Dental surgery refit Gantt chart template: chair delivery sets the date
An editable Gantt chart for refitting one dental treatment room: chair and cabinetry lead times, plumbing and electrics, compressor and suction, commissioning, staff familiarisation and the first patients, with dependencies.
What the dental surgery refit gantt chart template: chair delivery sets the date process is
A surgery refit looks like building work, but its date is usually set by an order. The chair and delivery unit are made to order and arrive when the supplier says, while the plumber and electrician can only work in a fixed sequence in a room that has no patients in it. A timeline shows which of those two things is really deciding the reopening date, and it shows it before you commit to a closure.
This template has five groups: Design and orders, Lead times, Building works, Equipment and commissioning, and Staff and patients. It has 22 tasks and four milestones, and a total length of 47 working days in the illustrative numbers. "Agree scope and room layout" (3 working days) is the only starting task. It leads to "Order the chair and delivery unit" (1) and "Order the cabinetry" (1), and to "Close the room and move bookings" (1). The two lead times, "Chair and delivery unit lead time" (30) and "Cabinetry lead time" (20), are plain waits: nobody on your side is working on them, and the plan treats them as exactly that.
The building path runs beside the waits. "Strip out old fittings" (3) is followed by "First fix plumbing and electrics" (5) and "Plaster and decorate" (4). "Install compressor and suction" (3) starts 3 working days into the first fix with a start-to-start link, because the pipe and cable runs can begin before the first fix is complete. In the illustrative numbers the decorating is finished on day 16, but "Fit the cabinetry" (3) has to wait for the cabinetry lead time, so "Room ready for equipment" arrives on day 27. That leaves the room waiting for the chair: "Chair delivered" arrives on day 34, and everything after it is a chain. "Fit the chair and delivery unit" (2), "Connect and test services" (2), "Commission the equipment" (2) and "Clean down and infection control check" (1) lead to "Room signed off for use".
The last group is the reopening. "Staff familiarisation session" (1) follows commissioning, "Reopen bookings for the room" (1) follows the sign-off, and "First patients seen in the room" needs all three. "Snagging after the first week" (5) closes the plan. Every duration is illustrative. Replace them with the lead times your suppliers quote and the days your trades give you. If the chair slips, change one task and watch the reopening move.
A timeline schedules the work. It does not check electrical, gas, radiation or infection control requirements, which differ by country and by premises, and it does not replace the sign-offs your regulator or your installer requires. Keep each of those as a task or a note with its own owner. For related plans, see /templates/equipment-installation-gantt for a general install, /templates/dental-new-patient-examination-process for the flowchart of what happens in the room once it reopens, and /guides/surgery-downtime-gantt-chart for how to read the days a room is out of use.
What this flowchart covers
In this template
- Five groups, Design and orders, Lead times, Building works, Equipment and commissioning and Staff and patients, with 22 tasks and four milestones: "Chair delivered", "Room ready for equipment", "Room signed off for use" and "First patients seen in the room".
- Two supplier waits as plain tasks: "Chair and delivery unit lead time" (30 working days) and "Cabinetry lead time" (20), each starting only when its order task has been placed.
- A start-to-start link that overlaps trades: "Install compressor and suction" starts 3 working days into "First fix plumbing and electrics".
- Two joins that show the real constraint: "Fit the cabinetry" waits for "Plaster and decorate" and the cabinetry lead time, and "Fit the chair and delivery unit" waits for "Room ready for equipment" and "Chair delivered".
- The reopening: "Staff familiarisation session", "Reopen bookings for the room" and "First patients seen in the room", followed by "Snagging after the first week".
When to use this template
- You are refitting a treatment room and need to know how many working days it will be out of use.
- A chair or cabinetry order has a long lead time and you want to see whether it, or the building work, decides the reopening date.
- You need to tell the team and patients when the room will be back and want a plan that moves when a delivery date moves.
- You run more than one surgery and want the same refit sequence resized for each room.
The plan, task by task
Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.
| # | Task | Group | Working days | Depends on |
|---|---|---|---|---|
| 1 | Agree scope and room layout | Design and orders | 3 | |
| 2 | Order the chair and delivery unit | Design and orders | 1 | 1 |
| 3 | Order the cabinetry | Design and orders | 1 | 1 |
| 4 | Chair and delivery unit lead time | Lead times | 30 | 2 |
| 5 | Cabinetry lead time | Lead times | 20 | 3 |
| 6 | Chair delivered | Lead times | Milestone | 4 |
| 7 | Close the room and move bookings | Building works | 1 | 1 |
| 8 | Strip out old fittings | Building works | 3 | 7 |
| 9 | First fix plumbing and electrics | Building works | 5 | 8 |
| 10 | Plaster and decorate | Building works | 4 | 9 |
| 11 | Fit the cabinetry | Building works | 3 | 5, 10 |
| 12 | Room ready for equipment | Building works | Milestone | 11 |
| 13 | Install compressor and suction | Equipment and commissioning | 3 | 9SS+3 |
| 14 | Fit the chair and delivery unit | Equipment and commissioning | 2 | 6, 12 |
| 15 | Connect and test services | Equipment and commissioning | 2 | 13, 14 |
| 16 | Commission the equipment | Equipment and commissioning | 2 | 15 |
| 17 | Clean down and infection control check | Equipment and commissioning | 1 | 16 |
| 18 | Room signed off for use | Equipment and commissioning | Milestone | 17 |
| 19 | Staff familiarisation session | Staff and patients | 1 | 16 |
| 20 | Reopen bookings for the room | Staff and patients | 1 | 18 |
| 21 | First patients seen in the room | Staff and patients | Milestone | 18, 19, 20 |
| 22 | Snagging after the first week | Staff and patients | 5 | 21 |
How it works
Fix the dates that are real
Give "Agree scope and room layout" a fixed Start on the day you begin. If the installer has given you a booked day for fitting, give "Fit the chair and delivery unit" a fixed Start on it. The plan starts on the earliest fixed Start and is scheduled forward, so a conflict flag on the fitting task shows the earliest date its dependencies allow.
Enter the quoted lead times
Set "Chair and delivery unit lead time" and "Cabinetry lead time" from your suppliers' written quotes. Check which of "Room ready for equipment" and "Chair delivered" arrives later, because that one is deciding your reopening.
Resize the building works
Set "Strip out old fittings", "First fix plumbing and electrics" and "Plaster and decorate" from your trades' own estimates, and adjust the start-to-start link on "Install compressor and suction" to when that work can really begin.
Give commissioning its time
Set "Connect and test services", "Commission the equipment" and "Clean down and infection control check" to what your installer and your practice procedures need. Add a task for any inspection your own rules require.
Plan the reopening
Decide who needs "Staff familiarisation session" and when "Reopen bookings for the room" should be released, so the diary does not fill before the date is firm.
Add owners, share and export
Put the person responsible for each task in People, share the chart as a link with the practice manager and the installer, and export a PDF or PNG for the team room.
Frequently asked questions
Can the chart tell me when the chair will arrive?
No. It shows the duration you enter for "Chair and delivery unit lead time" and moves the dates after it. When the supplier confirms a new date, change that one task and "Chair delivered", the fitting and the reopening move with it.
How do I check the refit fits inside a planned closure?
Give "Agree scope and room layout" a fixed Start and "Fit the chair and delivery unit" a fixed Start on the booked day. The chart schedules forward from the earliest fixed Start. If the lead times and the building work cannot finish by then, the fitting task shows a conflict and the earliest date its dependencies allow.
Does the plan cover electrical or radiation requirements?
No. It schedules the work. Requirements for electrical, gas, compressed air or radiation differ by country and by premises, so keep them as tasks or notes with your own durations, and follow the guidance of your installer and regulator.
What if the cabinetry is late but the chair is on time?
Lengthen "Cabinetry lead time" and see whether "Room ready for equipment" now arrives after "Chair delivered". If it does, the cabinetry has become the task that decides the date. See /guides/surgery-downtime-gantt-chart for reading downtime through a plan.
Can I use it for a larger fit-out?
Yes, for a single room or a few. Add the rooms as further tasks in the groups you need. For a whole new site, see /templates/clinic-opening-gantt-chart.