Food bank satellite hub Gantt chart template: trial session and go-live review

An editable Gantt chart for opening a second food bank pick-up point in a host venue: host agreement wait, partner briefing, volunteer training, a trial session, a review and go-live.

Use this template

What the food bank satellite hub gantt chart template: trial session and go-live review process is

Opening a second pick-up point in a church hall, community centre or school is mostly a matter of agreement, with the building second. The host has to sign, referral partners have to know where to send people, volunteers have to be trained for a site that does not exist yet, and the whole thing has to be tried once before it is announced. A timeline helps because the opening is not the end of a chain of tasks. It is the result of a trial session and a decision.

This template has five groups: Host venue, Referral partners, Volunteers, Stock and kit and Trial and opening. It has 23 tasks and three milestones, and a total length of 36 working days in the illustrative numbers. "Shortlist host venues" (3 working days) is the only starting task, and it leads through "Visit venues and agree terms in principle" (3) and "Send the host agreement for signature" (1) to "Wait for the host to sign" (10). "Host agreement signed" is the first milestone, and four groups of work wait for it.

After the signature, the work fans out. "Brief referral partners on the new pick-up point" (2) leads to "Agree how referrals reach the hub and update the form" (3), which starts one working day into the briefing, then "Wait for partners to confirm they can refer" (4). "Write the hub volunteer roles" (2) leads to "Recruit hub volunteers" (8), and "Train hub volunteers" (2) starts 5 working days into the recruiting, so the first recruits are trained while the rest are still being found. "Order shelving, crates and a label printer" leads to "Wait for the kit to arrive" (7), "Set up the hub" (2) and "Plan the first stock transfer" (2).

Everything meets at the milestone "Hub ready for trial". "Run a trial session" (1) and "Review the trial session" (2) lead to the milestone "Go-live decision". After the decision, "Fix the issues found in the trial" (3) and "Announce the opening to partners and clients" (2) run side by side, and "Go-live session" (1) waits for both. If the trial shows a problem that is too big to fix, add the extra work to the fix task and lengthen it. The chart has no loops. All durations are illustrative: replace them with what your host, partners and volunteers say they need.

A timeline schedules the work. It does not decide what a host agreement should contain, what training or checks your volunteers need, or who may be referred to a pick-up point. Those rules differ by country and by organisation, so keep them as tasks with their own owners. For related plans, see /templates/new-clinician-onboarding-gantt-chart for another plan built around training and a gate, /templates/food-bank-client-registration-and-referral-process for the flowchart of the referral steps and /templates/volunteer-recruitment-and-onboarding-process for the recruiting steps.

What this flowchart covers

In this template

  • Five groups, Host venue, Referral partners, Volunteers, Stock and kit and Trial and opening, with 23 tasks and three milestones: "Host agreement signed", "Hub ready for trial" and "Go-live decision".
  • A host wait with a gate behind it: "Wait for the host to sign" ends in "Host agreement signed", which four groups of work wait for.
  • Overlapping partner and volunteer work: "Agree how referrals reach the hub and update the form" starts one working day into the briefing and "Train hub volunteers" starts 5 working days into "Recruit hub volunteers".
  • A trial-session gate: "Run a trial session", "Review the trial session" and "Go-live decision" come before any announcement.
  • A short close: "Fix the issues found in the trial" and "Announce the opening to partners and clients" run side by side before "Go-live session".

When to use this template

  • You are adding a second pick-up point in a host venue and want to see which agreement or partner sets the opening date.
  • You want a trial session built into the plan so the opening follows a decision that someone has made.
  • You need to show a host, a funder or trustees how long each step takes and what has to be true before you announce.
  • You plan to open more than one hub and want one plan to resize each time.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Shortlist host venuesHost venue3
2Visit venues and agree terms in principleHost venue31
3Send the host agreement for signatureHost venue12
4Wait for the host to signHost venue103
5Host agreement signedHost venueMilestone4
6Plan the layout, storage and accessHost venue25
7Brief referral partners on the new pick-up pointReferral partners25
8Agree how referrals reach the hub and update the formReferral partners37SS+1
9Wait for partners to confirm they can referReferral partners48
10Write the hub volunteer rolesVolunteers25
11Recruit hub volunteersVolunteers810
12Train hub volunteersVolunteers211SS+5
13Order shelving, crates and a label printerStock and kit15
14Wait for the kit to arriveStock and kit713
15Set up the hubStock and kit26, 14
16Plan the first stock transferStock and kit215
17Hub ready for trialTrial and openingMilestone9, 12, 16
18Run a trial sessionTrial and opening117
19Review the trial sessionTrial and opening218
20Go-live decisionTrial and openingMilestone19
21Fix the issues found in the trialTrial and opening320
22Announce the opening to partners and clientsReferral partners220
23Go-live sessionTrial and opening121, 22

How it works

  1. Replace the host wait

    Set "Wait for the host to sign" to what the venue tells you, and add tasks of your own for anything the host must approve. Everything under "Host agreement signed" moves when you change it.

  2. Fix the dates that are real

    Give "Shortlist host venues" a fixed Start on the day you begin. If a venue has offered a particular opening day, give "Go-live session" a fixed Start on it. The plan is scheduled forward from the earliest fixed Start, so a conflict flag tells you the earliest date its dependencies allow.

  3. Size the partner and volunteer work

    Set "Wait for partners to confirm they can refer", "Recruit hub volunteers" and "Train hub volunteers" from what you know of your people. Adjust the start-to-start links to when you can really begin the next task.

  4. Give the trial its weight

    Set "Run a trial session" and "Review the trial session" to what you want to learn. Keep the "Go-live decision" milestone, so nothing is announced before someone has decided.

  5. Plan the fixes

    Set "Fix the issues found in the trial" from the problems trial sessions usually show at your sites, and keep it parallel to the announcement only if the fixes will not change the date.

  6. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with the host and partners, and export a PDF or PNG for the trustees.

Frequently asked questions

Can the chart tell me when the host will sign?

No. It shows the duration you enter for "Wait for the host to sign" and moves the dates after it. When the host gives you a date, change that task and "Host agreement signed" and everything after it moves with it.

What if the trial session goes badly?

Lengthen "Fix the issues found in the trial" and the dates for "Go-live session" move. If you need a second trial, add a second "Run a trial session" and "Review the trial session" pair before the decision. The chart has no loops, so each pass is its own pair of tasks.

Does it say who can be referred to the hub?

No. Who can be referred and how depends on your organisation and your partners. Keep your own rules as a task or a note, and use the chart for when the work happens.

Can I open two hubs at once?

Copy the chart and give each hub its own host wait and trial. They can share the volunteer recruiting if one pool serves both. For recruiting in waves, see /templates/volunteer-recruitment-drive-gantt-chart.

My trial needs real food. How do I plan it?

Plan the first stock transfer with "Plan the first stock transfer" and treat the details as your own tasks, because how stock is moved and stored depends on your rules and your area.