Dental practice handover Gantt chart template: notice wait and completion
An editable Gantt chart for an owner handing a dental practice to a successor: due diligence, staff and patient notices, records transfer, introductions, supplier accounts, a notice wait and a fixed completion date.
What the dental practice handover gantt chart template: notice wait and completion process is
A handover has a different shape from most projects. The end is fixed first, as a completion date agreed between the owner and the successor, and the plan has to be checked against it. Between the start and the end there is a stretch of waiting for patient notices to run their course, and several threads of work that all have to finish before completion day. A timeline shows whether those threads fit, and which one is the longest.
This template has five groups: Due diligence, Staff and patients, Records and systems, Suppliers and accounts, and Completion. It has 22 tasks and four milestones, and a total length of 41 working days in the illustrative numbers. "Agree heads of terms" (2 working days) is the only starting task. "Buyer reviews accounts and patient numbers" (8) and "Review lease, equipment and contracts" (6) run side by side, and "Answer the buyer's questions" (4) starts 3 working days into the accounts review with a start-to-start link, so questions are answered as they arise. "Due diligence complete" is the first gate, and "Draft the staff announcement" (2) is prepared in the meantime.
After the gate the plan splits into four threads. In Staff and patients, "Brief the team in person" (1) is followed by "Send patient notices" (2), then "Notice period runs" (15), a plain wait with nothing to do on your side except "Introduce the successor to staff and patients" (6). In Records and systems, "Plan the records transfer" (3) and "Test export of records and imaging" (4) can finish early, but "Final records copy and transfer" (2) waits for the notice period to end before "Records transferred". In Suppliers and accounts, "Notify suppliers and labs" (4) leads to "Move utility, lab and card accounts" (3), and "Confirm insurance cover for the successor" (3) stands alone.
In the illustrative numbers the notice wait decides everything: "Ready for completion" arrives on day 30 because the records copy cannot start until the notice period is over. The other threads finish by day 17, so they have a good deal of slack. "Completion day" (1) is the task to give a fixed Start, and "Practice handed over" follows it. "Hand over keys, alarm codes and logins" (1) starts with completion, and "Owner available for handover questions" (10) runs afterwards. The notice length, and whether records can be copied before it ends, differ by country and by agreement, so the plan holds only the durations you enter. All durations are illustrative.
A timeline schedules the work. It does not replace legal advice, and it does not state what notice you must give patients, staff or landlords. Keep those requirements as tasks or notes with their own owners. For related plans, see /templates/veterinary-practice-integration-gantt-chart for taking over another practice, /templates/dental-recall-and-hygiene-visit-process for the recall flowchart the successor will inherit, and /guides/gantt-chart-milestones for how a fixed completion is marked in a plan.
What this flowchart covers
In this template
- Five groups, Due diligence, Staff and patients, Records and systems, Suppliers and accounts and Completion, with 22 tasks and four milestones: "Due diligence complete", "Records transferred", "Ready for completion" and "Practice handed over".
- A notice wait as a plain task: "Notice period runs" (15 working days in the illustrative plan) follows "Send patient notices" and holds "Final records copy and transfer".
- Early preparation that does not wait: "Plan the records transfer", "Test export of records and imaging", "Notify suppliers and labs" and "Introduce the successor to staff and patients" all finish before the notice wait ends.
- A start-to-start link in due diligence: "Answer the buyer's questions" starts 3 working days into "Buyer reviews accounts and patient numbers".
- A fixed completion: "Completion day" waits for "Ready for completion", with "Hand over keys, alarm codes and logins" starting with it and "Owner available for handover questions" after "Practice handed over".
When to use this template
- You are selling or buying a practice and need to see whether the threads of work fit before the agreed completion date.
- You want to know how much of the run-up is waiting for notices and how much is work you can do while you wait.
- The successor needs to be introduced to staff and patients and you want those sessions placed inside the notice wait.
- You advise several owners and want one handover sequence to resize for each.
The plan, task by task
Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.
| # | Task | Group | Working days | Depends on |
|---|---|---|---|---|
| 1 | Agree heads of terms | Due diligence | 2 | |
| 2 | Buyer reviews accounts and patient numbers | Due diligence | 8 | 1 |
| 3 | Review lease, equipment and contracts | Due diligence | 6 | 1 |
| 4 | Answer the buyer's questions | Due diligence | 4 | 2SS+3 |
| 5 | Due diligence complete | Due diligence | Milestone | 2, 3, 4 |
| 6 | Draft the staff announcement | Staff and patients | 2 | 1 |
| 7 | Brief the team in person | Staff and patients | 1 | 5, 6 |
| 8 | Send patient notices | Staff and patients | 2 | 7 |
| 9 | Notice period runs | Staff and patients | 15 | 8 |
| 10 | Introduce the successor to staff and patients | Staff and patients | 6 | 7 |
| 11 | Plan the records transfer | Records and systems | 3 | 5 |
| 12 | Test export of records and imaging | Records and systems | 4 | 11 |
| 13 | Final records copy and transfer | Records and systems | 2 | 9, 12 |
| 14 | Records transferred | Records and systems | Milestone | 13 |
| 15 | Notify suppliers and labs | Suppliers and accounts | 4 | 5 |
| 16 | Move utility, lab and card accounts | Suppliers and accounts | 3 | 15 |
| 17 | Confirm insurance cover for the successor | Suppliers and accounts | 3 | 5 |
| 18 | Ready for completion | Suppliers and accounts | Milestone | 10, 14, 16, 17 |
| 19 | Completion day | Completion | 1 | 18 |
| 20 | Practice handed over | Completion | Milestone | 19 |
| 21 | Hand over keys, alarm codes and logins | Completion | 1 | 19SS |
| 22 | Owner available for handover questions | Completion | 10 | 20 |
How it works
Fix the dates that are real
Give "Agree heads of terms" a fixed Start on the day you begin, and give "Completion day" a fixed Start on the agreed completion date. The plan starts on the earliest fixed Start and is scheduled forward, so a conflict flag on the completion task tells you the earliest date its dependencies allow. Compare that with the date in the agreement.
Enter your own notice length
Set "Notice period runs" from the requirement that applies to your practice and tenancy. It differs by country, so take it from your adviser and enter it as a number of working days.
Resize due diligence
Set "Buyer reviews accounts and patient numbers" and "Review lease, equipment and contracts" from what the buyer has asked for, and adjust the start-to-start link on "Answer the buyer's questions" to how early questions arrive.
Place records and accounts
Check whether "Final records copy and transfer" really has to wait for the notice period in your case. If it does not, change its dependency in the sheet and see how far "Ready for completion" moves.
Plan the introductions
Set "Introduce the successor to staff and patients" to the sessions you can hold, and make sure it ends before "Ready for completion".
Add owners, share and export
Put the person responsible for each task in People, share the chart as a link with the buyer and the advisers, and export a PDF or PNG for the file.
Frequently asked questions
Can the chart tell me how long the notice period must be?
No. It shows the duration you enter for "Notice period runs" and moves the dates after it. The required notice differs by country and by tenancy, so take it from your adviser and change that one task.
The completion date is already agreed. How do I check it fits?
Give "Agree heads of terms" a fixed Start and "Completion day" a fixed Start on the agreed date. The chart schedules forward from the earliest fixed Start. If due diligence, the notice wait and the records copy cannot finish by then, the completion task shows a conflict and the earliest date its dependencies allow.
Does the plan make the handover legal or compliant?
No. It schedules the work. It does not check any contract, notice or registration, and it does not replace advice. Keep each requirement as a task or a note with an owner.
What if due diligence takes longer?
Lengthen "Buyer reviews accounts and patient numbers" and see which dates move. Everything after "Due diligence complete" moves with it, including the notice wait. See /guides/gantt-chart-delays for reading a delay through a plan.
Can I use it for a partner buy-in?
Yes. Remove the patient notice tasks, keep due diligence and the account moves, and resize the rest. For a larger takeover with several sites, see /templates/veterinary-practice-integration-gantt-chart.