a veterinary practice and want to see what can be prepared before completion and what has to wait for it.
  • Staff have to be told and given time before the transfer, and you need to check that the wait fits before the date you have in mind.
  • You are moving a practice onto your records system and need to decide how long both systems should run together.
  • You are integrating several practices and want the same sequence of people, systems, stock and brand work for each.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Agree integration scope and leadDue diligence2
2Review contracts, leases and equipment listsDue diligence51
3Check clinical records and drug registerDue diligence41
4Due diligence clearedDue diligenceMilestone2, 3
5Exchange contracts and fix completion dateDue diligence34
6Send staff transfer noticesPeople15
7Wait out the staff notice periodPeople106
8CompletionDue diligenceMilestone5, 7
9Move staff onto the new payrollPeople38
10Induct transferred staffPeople49
11Plan the records migrationSystems and records34
12Make a test copy of client recordsSystems and records411
13Copy final records on completion daySystems and records28, 12
14Run old and new systems side by sideSystems and records1013
15Train staff on the new systemSystems and records314SS+1
16Switch off the old systemSystems and records114, 15
17Book the drug register and stock countDrug store and stock15
18Count stock and drug register at completionDrug store and stock28, 17
19Reconcile counts and move to one supplier accountDrug store and stock318
20Prepare client letters and signageBrand and clients45
21Send the client announcementBrand and clients18, 20
22Change signage and brandingBrand and clients38, 20
23Integration completeDue diligenceMilestone10, 16, 19, 21, 22

How it works

  1. Fix the completion date

    Give "Exchange contracts and fix completion date" a fixed Start when you expect to exchange. The plan starts on the earliest fixed Start and is scheduled forward, so a conflict flag on "Completion" tells you the earliest date its dependencies allow. Compare that with the date in the contract.

  2. Replace the notice wait

    Set "Wait out the staff notice period" to the notice your staff and contracts require. It differs by country and by contract, so the illustrative 10 days are a placeholder.

  3. Size the due diligence checks

    Set "Review contracts, leases and equipment lists" and "Check clinical records and drug register" to the time your advisers and clinical lead give you. "Due diligence cleared" moves with the longer of the two.

  4. Choose the overlap

    Set "Run old and new systems side by side" to the time you want both systems live, and move the start-to-start link on "Train staff on the new system" to when training can begin. "Switch off the old system" follows the later of the two.

  5. Plan the stock count and the announcement

    Set "Count stock and drug register at completion" and "Reconcile counts and move to one supplier account" from your own stock, and decide how early "Send the client announcement" should follow completion.

  6. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with the vendor, advisers and clinical leads, and export a PDF or PNG for the deal file.

Frequently asked questions

Can the chart tell me the legal notice period for staff?

No. It shows the duration you enter for "Wait out the staff notice period" and moves the dates after it. Notice requirements differ by country and by contract, so take them from your advisers and enter them as that task's duration.

How do I check the completion date still works?

Give "Exchange contracts and fix completion date" a fixed Start. The chart schedules forward from the earliest fixed Start, so if the notice wait and the due diligence cannot fit before the date you need, "Completion" shows a conflict and the earliest date its dependencies allow.

How long should the two systems run together?

That is your decision. The 10 days are illustrative. Lengthen "Run old and new systems side by side" and "Switch off the old system", "Integration complete" and everything after it move with it.

Does the plan cover controlled drugs rules?

No. It schedules "Book the drug register and stock count" and the tasks after it. The rules for counting, transferring and recording controlled drugs differ by country, so keep them as notes on those tasks.

Can I use it for a merger of two practices rather than a purchase?

Yes. Remove the exchange and notice tasks you do not need, keep the systems and stock paths, and add a task for any step your merger needs. For a larger corporate integration, see /templates/merger-acquisition-integration-gantt-chart.