How to plan the gap between two tenants on a Gantt chart
Plan a rental turnover on a Gantt chart: notice, move-out inspection, repairs, cleaning, relisting and referencing, so you can see which chain sets the empty weeks and where a fixed move-in date conflicts.
The weeks between one tenant leaving and the next arriving earn no rent, and most of them are set by a single chain of dependent tasks. This guide shows how to lay a turnover on a Gantt chart, read which chain sets the move-in date and decide what to start earlier.
The short version
- Fix the first task's Start on the day the notice arrives and, if the next tenant has a date, fix the move-in task's Start on it.
- Read the conflict flag and the finish date, because the plan is scheduled forward only.
- Turn on Critical path to see whether the repairs or the relisting stream sets the move-in date.
- Start relisting while repairs are under way with a start-to-start link, so the two streams overlap.
- Treat the notice, the contractor quotes and the referencing as waits whose durations you replace with real answers.
Find the chain that sets the empty weeks
A turnover looks like one job but it runs as two streams. In one stream the home is made ready: the move-out inspection, the repair scope, quotes, owner approval, the repairs, the cleaning and the safety checks. In the other stream the next tenant is found: the listing, the viewings, the referencing and the agreement. Either stream can be the slower one, and which it is changes from home to home.
A Gantt chart in QueryChart schedules forward. With no dates set, the plan starts on the day the chart is created and each task starts when what it depends on allows. To use it for a turnover, give the first task a fixed Start on the day the notice arrives. If a next tenant already has a date, give the last task a fixed Start on that date as well. The chain then produces a finish date, and the chart flags the fixed date if the chain cannot meet it.
The example below has five groups and 24 tasks. The **Notice period runs** task is a plain wait. The relisting stream does not wait for the repairs: **Advertise the home** starts one day after **Update the listing details and rent** with a start-to-start link, so viewings run while the home is still being repaired. Both streams meet at **Move-in day and key handover**, which waits for **Home ready to let** and for the tenancy to be signed and paid.
After the example, a flowchart shows what happens on the move-in day itself, which a Gantt chart does not draw. Durations here are illustrative working days; replace each with what your contractor, cleaner and referencing provider tell you, and replace the notice wait with the period that applies to your tenancy, because notice rules differ by country and by type of tenancy. A timeline schedules the work. It does not make a notice valid or a home fit to let, so keep your local requirements as a checklist beside it. For more on gaps and waits, see /guides/gantt-chart-buffer-time and /guides/gantt-chart-delays. The full chart is at /templates/tenant-turnover-gantt-chart.
A tenant turnover, built in stages
Twenty-four tasks in five groups. Durations are illustrative working days. Open the spreadsheet panel to see the rows behind each stage.
Notice and the end of the tenancy
"Confirm the notice and the end date" (1 working day) is the first task and starts three branches. "Notice period runs" (15) is a plain wait that leads to "Tenancy ends", a milestone. Fix the Start of the first task on the day the notice arrives and replace the 15 with the period that applies to your tenancy.
Inspection and repairs
"Move-out inspection" (1) leads to "Record damage and meter readings" (1), "Scope the repairs" (1), "Get contractor quotes" (3), "Owner approves the repair costs" (1) and "Carry out the repairs" (6). "Repairs complete" is a milestone. Each step needs the one before, so this is a single chain with no overlap.
Clean, check and hand over
"Deep clean" (2) and "Safety checks and certificates" (2) both start when "Repairs complete" is reached and run side by side. "Final photographs and key set" (1) waits for both, and "Home ready to let" is the milestone that closes the preparation stream.
Relisting while repairs run
"Update the listing details and rent" (2) starts as soon as the notice is confirmed. "Advertise the home" (1) starts one day after it with a start-to-start link, and "Viewings" (8) follow. "Applicant chosen" is a milestone. Nothing here waits for the repairs, which is where the overlap comes from.
Referencing, agreement and move-in
"Reference and affordability checks" (5), "Sign the tenancy agreement" (2) and "Collect deposit and first rent" (1) follow the applicant. "Move-in day and key handover" (1) waits for these and for "Home ready to let". In this example the repairs chain is the longer one, so the move-in date follows it. Fix the Start of the handover on the next tenant's date and read the conflict flag.
What happens on the move-in day
A move-in inspection flowchart. The last task on the Gantt chart, the key handover, opens this process.
Get the home ready for handover
"Tenancy start date confirmed and keys due" leads to "Prepare the inventory with meter readings and dated photos" and then "Home clean and ready for handover?". If the answer is No, "Complete cleaning or urgent fixes before the tenant arrives" loops back. That loop is why "Final photographs and key set" sits before the handover on the Gantt chart.
Walk each room and log what differs
"Walk each room against the inventory and note the condition" leads to "Differences or defects found?". Each item is logged with a photo, and "Does the defect affect safe use of the home?" decides whether an urgent repair is raised. A Gantt chart has no decision shape, so the plan only holds the time this walk takes.
Agree the inventory with the tenant
"Compare the tenant's notes with the inventory and update it" leads to "Tenant signs the inventory as accurate?". A disputed item goes to "Re-inspect the disputed item and record both views" and back to the question. The signed inventory is stored before anything else closes.
Close out the repairs
"Repairs from the list still open?" returns to "Complete the logged repairs and report back" until the answer is No, and then "Move-in record complete and shared with the tenant" ends the process. Repairs after move-in are outside the turnover plan, so give the handover a short margin if you expect a long list.
How it works
Open the tenant turnover chart
Open the template and replace each duration with what your contractor, cleaner, referencing provider and local rules tell you. Put the responsible person for each task in People.
Fix the first Start and the move-in date
Give "Confirm the notice and the end date" a fixed Start on the day the notice arrives. If the next tenant has a date, give "Move-in day and key handover" a fixed Start on it. Pin no other dates unless they are genuinely fixed.
Read the finish date and the conflict flag
Compare the finish date the dependencies produce with the date the tenant expects. A fixed Start that the chain cannot meet is flagged. Turn on Critical path in the View menu to light the chain that sets the finish.
Decide which stream to speed up
If the repairs chain is the longer one, look at the quotes and the owner approval, because those are waits on other people. If the relisting stream is longer, look at the viewings and the referencing. Hover over a task to see its dates.
Change one thing and read again
Start the listing earlier, ask for quotes sooner, or split the repairs into a first and second visit. Read the finish date after each change. Progress does not move dates, so change durations and links, not progress.
Share the plan with the owner and the contractor
Share the chart as a link so the owner, the contractor and the agent can see their waits and add comments. Export a PDF for the owner if a printed timeline is useful.
Mistakes to avoid
Starting the listing only after the repairs
If every task waits for the one before it, the two streams add up instead of overlapping. Link the listing to the notice and use a start-to-start link for the advertising, so viewings can begin while the home is still being repaired.
Leaving the owner's approval out
Repairs often wait for the owner to agree the cost. If that step is missing, the plan looks shorter than it is. Keep it as its own task and give it the time the owner usually takes.
Using the example notice period as your own
Notice rules differ by country and by type of tenancy. The 15 working days in the example is a placeholder. Replace it with the period that applies to your tenancy.
Assuming the chart makes the turnover lawful
The chart schedules tasks. It does not check that a notice is valid, that the deposit is handled correctly or that the home meets safety rules. Keep those requirements as a separate checklist.
Open the tenant turnover Gantt chart
Open the turnover chart, fix the first Start and the move-in date, and see which chain is setting the empty weeks.
Related guides
Frequently asked questions
Can QueryChart count back from the day the next tenant moves in?
No. Scheduling is forward only. Fix the Start of the first task and of the move-in task, then compare the finish date with the date you need. A fixed Start that conflicts with a dependency is flagged.
How do I show that the listing can start before the repairs finish?
Link "Advertise the home" to the listing task with a start-to-start link and a short lag, and do not link it to the repairs. The viewings then run beside the repair stream.
What if the contractor needs longer than planned?
Increase the duration of "Carry out the repairs" or "Get contractor quotes" and read the finish date. Every task after it moves, and the conflict flag shows whether a fixed move-in date still holds.
Does this show how much rent the gap costs?
No. The chart schedules tasks and does not track costs or income. Count the working days between "Tenancy ends" and "New tenancy begins" and multiply by your own rent figure.
Does the timeline make the turnover compliant?
No. It schedules the work. It does not make a notice valid or a home fit to let. Use your local rules for that.