Decontamination room upgrade Gantt chart template: lead times, validation

An editable Gantt chart for upgrading a dental decontamination room: layout, equipment orders with lead times, building work, installation, validation runs, staff training and handback, with an interim arrangement.

Use this template

What the decontamination room upgrade gantt chart template: lead times, validation process is

An upgrade of a decontamination room has two clocks. One is the supplier's lead time for the washer-disinfector and the steriliser. The other is the building work, which cannot finish without that equipment. A timeline helps because it shows which clock is the slow one in your numbers, and how long the practice has to run on an interim arrangement while the room is out of use.

This template has five groups: Design and approval, Equipment orders, Building work, Validation and Staff and interim cover. It has 24 tasks and three milestones, and a total length of 59 working days in the illustrative numbers. "Survey the current room and workflow" (3 working days) is the only starting task. It leads to "Draft the layout with dirty-to-clean flow" (4), "Review the layout with the decontamination lead" (2) and the milestone "Layout agreed". That gate opens three paths: equipment, building quotes and the interim arrangement.

Equipment is the long path. "Choose the washer-disinfector and steriliser" (4) and "Place the equipment orders" (1) lead to two waits, "Washer-disinfector lead time" (30) and "Steriliser and bench lead time" (20). "Equipment delivered" needs both. Building work starts when the room can be closed: "Strip out the old room" (3) waits for "Get builder quote and dates" (5) and "Set up the interim arrangement" (3). "Plumbing and electrics first fix" (5) comes next, and "Drainage and ventilation" (4) starts 2 working days into it. Then "Surfaces and flooring" (4) and "Fit benches and sinks" (3) follow. In the illustrative numbers the building work finishes well before the equipment arrives, so "Install and connect the equipment" (3) is held by "Equipment delivered", and the room sits ready and unused until then. Shorten the lead time or start the building later, and the picture changes.

After installation the plan turns to proof. "Installation checks" (2) and "Commissioning and test runs" (4) come first, and "Train staff on the new equipment" (3) starts 1 working day into commissioning. "Validation runs with test loads" (3) and "Review the validation records" (2) lead to "Room cleared for use", which also waits for the training. "Hand the room back and end the interim arrangement" (1) closes the plan. What validation must cover, how often it is repeated and who may sign it off differ by country and by the equipment, so the plan holds your durations and leaves the requirements to you. All durations are illustrative.

A timeline schedules the project. It does not decide whether the room meets any standard, and it does not replace the manufacturer's or your regulator's instructions. For the routine this room supports, see /templates/dental-instrument-decontamination-process. For the same lead-time logic in a different setting, see /templates/equipment-installation-gantt, and for planning the downtime itself, see /guides/surgery-downtime-gantt-chart.

What this flowchart covers

In this template

  • Five groups, Design and approval, Equipment orders, Building work, Validation and Staff and interim cover, with 24 tasks and three milestones: "Layout agreed", "Equipment delivered" and "Room cleared for use".
  • Two lead-time waits that join: "Washer-disinfector lead time" and "Steriliser and bench lead time" both lead to "Equipment delivered".
  • Building work in a fixed order, with "Drainage and ventilation" starting 2 working days into "Plumbing and electrics first fix".
  • An interim arrangement that starts before "Strip out the old room" and ends only at "Hand the room back and end the interim arrangement".
  • A validation block after installation, with "Train staff on the new equipment" overlapping "Commissioning and test runs".

When to use this template

  • You are upgrading or moving a decontamination room and want to know how long the practice runs on an interim arrangement.
  • Equipment has long and uncertain lead times and you want to see how much they decide the handback date.
  • You need to decide when to place the orders so the room is not built and then left waiting.
  • You want the builder, the supplier and the clinical team to see the same order of work.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Survey the current room and workflowDesign and approval3
2Draft the layout with dirty-to-clean flowDesign and approval41
3Review the layout with the decontamination leadDesign and approval22
4Layout agreedDesign and approvalMilestone3
5Choose the washer-disinfector and steriliserEquipment orders44
6Place the equipment ordersEquipment orders15
7Washer-disinfector lead timeEquipment orders306
8Steriliser and bench lead timeEquipment orders206
9Equipment deliveredEquipment ordersMilestone7, 8
10Get builder quote and datesBuilding work54
11Set up the interim arrangementStaff and interim cover34
12Strip out the old roomBuilding work310, 11
13Plumbing and electrics first fixBuilding work512
14Drainage and ventilationBuilding work413SS+2
15Surfaces and flooringBuilding work413, 14
16Fit benches and sinksBuilding work315
17Install and connect the equipmentBuilding work39, 16
18Installation checksValidation217
19Commissioning and test runsValidation418
20Train staff on the new equipmentStaff and interim cover319SS+1
21Validation runs with test loadsValidation319
22Review the validation recordsValidation221
23Room cleared for useValidationMilestone20, 22
24Hand the room back and end the interim arrangementStaff and interim cover123

How it works

  1. Replace the lead times

    Set "Washer-disinfector lead time" and "Steriliser and bench lead time" from the quotes you hold. Check whether "Equipment delivered" or the building work is later in your numbers.

  2. Fix the dates that are real

    Give "Survey the current room and workflow" a fixed Start. If the builder has given you a closure date, give "Strip out the old room" a fixed Start as well. The plan is scheduled forward from the earliest fixed Start, and a conflict flag shows the earliest date the dependencies allow.

  3. Resize the building work

    Set the durations from the builder's programme. Keep the 2-day start-to-start link on "Drainage and ventilation" only if the trades overlap on site.

  4. Resize validation and training

    Set "Validation runs with test loads" and "Review the validation records" to what the equipment supplier and your own procedure require. Check that "Train staff on the new equipment" fits inside the commissioning window.

  5. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with the builder and the supplier, and export a PDF or PNG for the project file.

Frequently asked questions

Can the chart tell me when the equipment will arrive?

No. It shows the lead times you enter and moves "Equipment delivered" and everything after it. When the supplier changes the date, change the lead-time task.

Does the plan show how long validation must take?

No. Validation requirements differ by country and by equipment. Enter the durations your own procedure and supplier give you, and keep the requirements as tasks or notes.

What if the building work is slower than the equipment?

Lengthen the building tasks. When they pass the lead times, "Install and connect the equipment" is held by "Fit benches and sinks" instead, and the schedule shows it.

Can I keep the room open while the work is done?

This template assumes the room is out of use from "Strip out the old room" until "Room cleared for use", with an interim arrangement beside it. If you phase the work, split the building tasks and move the interim end earlier.

Part of

QueryChart features for this process

Use this template

More in Operations process templates

Browse all Operations process templates