How to plan a veterinary practice integration on a Gantt chart

Plan the integration of an acquired veterinary practice on a Gantt chart: due diligence, a staff notice wait, records migration with a side-by-side run, the drug register count and the client announcement, all anchored to completion.

An acquisition has one date that everything waits for, the completion, and several waits that run on either side of it. This guide shows how to put them on a Gantt chart, see which strand sets the finish and decide what to run in parallel.

The short version

  • Fix the Start of the first task and let completion follow from the dependencies you give it.
  • Link the work that can only happen on completion day to the "Completion" milestone and nothing earlier.
  • Give the staff notice period a plain wait task with a duration you replace.
  • Use a start-to-start link with a lag to train staff while the old and new systems run side by side.
  • Turn on Critical path to see whether the staff wait or the records migration sets the finish.

Let completion be the gate that the integration waits for

Integrating a veterinary practice looks like one project, but it is five strands that meet at one moment. The paperwork before completion is due diligence. After it, staff move across, client records are copied into the new system, the drug register and stock are counted and the clients hear about the change. Each strand has its own wait, and the strands only share one thing: none of them can start its real work until completion has happened.

A Gantt chart in QueryChart schedules forward from the earliest fixed Start. Give "Agree integration scope and lead" a fixed Start on the day you begin and the plan flows from there. "Exchange contracts and fix completion date" is the task that sets the date everything else hangs on, so link "Completion", a milestone, to it and to the staff notice wait. Work that must happen on completion day, such as copying the final records and counting the drug register, is linked to "Completion" and nothing earlier.

The example below is the veterinary practice integration template: 23 tasks in five groups. Two features make it different from a generic project plan. The first is a plain wait for staff notice, "Wait out the staff notice period", which is given an illustrative 10 working days that you replace with what your own contracts and local rules set. The second is a parallel run: "Train staff on the new system" starts one working day into "Run old and new systems side by side", using a start-to-start link with a 1 day lag, so the training happens while both systems are live.

After the example, a flowchart shows a process worth harmonising across the sites you now run: dispensing medicine. A Gantt chart can say when each site adopts it, but it cannot draw the checks and loops inside the process itself. Durations in both charts are illustrative. Notice periods, controlled drug handling and client data rules differ by country and practice type, so the plan holds your durations and your own advice decides what they are. A timeline schedules the work. It is not veterinary, legal or financial advice, and it does not confirm that an integration is compliant.

For waits and gaps in general see /guides/gantt-chart-buffer-time and /guides/gantt-chart-delays. For a neighbouring project with a fixed opening date, see /templates/clinic-opening-gantt-chart, and for a seasonal programme that runs inside a practice, see /guides/seasonal-clinic-campaign-gantt-chart.

A practice integration, built in stages

Twenty-three tasks in five groups. Durations are illustrative working days. Open the spreadsheet panel to see the rows behind each stage.

  1. Scope and due diligence

    "Agree integration scope and lead" (2 working days) leads to "Review contracts, leases and equipment lists" (5) and "Check clinical records and drug register" (4), which run side by side. "Due diligence cleared" is a milestone on day 7, and "Exchange contracts and fix completion date" (3) follows it. Fix the Start of the first task on the day you begin.

  2. Staff and the notice wait

    "Send staff transfer notices" (1) leads to "Wait out the staff notice period" (10), a plain wait with an illustrative duration. "Completion" waits for both the exchange and that wait. "Move staff onto the new payroll" (3) and "Induct transferred staff" (4) can only start after it.

  3. Records and the side-by-side run

    "Plan the records migration" (3) and "Make a test copy of client records" (4) run before completion, so the final copy is a rehearsed one. "Copy final records on completion day" (2) needs "Completion". "Run old and new systems side by side" (10) is followed by "Switch off the old system" (1), and "Train staff on the new system" (3) starts 1 working day into the run.

  4. The drug register and the stock

    "Book the drug register and stock count" (1) is arranged after the exchange. "Count stock and drug register at completion" (2) needs both that booking and "Completion", and "Reconcile counts and move to one supplier account" (3) follows. The rules for how a register is counted differ by country, so replace these durations with your own.

  5. Clients, branding and the finish

    "Prepare client letters and signage" (4) is done before completion. "Send the client announcement" (1) and "Change signage and branding" (3) wait for "Completion". "Integration complete" collects staff, systems, stock and clients. The longest chain adds up to 34 working days, set by the notice wait and then the side-by-side run.

A process to harmonise across the sites

The medicine dispensing process as a flowchart. After an acquisition, the Gantt chart says when each site adopts it and this chart shows what is adopted.

  1. The prescription and the stock check

    "Treatment decision needs a medicine" leads to "Write the prescription with item, strength and course length" and then "Item in stock at the right strength?". A No sends the work to "Agree an alternative item or order the stock" and back to the prescription. Sites that came from different suppliers will meet this loop most often in the first weeks.

  2. Controlled items and the label

    "Controlled item on the prescription?" splits the route. Yes goes to "Draw the item from the locked store and enter it in the controlled register" and No goes to "Pick the item from the dispensary shelf". Both reach "Print the label with pet name, directions and warnings". The register step is where the count in the integration plan has to agree with how the new site actually works.

  3. The second check before handover

    "Second person agrees item, strength, quantity and label?" sends a No to "Correct the item or label and ask for a fresh check". A Yes leads to "Pack the medicine with written instructions". Staff who transfer in will have their own habit here, which is a good reason to put this chart in front of them during "Induct transferred staff".

  4. Counselling and the record

    "Owner arrives to collect the medicine" leads to "Counsel the owner on dose, timing, storage and signs to report" and "Owner confirms they can give it as directed?". A No offers a demonstration and counsels again. "Record the supply in the patient file" and "Add the item to the invoice" end at "Medicine supplied, explained and recorded". Which of these steps your sites must follow is set by your own rules and advice.

Veterinary medicine dispensing process flowchart

How it works

  1. Open the practice integration chart

    Open the template and replace each duration with what your contracts, advisers and suppliers tell you. Put the person responsible for each task in People.

  2. Fix the first Start

    Give "Agree integration scope and lead" a fixed Start on the day you begin. The plan is scheduled forward, so the completion date is a result of the chain until you have contracts that fix it.

  3. Set the staff notice wait

    Replace the duration of "Wait out the staff notice period" with the period your own contracts and local rules set. Hover over the task to see the dates it produces.

  4. Link completion-day work to the milestone

    Check that the final records copy, the drug register count, the client announcement and the signage change are each linked to "Completion" and not to an earlier task.

  5. Find the strand that sets the finish

    Turn on Critical path in the View menu. If the staff wait is lit, shorten the notice by agreement. If the records strand is lit, look at the side-by-side run and the training.

  6. Share the plan with the site leads

    Share the chart as a link so each site lead can see their strand and add comments. Export a PDF for the people who are not in the chart.

Mistakes to avoid

  • Starting completion-day work too early

    If the final records copy or the stock count is linked to due diligence instead of completion, the chart shows them done before the practice is yours. Link them to the milestone.

  • Leaving the side-by-side run out

    Without a parallel run the old system switches off the day the new one starts. Give the run a duration and start the training inside it.

  • Using the template durations as facts

    The notice period, the count and the migration times are illustrative. Your own contracts, advisers and suppliers set the real ones.

  • Assuming the chart checks compliance

    QueryChart schedules the tasks. It does not check controlled drug rules, data protection duties or employment law, and it is not advice. Keep a separate checklist.

Open the practice integration Gantt chart

Open the template, fix the first Start and see which strand sets the integration finish.

Open the practice integration Gantt chart

Related guides

Frequently asked questions

Can QueryChart work backwards from the completion date?

No. Scheduling is forward only. Fix the Start of the first task, and fix the Start of "Completion" if the date is already agreed, then read the conflict flag to see whether the chain before it fits.

How long is the staff notice period?

It depends on the contracts and the local rules. The chart holds a wait task with an illustrative duration that you replace with the one you are given.

How do I train staff while both systems are running?

Link the training to the side-by-side run with a start-to-start dependency and a lag. In the example the training starts 1 working day into the run.

Can I paste my own integration plan?

Yes. Paste your table into the spreadsheet panel with one row per task and the group, duration and dependencies in columns. You can then edit it as a chart.

The template behind this guide

Veterinary practice integration Gantt chart template: completion and overlap — An editable Gantt chart for acquiring a veterinary practice and bringing it into your group: due diligence, staff transfer notice wait, records migration with parallel running, stock count and branding, with dependencies.