Food bank premises move Gantt chart template: fridge delivery sets the date

An editable Gantt chart for moving a food bank to new premises: keys and lease handover, racking and fridge lead times, the move on a closed day, cold-store restart and the reopening session.

Use this template

What the food bank premises move gantt chart template: fridge delivery sets the date process is

Most of a food bank move is waiting for other people. The landlord hands over the keys when the lease is done, the racking supplier delivers when the order reaches the front of its queue, and the fridge and freezer supplier usually has the longest lead time of all. The volunteers' work fits into those waits. A timeline shows which wait sets the reopening date and how much room the rest of the plan has.

This template has five groups: Premises, Equipment, Stock and cold chain, Move and Reopening. It has 24 tasks and four milestones, and a total length of 40 working days in the illustrative numbers. "Agree the move plan and budget with trustees" (3 working days) is the only starting task. It leads to "Order racking" and "Order fridges and freezers", then to "Wait for the racking delivery" (15) and "Wait for the fridge and freezer delivery" (25). In the illustrative numbers the fridge wait is the longest chain, so "Fridges and freezers delivered" sets the date for "Install and test fridges and freezers" (3), "Restart the cold store and log temperatures" (3) and "Cold store running".

The other waits fit inside it. "Wait for keys and lease handover" (10) leads to the milestone "Keys and lease handed over", then to "Survey and mark out the new layout" (2) and "Fit out electrics and flooring" (6). "Install racking" (3) needs both the fit-out and the racking delivery, and "Move on the closed day" (1) needs the racking installed, the transport booked and the shelves packed. "Run down stock before the move" (8) starts early and "Pack shelves and label boxes" (4) starts 4 working days into it with a start-to-start link, so packing begins while the shelves are still emptying.

The reopening group follows from the equipment. "Tell referral partners and clients the new address" (4) starts once the fridge delivery is known, because that is when the reopening date stops being a guess. "Run a test session with volunteers" (1) needs "Unpack and shelve dry stock" (3) and "Cold store running", and then "Reopening session" (1), the milestone "Food bank reopened" and "Review the first weeks at the new site" (3) follow. All durations are illustrative: replace them with the lead times your suppliers quote and the handover date your landlord gives you.

A timeline schedules the work. It does not decide what your lease says, what your insurer or council needs to see, or what your cold storage must meet. Those rules differ by country and by premises, so keep them as tasks with their own owners and put your own durations in the plan. For related plans, see /templates/fundraising-campaign-gantt-chart for the money side of a move, /templates/equipment-installation-gantt for installing kit with its own lead times, and /templates/food-bank-stock-rotation-and-expiry-process for the flowchart of how stock is handled once the doors open. For the longer explanation, see /guides/food-bank-relocation-gantt-chart.

What this flowchart covers

In this template

  • Five groups, Premises, Equipment, Stock and cold chain, Move and Reopening, with 24 tasks and four milestones: "Keys and lease handed over", "Fridges and freezers delivered", "Cold store running" and "Food bank reopened".
  • Three supplier and landlord waits as plain tasks: "Wait for keys and lease handover", "Wait for the racking delivery" and "Wait for the fridge and freezer delivery".
  • A move that starts packing early: "Pack shelves and label boxes" starts 4 working days into "Run down stock before the move", then "Move on the closed day" waits for the racking, the transport and the packing.
  • A cold chain path after the equipment arrives: "Install and test fridges and freezers", "Restart the cold store and log temperatures" and "Cold store running" before the test session.
  • A reopening group that waits for the delivery date: "Tell referral partners and clients the new address", "Run a test session with volunteers", "Reopening session" and "Review the first weeks at the new site".

When to use this template

  • You are moving a food bank, pantry or community larder to a new building and want to see which supplier decides the reopening date.
  • You need to give referral partners and clients a reopening date and want to know when it is safe to say one.
  • You depend on volunteers for the move itself and want to see how many days of packing and moving the plan really holds.
  • Trustees ask whether a closed day is enough and you want to show what has to be finished before it.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Agree the move plan and budget with trusteesPremises3
2Order rackingEquipment11
3Order fridges and freezersEquipment11
4Wait for the racking deliveryEquipment152
5Wait for the fridge and freezer deliveryEquipment253
6Wait for keys and lease handoverPremises101
7Keys and lease handed overPremisesMilestone6
8Survey and mark out the new layoutPremises27
9Fit out electrics and flooringPremises68
10Install rackingEquipment34, 9
11Fridges and freezers deliveredEquipmentMilestone5
12Install and test fridges and freezersEquipment39, 11
13Run down stock before the moveStock and cold chain81
14Book transport and volunteer moversMove31
15Pack shelves and label boxesMove413SS+4
16Move on the closed dayMove110, 14, 15
17Unpack and shelve dry stockMove310, 16
18Restart the cold store and log temperaturesStock and cold chain312, 16
19Cold store runningStock and cold chainMilestone18
20Tell referral partners and clients the new addressReopening411
21Run a test session with volunteersReopening117, 19
22Reopening sessionReopening120, 21
23Food bank reopenedReopeningMilestone22
24Review the first weeks at the new siteReopening323

How it works

  1. Replace the waits with real quotes

    Set "Wait for the racking delivery" and "Wait for the fridge and freezer delivery" to the lead times your suppliers give you, and "Wait for keys and lease handover" to the handover you have been told. These three tasks do most of the work of the plan.

  2. Fix the dates that are real

    Give "Agree the move plan and budget with trustees" a fixed Start on the day you begin. If you already have a closed day booked, give "Move on the closed day" a fixed Start on it. The plan is scheduled forward from the earliest fixed Start, so a conflict flag on the move task tells you the earliest date its dependencies allow.

  3. Size the fit-out and the move

    Set "Fit out electrics and flooring", "Install racking" and "Unpack and shelve dry stock" from what you have been quoted and how many volunteers you can call on. Adjust the 4-day start-to-start link on "Pack shelves and label boxes" to match how fast the shelves actually empty.

  4. Give the cold store its time

    Set "Install and test fridges and freezers" and "Restart the cold store and log temperatures" to the time your installer and your own checks need. Treat any storage requirement as a task or a note of your own, because the chart only holds your durations.

  5. Tell partners when the date is firm

    Keep "Tell referral partners and clients the new address" after "Fridges and freezers delivered", so the date you announce is one the plan supports.

  6. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with trustees and the volunteer lead, and export a PDF or PNG for the project file.

Frequently asked questions

Can the chart tell me when the fridges will arrive?

No. It shows the duration you enter for "Wait for the fridge and freezer delivery" and moves the dates after it. When the supplier confirms a delivery date, change that task and "Install and test fridges and freezers", "Cold store running" and "Food bank reopened" move with it.

We have a closed day already booked. How do I check it fits?

Give "Move on the closed day" a fixed Start on that date. The chart schedules forward from the earliest fixed Start, so if the racking, the packing or the transport cannot be ready by then, the task shows a conflict and the earliest date its dependencies allow.

Does it handle notice periods and lease terms?

No. Notice periods, lease terms and handover rules differ by country and by tenancy, and the plan only holds the durations you enter. Put the real figures from your own agreement into "Wait for keys and lease handover".

What if the racking arrives after the fridges?

Change "Wait for the racking delivery" and see which dates move. "Install racking" and everything that depends on it, including "Move on the closed day", moves, while the cold store path does not.

Can I use it for a smaller move?

Yes. Shorten the waits, remove the tasks you do not need and keep the milestones. For stock handling after the move, see /templates/food-bank-stock-rotation-and-expiry-process.