How to plan a food bank move on a Gantt chart
Plan a food bank move on a Gantt chart: keys, racking and fridge deliveries as plain waits, the move on a closed day, the cold store restart and the reopening session, with the date the fridges set.
A food bank can pack and move in a day, but it cannot reopen until the fridges and freezers are in and the cold store is running. This guide shows how to put the waits, the move day and the reopening on a Gantt chart and see which delivery sets the date.
The short version
- Fix the Start of the first task and let the later dates follow from the dependencies.
- Give the keys, the racking and the fridges each a plain wait task with the quoted duration.
- Add a milestone for the fridge delivery so the install task cannot start before it.
- Use a start-to-start link so packing starts while the stock is still being run down.
- Turn on Critical path to see whether the fridge delivery or the building work sets the reopening day.
Treat the keys and the deliveries as waits and find the one that sets the reopening
A food bank move has two kinds of work. The first is what the team and volunteers do: survey the new space, fit out, pack, move, unpack and run a test session. The second is what other people control: the landlord hands over the keys, the racking supplier delivers and the fridge and freezer supplier delivers, usually last. The food bank reopens on the later of the two chains, and the volunteers' work fits into the waits.
A Gantt chart in QueryChart schedules forward from the earliest fixed Start. Give "Agree the move plan and budget with trustees" a fixed Start on the day you begin. "Order racking" and "Order fridges and freezers" follow it, and each supplier's lead time is a plain wait task: "Wait for the racking delivery" and "Wait for the fridge and freezer delivery". Replace the durations with the quotes you get. "Fridges and freezers delivered" is a milestone, so the install task can only start once the delivery has arrived.
The example below is the food bank premises move template: 24 tasks in five groups and about 40 working days in its illustrative numbers. The keys wait ends on day 13, the racking is installed by day 24 and "Move on the closed day" falls on day 25. The fridges arrive on day 29, so "Restart the cold store and log temperatures" runs on days 33 to 35 and the reopening session is on day 37. "Pack shelves and label boxes" starts four days into "Run down stock before the move" through a start-to-start link. The durations are illustrative and you replace them with your own.
After the example, a flowchart shows a routine the food bank carries into the new building: the weekly stock rotation and expiry check. A Gantt chart says when the cold store is running and cannot show the decisions made about each near-date item once it is. Handover dates, lease terms and what a cold store must show before it is used differ by country and by local authority, so the plan holds your own durations and your own advisers decide the rest. A timeline schedules the work. It is not legal or food safety advice.
For waits and gaps in general see /guides/gantt-chart-buffer-time and /guides/gantt-chart-delays. For the chart itself see /templates/food-bank-premises-move-gantt-chart, for the routine in the new store see /templates/food-bank-stock-rotation-and-expiry-process, and for a plan with a fixed date see /guides/seasonal-collection-drive-gantt-chart.
A food bank move, built in stages
Twenty-four tasks in five groups. Durations are illustrative working days. Open the spreadsheet panel to see the rows behind each stage.
The plan and the two orders
"Agree the move plan and budget with trustees" (3 working days) leads to "Order racking" (1) and "Order fridges and freezers" (1), which run on day 4. Fix the Start of the first task on the day you begin.
The waits
"Wait for the racking delivery" (15), "Wait for the fridge and freezer delivery" (25) and "Wait for keys and lease handover" (10) are plain waits with illustrative durations. "Keys and lease handed over" is a milestone on day 13.
Fit out and installs
"Survey and mark out the new layout" (2) and "Fit out electrics and flooring" (6) run once the keys are in. "Install racking" (3) waits for the delivery and the fit out and ends on day 24. "Fridges and freezers delivered" falls on day 29, so "Install and test fridges and freezers" (3) runs on days 30 to 32.
Stock, the move and the cold store
"Run down stock before the move" (8) starts on day 4 and "Pack shelves and label boxes" (4) starts four days into it. "Move on the closed day" (1) falls on day 25 and "Unpack and shelve dry stock" (3) follows. "Restart the cold store and log temperatures" (3) waits for the fridges and ends with the milestone "Cold store running" on day 35.
Reopening
"Tell referral partners and clients the new address" (4) starts once the fridge delivery has a date. "Run a test session with volunteers" (1) falls on day 36 and "Reopening session" (1) on day 37, with "Food bank reopened" as the milestone. "Review the first weeks at the new site" (3) ends on day 40. The fridge delivery sets the longest chain, so the racking has a few days of slack in this example.
The routine the new store runs
The weekly stock rotation as a flowchart. The Gantt chart says when the cold store is running and this chart shows how near-date items are decided once the food bank is open.
The weekly check
"Weekly stock check of shelves and store" leads to "Rotate stock so the earliest dates sit at the front". "Any item at or near its date?" sends a No to "Record items, quantities and the decision" and a Yes to "Pull near-date and past-date items to the review table".
Doubtful items
"Packaging damaged or condition in doubt?" has three branches. Yes leads to "Set aside as unfit and label it", No leads on to the use decision and Not sure leads to "Ask the manager for a decision". "Safe to keep in stock?" then sends a Yes onwards and a No to the set-aside step. Your own written procedure sets what counts as safe.
Use it, pass it on or dispose of it
"Can it be used in parcels in time?" sends a Yes to "Move to the front of the packing stock". A No leads to "Does a partner agency want it?", where a Yes leads to "Offer it and hand it over to the partner agency" and a No leads to "Dispose of it by the agreed route and weigh it".
Records and waste
"Record items, quantities and the decision" leads to "Add disposed weights to the waste report". "Waste rising for a type of food?" sends a Yes to "Adjust collection requests and ordering" and both branches end at "Stock checked and waste reported".
How it works
Open the premises move chart
Open the template and replace each duration with what your landlord, your suppliers and your own advisers tell you. Put the person responsible for each task in People.
Fix the first Start
Give "Agree the move plan and budget with trustees" a fixed Start on the day you begin. The plan is scheduled forward, so every later date is a result of the chain until you fix one.
Set the waits
Replace the durations of the keys, racking and fridge waits with the dates you have been given. Hover over a task to see the dates it produces.
Find what sets the reopening
Turn on Critical path in the View menu. If the fridge wait is lit, ask the supplier about earlier delivery or about a different model. If the building tasks are lit, look at the fit out durations.
Place the move day
Read the date of "Move on the closed day" and check that the racking is installed before it. Tell volunteers and partners the date once it no longer depends on a wait.
Share the plan with the team
Share the chart as a link so trustees, volunteers and the manager can see their part and add comments. Export a PDF for people who are not in the chart.
Mistakes to avoid
Fixing the move day before the deliveries
If the date is announced before the racking and the fridges have dates, a late delivery moves the reopening. Confirm the waits first and fix the move day once the chain fits.
Treating a delivery as a task the team does
A supplier order is a wait. Give it a plain wait task with the quoted duration so a late delivery shows up as a late reopening.
Reopening without a milestone for the cold store
If nothing marks the cold store as running, the reopening date rests on a guess. End the cold store work with a milestone and link the reopening to it.
Using the template durations as facts
Lead times, fit out and restart times are illustrative. Handover dates and what a cold store must show before use differ by country and by local authority, and the chart is not advice.
Open the food bank move Gantt chart
Open the template, fix the first Start and see whether the fridge delivery or the building work sets the reopening day.
Related guides
Frequently asked questions
Can QueryChart work backwards from a reopening date?
No. Scheduling is forward only. Fix the Start of the first task, and fix the Start of the reopening session if a date is already agreed, then read the conflict flag to see whether the chain before it fits.
How do I show a fridge delivery that takes weeks?
Add a plain task for the wait and give it the supplier's duration. In the example the fridge wait is 25 working days and the racking wait is 15.
Can packing start before the stock run down is finished?
Yes. Link them with a start-to-start dependency and a lag. In the example packing starts four days after the run down starts.
Can I paste my own move plan?
Yes. Paste your table into the spreadsheet panel with one row per task and the group, duration and dependencies in columns. You can then edit it as a chart.