Dental associate onboarding Gantt chart template: supervised ramp, list build
An editable Gantt chart for onboarding a new associate dentist: contract and checks, systems access, induction, a ramp of supervised sessions, building the patient list and a 90-day review, with dependencies.
What the dental associate onboarding gantt chart template: supervised ramp, list build process is
Onboarding an associate dentist differs from onboarding most staff in one way: clinical work is released in steps. First there are sessions with a mentor, then reduced sessions with a mentor on call, then full sessions, and the diary opens to new patients only as the ramp allows. A timeline shows how much of the first quarter is checks and supervision, and when the associate's own list starts to fill.
This template has five groups: Contract and checks, Systems and kit, Induction, Supervised sessions and Patient list. It has 24 tasks and three milestones, and a total length of 63 working days in the illustrative numbers, which is the first 90 days or so in a five-day week. "Agree the offer and contract terms" (5 working days) leads to "Contract signed". Two waits then run side by side, "Registration and indemnity checks" (10) and "Reference and background checks" (12), and "Cleared to start" needs both. How long these take, and what must be checked, differ by country and by employer, so replace the durations with what you are told.
The practice does not wait idle for the checks. "Request systems accounts" (1) leads to "Account setup wait" (5), and "Order loupes, uniform and personal kit" (3) and "Plan the induction week" (2) can happen straight after signing. "Systems and prescribing access tested" (1) waits for the accounts and for "Cleared to start". "Induction week: policies and safety" (5) waits for the clearance, the plan and the kit. "Meet the team and tour the surgery" (1) starts 1 working day into it and "Learn the practice systems" (3) starts 2 working days into it, once the access is tested.
The patient side is built early. "Choose patients for the associate's list" (3) and "Book patients for the supervised sessions" (4) run during the waits, so the first sessions are full. "First supervised sessions with a mentor" (10) waits for the induction, the tour, the systems and the booked patients. Then "Mentor reviews the first cases" (2), "Reduced-load sessions with a mentor on call" (10) and "Ramp to full sessions" (15) must follow in order, with "Solo sessions confirmed" as a milestone. "Open the diary to new patients in steps" (8) starts 2 working days into the reduced-load sessions. "Check case mix and list size" (3) and "Gather mentor and patient feedback" (2) lead to "90-day review held". Durations are illustrative.
A timeline schedules the onboarding. It does not decide when an associate is ready to work alone, and it does not replace the practice's own supervision rules. For the plan of a clinician joining a veterinary group, see /templates/new-clinician-onboarding-gantt-chart, and for the first-day steps of a patient, see /templates/dental-new-patient-examination-process.
What this flowchart covers
In this template
- Five groups, Contract and checks, Systems and kit, Induction, Supervised sessions and Patient list, with 24 tasks and three milestones: "Contract signed", "Cleared to start" and "Solo sessions confirmed".
- Two check waits that join: "Registration and indemnity checks" and "Reference and background checks" both lead to "Cleared to start".
- A staged ramp: "First supervised sessions with a mentor", "Reduced-load sessions with a mentor on call" and "Ramp to full sessions" in order.
- A patient list built alongside: "Choose patients for the associate's list", "Book patients for the supervised sessions" and "Open the diary to new patients in steps".
- A close with "Check case mix and list size", "Gather mentor and patient feedback" and "90-day review held".
When to use this template
- You are bringing in an associate and want the practice to see how long checks, induction and supervision will take.
- You want to know when the associate's own list can start to fill, and what limits it.
- You need the mentor's time to show up in the plan as sessions, not as a vague commitment.
- You onboard associates regularly and want one plan to resize for each.
The plan, task by task
Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.
| # | Task | Group | Working days | Depends on |
|---|---|---|---|---|
| 1 | Agree the offer and contract terms | Contract and checks | 5 | |
| 2 | Contract signed | Contract and checks | Milestone | 1 |
| 3 | Registration and indemnity checks | Contract and checks | 10 | 2 |
| 4 | Reference and background checks | Contract and checks | 12 | 2 |
| 5 | Cleared to start | Contract and checks | Milestone | 3, 4 |
| 6 | Request systems accounts | Systems and kit | 1 | 2 |
| 7 | Account setup wait | Systems and kit | 5 | 6 |
| 8 | Order loupes, uniform and personal kit | Systems and kit | 3 | 2 |
| 9 | Systems and prescribing access tested | Systems and kit | 1 | 5, 7 |
| 10 | Plan the induction week | Induction | 2 | 2 |
| 11 | Induction week: policies and safety | Induction | 5 | 5, 8, 10 |
| 12 | Meet the team and tour the surgery | Induction | 1 | 11SS+1 |
| 13 | Learn the practice systems | Induction | 3 | 9, 11SS+2 |
| 14 | Choose patients for the associate's list | Patient list | 3 | 10 |
| 15 | Book patients for the supervised sessions | Patient list | 4 | 14 |
| 16 | First supervised sessions with a mentor | Supervised sessions | 10 | 11, 12, 13, 15 |
| 17 | Mentor reviews the first cases | Supervised sessions | 2 | 16 |
| 18 | Reduced-load sessions with a mentor on call | Supervised sessions | 10 | 17 |
| 19 | Ramp to full sessions | Supervised sessions | 15 | 18 |
| 20 | Solo sessions confirmed | Supervised sessions | Milestone | 19 |
| 21 | Open the diary to new patients in steps | Patient list | 8 | 18SS+2 |
| 22 | Check case mix and list size | Patient list | 3 | 19, 21 |
| 23 | Gather mentor and patient feedback | Supervised sessions | 2 | 19 |
| 24 | 90-day review held | Supervised sessions | 1 | 22, 23 |
How it works
Fix the start
Give "Agree the offer and contract terms" a fixed Start. If the associate has a known start date, give "Induction week: policies and safety" a fixed Start as well. The plan is scheduled forward from the earliest fixed Start, and a conflict flag shows when the checks cannot finish in time.
Replace the check waits
Set "Registration and indemnity checks" and "Reference and background checks" from what the bodies and referees tell you. They run side by side, so only the longer one sets "Cleared to start".
Set the ramp
Resize "First supervised sessions with a mentor", "Reduced-load sessions with a mentor on call" and "Ramp to full sessions" to your own supervision plan. The ramp is the longest path in the illustrative numbers, so its length sets the review date.
Pace the list build
Change the 2-day start-to-start link on "Open the diary to new patients in steps" to when the associate may take new patients, and size the task to how many you want to add.
Add owners, share and export
Put the mentor and the practice manager in People against their tasks, share the chart as a link with the associate, and export a PDF or PNG for the personnel file.
Frequently asked questions
Does the plan decide when the associate may work alone?
No. It shows "Solo sessions confirmed" after the ramp you set. Whether the associate is ready is a decision for the mentor and the practice owner.
How is this different from a general employee onboarding plan?
This one is built around supervised clinical sessions and a patient list that is built in steps. A general plan has neither. See /templates/employee-onboarding-gantt-chart for the general version.
Can the checks take longer than the plan shows?
Yes, and then "Cleared to start" and everything after it move. Check periods differ by country and employer, so enter the durations you are given and change them as they firm up.
Can I add a second mentor?
Yes. Add a parallel task such as sessions with a second mentor, link it from "Mentor reviews the first cases" and join it before "Ramp to full sessions". The chart does not level mentor time, so check overlaps yourself.