Winter food appeal Gantt chart template: collection weekend and sorting surge
An editable Gantt chart for a seasonal donated-goods drive: supermarket and school permissions, collection points and posters, the volunteer rota for the collection weekend, the sorting surge and thank-yous.
What the winter food appeal gantt chart template: collection weekend and sorting surge process is
A food appeal collects donated goods rather than money, and that changes the plan. The goods are collected in other people's buildings, so supermarkets and schools have to say yes first. The goods are physical, so crates and bags have to arrive before anyone can collect, and every tin and packet has to be sorted and date-checked afterwards. A timeline shows how much of the work lands in the days after the collection weekend, which is the part that is easiest to underestimate.
This template has five groups: Permissions, Collection points, Volunteers, Collection weekend and Sorting and thanks. It has 23 tasks and three milestones, and a total length of 34 working days in the illustrative numbers. "Agree appeal goals and the wanted items list" (2 working days) is the only starting task. It leads to "Ask supermarkets for in-store collection" and "Ask schools to host collection crates", then to "Wait for supermarket replies" (10) and "Wait for school replies" (8). Those two waits end in the milestones "Supermarket slots confirmed" and "Schools confirmed", and nothing in the collection can be placed before them.
Preparation runs alongside the permission waits. "Order crates, trolleys and bags" leads to "Wait for crates and bags to arrive" (6), and "Design and print posters" (4) can start at once. "Put posters up and place school crates" (3) needs both and the school milestone. The volunteer path starts when the supermarkets confirm: "Build the weekend volunteer rota" (3), then "Recruit extra weekend volunteers" (6) with a start-to-start link, so recruiting starts one working day into the rota. "Brief volunteers and hand out vests" (1) then leads to "Collection weekend" (2).
Give "Collection weekend" a fixed Start on the weekend you have chosen, because that date does not move. The surge follows it. "Bring crates and store donations to the food bank" (2) waits for the weekend and for "Schools collect donations in class" (8), then "Sort and date-check donations" (5) starts one working day into it. "Write thank-you notes to stores and schools" (2) starts 2 working days into the sorting, "Donations shelved" is the milestone, and "Count totals and report to trustees" (2), "Send thank-you notes with the totals" (2) and "Appeal closed" finish the plan. All durations are illustrative: replace them with what stores, schools and your own volunteers tell you.
A timeline schedules the work. It does not decide which stores or schools will agree, how donated food must be stored or checked, or what the rules for a collection in your area are. Those differ by country and by organisation, so keep them as tasks or notes with their own owners. For related plans, see /templates/fundraising-campaign-gantt-chart for a plan that raises money rather than goods, /templates/food-bank-donation-intake-process for the flowchart of how donations are received and /templates/volunteer-shift-scheduling-and-cover-process for the rota itself. For the longer explanation, see /guides/seasonal-collection-drive-gantt-chart.
What this flowchart covers
In this template
- Five groups, Permissions, Collection points, Volunteers, Collection weekend and Sorting and thanks, with 23 tasks and three milestones: "Supermarket slots confirmed", "Schools confirmed" and "Donations shelved".
- Two permission waits that run side by side: "Wait for supermarket replies" and "Wait for school replies", each ending in a confirmation milestone.
- A collection weekend that is planned to a fixed date, preceded by "Build the weekend volunteer rota", "Recruit extra weekend volunteers" and "Brief volunteers and hand out vests".
- A school collection window: "Schools collect donations in class" (8 working days) must finish before the crates are brought to the food bank.
- A sorting surge with overlap: "Sort and date-check donations" starts one working day into the transfer and "Write thank-you notes to stores and schools" starts 2 working days into the sorting.
When to use this template
- You run a winter, harvest or back-to-school collection of donated goods and want to see when stores and schools must say yes.
- The collection weekend is fixed and you need to check whether the permissions, crates and volunteers can be ready by then.
- You want to show your volunteers and trustees how much work arrives after the weekend, in sorting and thank-yous.
- You run the same appeal every year and want one reusable plan to resize each time.
The plan, task by task
Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.
| # | Task | Group | Working days | Depends on |
|---|---|---|---|---|
| 1 | Agree appeal goals and the wanted items list | Permissions | 2 | |
| 2 | Ask supermarkets for in-store collection | Permissions | 1 | 1 |
| 3 | Wait for supermarket replies | Permissions | 10 | 2 |
| 4 | Ask schools to host collection crates | Permissions | 1 | 1 |
| 5 | Wait for school replies | Permissions | 8 | 4 |
| 6 | Supermarket slots confirmed | Permissions | Milestone | 3 |
| 7 | Schools confirmed | Permissions | Milestone | 5 |
| 8 | Order crates, trolleys and bags | Collection points | 1 | 1 |
| 9 | Wait for crates and bags to arrive | Collection points | 6 | 8 |
| 10 | Design and print posters | Collection points | 4 | 1 |
| 11 | Put posters up and place school crates | Collection points | 3 | 6, 7, 9, 10 |
| 12 | Schools collect donations in class | Collection points | 8 | 11 |
| 13 | Build the weekend volunteer rota | Volunteers | 3 | 6 |
| 14 | Recruit extra weekend volunteers | Volunteers | 6 | 13SS+1 |
| 15 | Brief volunteers and hand out vests | Volunteers | 1 | 13, 14 |
| 16 | Collection weekend | Collection weekend | 2 | 11, 15 |
| 17 | Bring crates and store donations to the food bank | Collection weekend | 2 | 12, 16 |
| 18 | Sort and date-check donations | Sorting and thanks | 5 | 17SS+1 |
| 19 | Donations shelved | Sorting and thanks | Milestone | 18 |
| 20 | Write thank-you notes to stores and schools | Sorting and thanks | 2 | 18SS+2 |
| 21 | Count totals and report to trustees | Sorting and thanks | 2 | 19 |
| 22 | Send thank-you notes with the totals | Sorting and thanks | 2 | 20, 21 |
| 23 | Appeal closed | Sorting and thanks | Milestone | 22 |
How it works
Fix the collection weekend
Give "Agree appeal goals and the wanted items list" a fixed Start on the day you begin, and give "Collection weekend" a fixed Start on the weekend you have chosen. The plan is scheduled forward from the earliest fixed Start, so a conflict flag on the weekend tells you the earliest date its dependencies allow.
Replace the permission waits
Set "Wait for supermarket replies" and "Wait for school replies" from how long the stores and schools usually take. If one store tends to answer late, make the wait longer rather than adding a loop.
Size the preparation
Set "Wait for crates and bags to arrive", "Design and print posters" and "Put posters up and place school crates" from your suppliers and your team. Adjust "Schools collect donations in class" to the real length of your school collection window.
Size the rota
Set "Build the weekend volunteer rota" and "Recruit extra weekend volunteers" to the time you really need, and check that "Brief volunteers and hand out vests" finishes before the weekend.
Plan the surge honestly
Set "Sort and date-check donations" from how many volunteers you will have on the days after, not from the weekend's enthusiasm. Keep any food safety check as a task of its own with the person who knows your local rules.
Add owners, share and export
Put the person responsible for each task in People, share the chart as a link with store contacts, school contacts and volunteers, and export a PDF or PNG for the trustees.
Frequently asked questions
How is this different from the fundraising campaign plan?
A fundraising campaign raises money and its waits are about donors and approvals. This plan collects donated goods, so its waits are about store and school permission, and most of its work lands after the collection weekend in sorting and shelving. For the money version, see /templates/fundraising-campaign-gantt-chart.
My collection weekend is fixed. How do I check everything fits?
Give "Collection weekend" a fixed Start on that date. The chart schedules forward from the earliest fixed Start, so if the permissions, crates or rota cannot be ready by then, the weekend task shows a conflict and the earliest date its dependencies allow.
What if a supermarket says no?
Shorten or remove the tasks that depend on that supermarket, or add a replacement store and its own wait. "Supermarket slots confirmed" and every date after it move when you change the wait.
Does the chart say how donated food must be handled?
No. It schedules the work only. How donations are checked, stored and recorded depends on where you are and who you are, so keep those rules as tasks or notes with their own owners.
Can I use it for a summer or holiday appeal?
Yes. Rename the tasks, change the school window and keep the milestones. For a scheme that feeds children in the holidays, see /templates/school-holiday-food-provision-gantt-chart.