School holiday food provision Gantt chart template: pre-order lead time

An editable Gantt chart for a holiday food provision scheme: partner venues confirmed, supply pre-order with a lead time, volunteer and venue rota, fixed scheme weeks and an end-of-scheme review, with dependencies.

Use this template

What the school holiday food provision gantt chart template: pre-order lead time process is

A holiday provision scheme has two kinds of date. The scheme weeks are fixed by the school calendar. Everything before them is a chain of waits: venues confirming, a supplier delivering, volunteers saying yes. A timeline helps because it shows which wait is the longest, so you know which call to make first. The plan is scheduled forward from the earliest fixed Start, so you check whether the earliest possible delivery fits the week you need.

This template has five groups: Venues, Supply, Volunteers and rota, Scheme days, and Review. It has 21 tasks and four milestones, and a total length of 48 working days in the illustrative numbers. **Agree the scheme weeks and budget** (2 working days) leads to **Approach partner venues** (3) and **Wait for venue confirmations** (8), then the gate **Partner venues confirmed**. Supply cannot start before that gate: **Estimate food quantities for each week** (2) depends on how many places each venue offers, then **Place the supply pre-order** (1) and **Wait for the supplier's delivery** (15) lead to **Food delivered**.

The supplier wait is the date driver. In the illustrative numbers the delivery lands on working day 31 and **Check and store the delivery** (2) ends on day 33, while the volunteer path is done on day 18. **Recruit holiday volunteers** (6) starts right after the weeks are agreed, **Draft the venue and volunteer rota** (3) starts 2 working days into it once venues are confirmed, and **Confirm cover and brief volunteers** (2) finishes with room to spare. If the supplier needs 15 days and the scheme starts sooner, the plan will show it, and the volunteers are not the problem.

The scheme itself is two weeks. **Pack and send week 1 food to venues** (2) waits for both the stored delivery and the confirmed rota, then **Scheme week 1** (5) runs. **Top up stock for week 2** (1) starts 3 working days into week 1 so you can see what is running short, and **Scheme week 2** (5) waits for both. **Scheme ends** is followed by **Return unused stock and count what is left** (2) and, in parallel, **Collect feedback from venues and volunteers** (3), both feeding **Hold the end-of-scheme review** and the final milestone **Scheme reviewed**. All durations are illustrative: use your supplier's real lead time.

The chart schedules the work. It does not decide who may be fed, what a venue must provide or how food must be stored, and those rules differ by country and local area. Keep them as tasks or notes with an owner. See also /templates/food-bank-parcel-packing-and-distribution-process, /templates/volunteer-shift-scheduling-and-cover-process and /guides/gantt-chart-dependencies.

What this flowchart covers

In this template

  • Five groups, Venues, Supply, Volunteers and rota, Scheme days and Review, with 21 tasks and four milestones: "Partner venues confirmed", "Food delivered", "Scheme ends" and "Scheme reviewed".
  • A supply chain with a lead time: "Estimate food quantities for each week", "Place the supply pre-order" and "Wait for the supplier's delivery" (15 working days in the illustrative plan).
  • A volunteer path that runs beside it: "Recruit holiday volunteers", "Draft the venue and volunteer rota" and "Confirm cover and brief volunteers".
  • Two scheme weeks, "Scheme week 1" and "Scheme week 2", with "Top up stock for week 2" starting during week 1.
  • A close in two parts, "Return unused stock and count what is left" and "Collect feedback from venues and volunteers", before "Hold the end-of-scheme review".

When to use this template

  • You run meals or food parcels during school holidays and need to see when the first venue call must happen.
  • Your supplier asks for an order weeks ahead and you want to check it against the date the scheme opens.
  • You plan with partner venues, such as community halls or churches, that confirm at different times.
  • You repeat the scheme every holiday and want one plan to resize.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Agree the scheme weeks and budgetVenues2
2Approach partner venuesVenues31
3Wait for venue confirmationsVenues82
4Partner venues confirmedVenuesMilestone3
5Estimate food quantities for each weekSupply24
6Place the supply pre-orderSupply15
7Wait for the supplier's deliverySupply156
8Food deliveredSupplyMilestone7
9Check and store the deliverySupply28
10Recruit holiday volunteersVolunteers and rota61
11Draft the venue and volunteer rotaVolunteers and rota34, 10SS+2
12Confirm cover and brief volunteersVolunteers and rota211
13Pack and send week 1 food to venuesScheme days29, 12
14Scheme week 1Scheme days513
15Top up stock for week 2Supply114SS+3
16Scheme week 2Scheme days514, 15
17Scheme endsScheme daysMilestone16
18Collect feedback from venues and volunteersReview316SS+3
19Return unused stock and count what is leftSupply217
20Hold the end-of-scheme reviewReview118, 19
21Scheme reviewedReviewMilestone20

How it works

  1. Fix the scheme weeks

    Give "Scheme week 1" a fixed Start on the first day of the scheme and "Agree the scheme weeks and budget" a fixed Start on the day you begin. The chart schedules forward, so a conflict flag on "Scheme week 1" shows the earliest date its dependencies allow. Compare that with the date you need.

  2. Put in the real lead time

    Set "Wait for the supplier's delivery" to what your supplier says. This task usually decides whether the scheme can open on time.

  3. Resize the venue wait

    Set "Wait for venue confirmations" to how long venues usually take to answer, and note which ones are likely to be late.

  4. Check the volunteer path

    Set "Recruit holiday volunteers" and "Draft the venue and volunteer rota" from your own pattern. If the rota is the longest path, add cover tasks.

  5. Resize the scheme and close

    Set the two scheme weeks, the top-up and the end-of-scheme tasks to your own length, and remove week 2 if the scheme is one week.

  6. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with venue leads, and export a PDF or PNG for funders.

Frequently asked questions

The scheme dates are fixed. How do I use a forward-only plan?

Give the first scheme task a fixed Start on the scheme date and the first task a fixed Start on the day you can begin. If the chain of waits cannot finish in time, the scheme task shows a conflict and the earliest date its dependencies allow.

Can the chart tell me when to place the order?

Not by reading back from the scheme date. It shows the earliest delivery date for the order date you set. Try different start dates until the delivery lands before the scheme.

Does it say how food must be stored or who is eligible?

No. Those rules differ by country and local area. Keep them as tasks or notes, and the plan will hold your own durations.

What if a venue drops out?

Lengthen "Wait for venue confirmations" or remove the venue from the estimate and shorten "Estimate food quantities for each week" and see which dates move.

Can I use it for one week?

Yes. Delete "Scheme week 2" and "Top up stock for week 2", and link "Scheme week 1" to "Scheme ends".

Part of

QueryChart features for this process

Use this template

More in Operations process templates

Browse all Operations process templates