Occupied-unit refurbishment Gantt chart template: tenants in place, unit by unit
An editable Gantt chart for refurbishing several rental units with tenants in place: consultation, access notices, contractor mobilisation, unit-by-unit works, snagging and tenant sign-off, with dependencies.
What the occupied-unit refurbishment gantt chart template: tenants in place, unit by unit process is
A refurbishment of empty units is limited by the work. A refurbishment with tenants in place is limited by the people in the units as well. They have to be told what will happen and given time to respond, each unit needs notice before the crew arrives, and the crew can only be in one unit at a time. A timeline lays these constraints next to each other, so you can see which unit is waiting for a notice and which is waiting for the crew.
This template has six groups: Tenants and notices, Contractor, Unit 1, Unit 2, Unit 3 and Handover. It has 22 tasks and three milestones, and a total length of 64 working days in the illustrative numbers. "Plan the works and the disruption for each unit" (3 working days) is the only starting task. It leads to the consultation path, "Write the tenant consultation letter" (2), "Consultation period" (8) and "Consider tenant feedback and adjust the plan" (3), ending at the milestone "Consultation closed". In parallel, "Tender and appoint the contractor" (6) and "Contractor mobilisation" (3) lead to the milestone "Ready to start unit 1".
The unit groups are where the plan differs from a normal renovation. "Access notice, unit 1" (4) starts after the consultation closes. "Access notice, unit 2" starts 3 working days into it, and "Access notice, unit 3" starts 3 working days into the unit 2 notice, so notices go out in a staggered line. The works are chained: "Works, unit 2" (10) waits for "Works, unit 1" (10), and "Works, unit 3" waits for unit 2, because the same crew does all three. "Snagging, unit 1" and "Snagging, unit 2" run behind their own works and do not hold the crew.
The Handover group closes the programme: "Tenant satisfaction check" (3) follows the last snagging task, then "Remedy snagging items" (4), "Tenant sign-off for each unit" (3), "Update asset and compliance records" (2) and the milestone "Refurbishment complete". If a tenant needs to be rehoused for a few days, add that as a task inside the unit's group rather than as a gap. How much notice you must give and what you must offer tenants differ by country and tenancy, so the plan holds your own durations and none of those rules. All durations here are illustrative.
The existing /templates/renovation-gantt covers a project where the building is empty. This one is for the case where it is not. For related plans, see /templates/tenant-move-in-inspection-process for checking a unit when work is finished and /templates/rental-maintenance-request-process for smaller repairs. For chaining one crew through several units, see /guides/gantt-chart-dependencies.
What this flowchart covers
In this template
- Six groups, Tenants and notices, Contractor, Unit 1, Unit 2, Unit 3 and Handover, with 22 tasks and three milestones: "Consultation closed", "Ready to start unit 1" and "Refurbishment complete".
- A consultation wait before any access notice: "Consultation period" (8 working days in the illustrative plan) sits between the letter and "Consider tenant feedback and adjust the plan".
- Staggered notices: "Access notice, unit 2" and "Access notice, unit 3" each start 3 working days into the previous unit's notice.
- One crew: "Works, unit 2" waits for "Works, unit 1", and "Works, unit 3" waits for "Works, unit 2".
- A handover that waits for all three units: "Remedy snagging items" needs the snagging of every unit and "Tenant satisfaction check" before it can start.
When to use this template
- You refurbish several rented units while tenants live in them.
- You need to show tenants or an owner how long each unit will be disrupted and in what order.
- You want to test whether a second crew would shorten the programme more than a shorter notice period would.
- You are comparing a unit-by-unit programme with doing a whole block at once.
The plan, task by task
Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.
| # | Task | Group | Working days | Depends on |
|---|---|---|---|---|
| 1 | Plan the works and the disruption for each unit | Tenants and notices | 3 | |
| 2 | Write the tenant consultation letter | Tenants and notices | 2 | 1 |
| 3 | Consultation period | Tenants and notices | 8 | 2 |
| 4 | Consider tenant feedback and adjust the plan | Tenants and notices | 3 | 3 |
| 5 | Consultation closed | Tenants and notices | Milestone | 4 |
| 6 | Tender and appoint the contractor | Contractor | 6 | 1 |
| 7 | Contractor mobilisation | Contractor | 3 | 6 |
| 8 | Ready to start unit 1 | Contractor | Milestone | 5, 7 |
| 9 | Access notice, unit 1 | Unit 1 | 4 | 5 |
| 10 | Works, unit 1 | Unit 1 | 10 | 8, 9 |
| 11 | Snagging, unit 1 | Unit 1 | 2 | 10 |
| 12 | Access notice, unit 2 | Unit 2 | 4 | 9SS+3 |
| 13 | Works, unit 2 | Unit 2 | 10 | 10, 12 |
| 14 | Snagging, unit 2 | Unit 2 | 2 | 13 |
| 15 | Access notice, unit 3 | Unit 3 | 4 | 12SS+3 |
| 16 | Works, unit 3 | Unit 3 | 10 | 13, 15 |
| 17 | Snagging, unit 3 | Unit 3 | 2 | 16 |
| 18 | Tenant satisfaction check | Handover | 3 | 17 |
| 19 | Remedy snagging items | Handover | 4 | 11, 14, 18 |
| 20 | Tenant sign-off for each unit | Handover | 3 | 19 |
| 21 | Update asset and compliance records | Handover | 2 | 20 |
| 22 | Refurbishment complete | Handover | Milestone | 21 |
How it works
Set the consultation
Change "Consultation period" to the time you will give tenants to respond. Treat it as a wait: it needs no effort from you, but nothing in the units can start until "Consultation closed".
Set the contractor path
Resize "Tender and appoint the contractor" and "Contractor mobilisation" from your procurement. The milestone "Ready to start unit 1" waits for both this path and the consultation.
Resize each unit
Set the notice, works and snagging tasks for each unit from its scope. Add a unit by copying the three tasks of a group and linking its works to the previous unit's works.
Fix the dates that are real
Give "Plan the works and the disruption for each unit" a fixed Start. If a unit must be finished before a new tenant arrives, give its works a fixed Start where the earlier work allows and check for a conflict flag. Scheduling runs forward from the earliest fixed Start.
Close out properly
Set the Handover tasks from the sign-off you really need, and keep "Refurbishment complete" behind them.
Add owners, share and export
Put the person responsible for each task in People, share the chart as a link with the contractor and the owner, and export a PDF or PNG to send to tenants.
Frequently asked questions
How is this different from the renovation template?
The renovation Gantt at /templates/renovation-gantt plans one project in an empty building. This plan adds a consultation, a separate access notice for each unit and one crew that moves between units.
Does the chart tell me what notice tenants are owed?
No. That differs by country and tenancy. The chart holds the durations you enter and moves the dates after them.
Can I add a fourth unit?
Yes. Copy the unit group's four tasks, link its notice to the previous notice with a start-to-start link and its works to the previous unit's works.
What if the works in one unit overrun?
Lengthen that unit's works task. Every later unit's works moves with it because of the crew link. See /guides/gantt-chart-critical-path for reading what a delay does to the end date.
Can I add a second crew?
Yes. Remove the link between the works tasks of two units, and give each its own predecessor from the contractor path. The chart will show the shorter programme.