Referral partner network Gantt chart template: three agency waves

An editable Gantt chart for bringing referral agencies on board to a food bank in three waves: agreements, voucher stock, short training, pilot referrals and review, with each wave waiting on the last wave's pilot.

Use this template

What the referral partner network gantt chart template: three agency waves process is

A referral network grows safely when each group of agencies has shown that the process works before the next group starts. The cost is time: agreements take weeks to come back and a pilot needs enough days to produce referrals worth reviewing. A timeline helps because it shows what can be prepared early, such as sending the next wave's agreements, and what must wait for evidence.

This template has four groups: Shared preparation, Wave 1, Wave 2 and Wave 3. It has 20 tasks and three milestones, and a total length of 68 working days in the illustrative numbers. **Agree which agencies join in each wave** (2 working days) leads to **Prepare voucher stock, guidance and the training session** (5), which every wave uses, and to **Send agreements, wave 1** (3). Then **Wait for signed agreements, wave 1** (10) is a plain wait, followed by **Issue vouchers and run training, wave 1** (2), **Pilot referrals, wave 1** (10), **Review the wave 1 pilot** (2) and the gate **Wave 1 cleared**.

The waves overlap in one place only. **Send agreements, wave 2** starts 4 working days into **Pilot referrals, wave 1** with a start-to-start link, so the wave 2 agencies are signing while wave 1 is still being tested. After that the wave waits twice: **Wait for signed agreements, wave 2** runs on its own, and **Issue vouchers and run training, wave 2** needs both the signatures and **Wave 1 cleared**. That second join is the rule that each wave waits on the previous wave's pilot. Wave 3 repeats the pattern against **Pilot referrals, wave 2** and **Wave 2 cleared**.

In the illustrative numbers the chain through the three pilots sets the end date, and the agreement waits are shorter than the pilots, so they do not delay anything. If agreements are slower than a pilot, the picture reverses and the wait becomes the driver. **Review the wave 3 pilot and the whole network** (3) leads to the last milestone, **Network in place**. All durations are illustrative: replace them with your own.

A timeline schedules the work. It does not decide which agencies may refer or what a referral must contain, which are your own rules and differ between organisations and countries. See /templates/food-bank-client-registration-and-referral-process for the flowchart of one referral, /templates/food-bank-satellite-hub-gantt-chart for opening another pick-up point and /guides/gantt-chart-dependencies for start-to-start links.

What this flowchart covers

In this template

  • Four groups, Shared preparation, Wave 1, Wave 2 and Wave 3, with 20 tasks and three milestones: "Wave 1 cleared", "Wave 2 cleared" and "Network in place".
  • A shared start: "Agree which agencies join in each wave" and "Prepare voucher stock, guidance and the training session" feed every wave.
  • A gate between waves: "Issue vouchers and run training, wave 2" needs both "Wait for signed agreements, wave 2" and "Wave 1 cleared", and wave 3 repeats it.
  • Early agreements: "Send agreements, wave 2" and "Send agreements, wave 3" start 4 working days into the previous wave's pilot.
  • A review at the end of each pilot, "Review the wave 1 pilot", "Review the wave 2 pilot" and "Review the wave 3 pilot and the whole network".

When to use this template

  • You are adding referral agencies, such as health visitors, housing teams or advice centres, in groups.
  • You want to see how long each pilot holds up the next wave and whether agreements can be sent ahead.
  • You need to show trustees or a funder how long the network takes to build.
  • You expect some agencies to be slow to sign and want to see whether it matters.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Agree which agencies join in each waveShared preparation2
2Prepare voucher stock, guidance and the training sessionShared preparation51
3Send agreements, wave 1Wave 131
4Wait for signed agreements, wave 1Wave 1103
5Issue vouchers and run training, wave 1Wave 122, 4
6Pilot referrals, wave 1Wave 1105
7Review the wave 1 pilotWave 126
8Wave 1 clearedWave 1Milestone7
9Send agreements, wave 2Wave 236SS+4
10Wait for signed agreements, wave 2Wave 2109
11Issue vouchers and run training, wave 2Wave 228, 10
12Pilot referrals, wave 2Wave 21011
13Review the wave 2 pilotWave 2212
14Wave 2 clearedWave 2Milestone13
15Send agreements, wave 3Wave 3312SS+4
16Wait for signed agreements, wave 3Wave 31015
17Issue vouchers and run training, wave 3Wave 3214, 16
18Pilot referrals, wave 3Wave 31017
19Review the wave 3 pilot and the whole networkWave 3318
20Network in placeWave 3Milestone19

How it works

  1. Fix the start

    Give "Agree which agencies join in each wave" a fixed Start on the day you begin. The plan is scheduled forward from the earliest fixed Start.

  2. Set the waves

    Rename the wave groups if you use different names, and move agencies between waves by editing the tasks you send them. Remove wave 3 if you plan two.

  3. Replace the agreement waits

    Set each "Wait for signed agreements" task to how long agencies usually take. If agreements are slower than a pilot, they become the date driver.

  4. Resize the pilots

    Set each "Pilot referrals" task to enough days for the referrals you need to see before you review, and set the review tasks to your own meeting rhythm.

  5. Decide how early the next wave starts

    Change the 4-day start-to-start link on "Send agreements, wave 2" and "Send agreements, wave 3" to when you are happy to ask the next agencies to sign.

  6. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with partners, and export a PDF or PNG.

Frequently asked questions

Why wait for a pilot review before the next wave?

That is how this plan is set up, and you can change it. Remove the link from "Wave 1 cleared" to "Issue vouchers and run training, wave 2" if you want waves to run in parallel.

Can the chart show which agencies are in which wave?

The chart shows the waves as groups. Put the agency names in the task labels or in the notes of each wave's tasks.

Does the plan decide who can refer?

No. It schedules the work. Eligibility and referral rules are yours and differ by country and organisation, so keep them as tasks or notes.

What if one agency in a wave is late?

Lengthen that wave's "Wait for signed agreements" task to see the effect, or move the agency to the next wave.

Can I paste my own agency list?

Yes. Paste your table into the spreadsheet view and add the dependencies in the line column. There is no file upload.