How to plan a dental surgery refit on a Gantt chart
Plan a dental surgery refit on a Gantt chart: chair and cabinetry lead times as plain waits, building works, services and commissioning, staff familiarisation and the day the first patients are seen in the room.
A treatment room that is being refitted earns nothing until it is signed off, and the chair often takes the longest to arrive. This guide shows how to put the lead times, the building works and the reopening on a Gantt chart and see how many days the room is out of use.
The short version
- Fix the Start of the first task and let the later dates follow from the dependencies.
- Give the chair and the cabinetry each a plain wait task with the supplier's quoted duration.
- Add a milestone for the chair delivery so the fitting task cannot start before it.
- Use a start-to-start link so the compressor work starts while the first fix is still running.
- Turn on Critical path to see whether the chair or the building works set the reopening day.
Treat the chair delivery as a wait and count the days the room is closed
A surgery refit has two clocks. The first is the building work: strip out, services, decorating and cabinetry, done by trades who work in order. The second is the equipment, which is made and shipped by a supplier on a lead time the practice does not control. The room reopens on the later of the two, and every day between the closure and the first patient is a day with one chair fewer.
A Gantt chart in QueryChart schedules forward from the earliest fixed Start. Give "Agree scope and room layout" a fixed Start on the day you begin. The two orders, "Order the chair and delivery unit" and "Order the cabinetry", follow the layout. Each lead time is a plain wait task with a duration you replace with the supplier's quote. "Chair delivered" is a milestone, so the fitting task can only start when the chair has arrived.
The example below is the dental surgery refit template: 22 tasks in five groups. In it the room closes on day 4 and the building works run beside the waits. The cabinetry lead time ends on day 24, so "Fit the cabinetry" starts on day 25 and "Room ready for equipment" falls on day 27. The chair wait ends on day 34, which leaves the room empty for a week. A start-to-start link lets "Install compressor and suction" begin three days after the first fix starts. The durations are illustrative and you replace them with your own.
After the example, a flowchart shows the process the new room joins once it is in use: instrument decontamination. A Gantt chart says when the room is ready and cannot show the washing, packing and checking loops that each tray goes through afterwards. Durations in both charts are illustrative. Room design, services, infection control sign-off and the rules for reopening differ by country and by regulator, so the plan holds your durations and your own advisers decide what they are. A timeline schedules the work. It is not dental, medical or legal advice.
For waits and gaps in general see /guides/gantt-chart-buffer-time and /guides/gantt-chart-delays. For the chart itself, see /templates/dental-surgery-refit-gantt-chart, and for the process that handles the instruments in the new room, /templates/dental-instrument-decontamination-process.
A surgery refit, built in stages
Twenty-two tasks in five groups. Durations are illustrative working days. Open the spreadsheet panel to see the rows behind each stage.
Scope and the two orders
"Agree scope and room layout" (3 working days) leads to "Order the chair and delivery unit" (1) and "Order the cabinetry" (1), which run on day 4. Fix the Start of the first task on the day you begin.
The lead times
"Chair and delivery unit lead time" (30) and "Cabinetry lead time" (20) are plain waits that start on day 5 with illustrative durations. The cabinetry arrives on day 24 and "Chair delivered" is a milestone on day 34.
Building works
"Close the room and move bookings" (1) starts on day 4 beside the waits. "Strip out old fittings" (3), "First fix plumbing and electrics" (5) and "Plaster and decorate" (4) follow in order. "Fit the cabinetry" (3) waits for the cabinetry and for the decorating, so it starts on day 25 and "Room ready for equipment" falls on day 27.
Equipment and commissioning
"Install compressor and suction" (3) starts three days into the first fix. "Fit the chair and delivery unit" (2) needs the delivery, so it starts on day 35, and "Connect and test services" (2) and "Commission the equipment" (2) follow. "Clean down and infection control check" (1) leads to the milestone "Room signed off for use" on day 41.
Reopening
"Staff familiarisation session" (1) and "Reopen bookings for the room" (1) lead to the milestone "First patients seen in the room" on day 42. "Snagging after the first week" (5) ends on day 47. The longest chain is set by the chair wait, so the building works have a week of slack in this example.
The process the new surgery joins
Instrument decontamination as a flowchart. The Gantt chart says when the room is signed off and this chart shows how each tray is handled once patients are being seen.
Leaving the surgery
"Used instruments leave the surgery" leads to "Place instruments in a closed transport tray" and "Pre-clean to remove visible debris". "Washer-disinfector available and working?" sends a Yes to "Run the wash and disinfect cycle" and a No to "Wash by hand using the written method".
The cleanliness check
"Instruments clean and undamaged?" has three branches. Yes leads to wrapping, Still soiled sends the tray back to "Pre-clean to remove visible debris" and Damaged leads to "Withdraw the damaged instrument and tell the lead", which ends at "Instrument repaired or replaced".
Packing and the steriliser
"Wrap or pouch and label the packs" leads to "Load the steriliser and start the cycle". If "Cycle completed and indicators passed?" is No, the load goes to "Quarantine the load and look for the cause". A fault that cannot be fixed leads to "Stop using the steriliser and call for service". Your own written procedure sets what counts as a pass.
Records and storage
A pass leads to "Complete the load record" and "Store packs in a clean closed area". "Pack intact and in date?" sends a Yes to "Instruments ready for the next patient" and a No back to the pre-clean step.
How it works
Open the surgery refit chart
Open the template and replace each duration with what your builder, your equipment supplier and your own advisers tell you. Put the person responsible for each task in People.
Fix the first Start
Give "Agree scope and room layout" a fixed Start on the day you begin. The plan is scheduled forward, so every later date is a result of the chain until you fix one.
Set the lead times
Replace the durations of the chair and cabinetry waits with the supplier's quotes. Hover over a task to see the dates it produces.
Find what sets the reopening
Turn on Critical path in the View menu. If the chair wait is lit, ask the supplier about earlier delivery or choose a different model. If the building tasks are lit, look at the trade durations.
Count the days without the room
Read the dates of the closure task and the first patients milestone. The days between them are the days the practice has one surgery fewer, which is what the booking team needs to plan around.
Share the plan with the team
Share the chart as a link so the builder, the manager and the clinical team can see their part and add comments. Export a PDF for people who are not in the chart.
Mistakes to avoid
Closing the room before the chair is on its way
If the order is placed late, the room sits empty while the wait runs. Order first and let the closure follow the layout.
Treating a delivery as a task the practice does
A chair order is a wait. Give it a plain wait task with the supplier's duration so a late delivery shows up as a late reopening.
Reopening bookings without a milestone
If nothing marks the room as signed off, the front desk has no date to book against. End the build with one and release the bookings from it.
Using the template durations as facts
Trade times, lead times and commissioning are illustrative. Requirements for reopening differ by country and by regulator, and the chart is not advice.
Open the surgery refit Gantt chart
Open the template, fix the first Start and see whether the chair or the building works set the reopening day.
Related guides
Frequently asked questions
Can QueryChart work backwards from a reopening date?
No. Scheduling is forward only. Fix the Start of the first task, and fix the Start of the first patients milestone if a date is already agreed, then read the conflict flag to see whether the chain before it fits.
How do I show a chair that takes weeks to arrive?
Add a plain task for the wait and give it the supplier's duration. In the example the chair wait is 30 working days and the cabinetry wait is 20.
Can the compressor work start before the first fix is finished?
Yes. Link it to the first fix with a start-to-start dependency and a lag. In the example it starts three days after the first fix starts.
Can I paste my own refit plan?
Yes. Paste your table into the spreadsheet panel with one row per task and the group, duration and dependencies in columns. You can then edit it as a chart.