Tenant turnover Gantt chart template: from notice to the next tenant

An editable Gantt chart for a vacated rental home: notice, move-out inspection, repairs, clean, relisting, viewings, referencing and move-in, with dependencies, milestones and the void period visible.

Use this template

What the tenant turnover gantt chart template: from notice to the next tenant process is

A tenant turnover is a short project with a cost clock attached. Rent stops on the day the tenancy ends and starts again when the next tenant moves in, and the days between are the void period. Most of the work in that gap is sequential: you cannot scope repairs until the home has been inspected, and you cannot hand over keys until the repairs and checks are finished. A timeline shows which of the tasks sit on that sequence and which ones can run earlier, while the current tenant is still living there.

This template has five groups: Notice and move-out, Inspection and repairs, Clean and ready, Relisting and viewings, and Referencing and move-in. It has 24 tasks and five milestones, and a total length of 33 working days in the illustrative numbers. **Confirm the notice and the end date** (1 working day) is the only starting task. It leads to **Notice period runs** (15), a plain wait task, and then to the milestone **Tenancy ends**. Two things start at once on day one without waiting for the tenancy to end: **Agree viewing access with the outgoing tenant** (1) and **Update the listing details and rent** (2). The chart is built so that marketing starts during the notice period instead of after the keys come back.

After **Tenancy ends**, the repair path is strictly in order: **Move-out inspection** (1), **Record damage and meter readings** (1), **Scope the repairs** (1), **Get contractor quotes** (3), **Owner approves the repair costs** (1) and **Carry out the repairs** (6). **Repairs complete** then opens two parallel tasks, **Deep clean** (2) and **Safety checks and certificates** (2), which both feed **Final photographs and key set** (1) and the milestone **Home ready to let**. The letting path runs on its own: **Advertise the home** (1), **Viewings** (8, starting one working day after advertising), **Applicant chosen**, **Reference and affordability checks** (5), **Sign the tenancy agreement** (2) and **Collect deposit and first rent** (1).

The two paths meet at **Move-in day and key handover** (1), which waits for both **Home ready to let** and **Collect deposit and first rent**. In the illustrative numbers the repair path is the longer one: a tenant is signed and paid by working day 20, and the home is not ready until day 32. That gap is the most useful thing the chart shows. It tells you that faster marketing would not shorten the void period, and that quotes, owner approval and trade availability would. All durations are illustrative. Notice periods, inspection rules, deposit handling and referencing requirements differ by country and by tenancy, so replace the numbers with your own and keep your local rules as notes on the tasks.

A timeline schedules the work. It does not decide what a tenant is owed, what a landlord must do or whether a notice is valid. For related plans, see /templates/tenant-move-in-inspection-process for the inspection steps, /templates/tenant-application-screening-process for the referencing steps and /templates/security-deposit-return-process for the deposit. For how to read the void period on a plan, see /guides/void-period-gantt-chart.

What this flowchart covers

In this template

  • Five groups, Notice and move-out, Inspection and repairs, Clean and ready, Relisting and viewings and Referencing and move-in, with 24 tasks and five milestones: "Tenancy ends", "Repairs complete", "Home ready to let", "Applicant chosen" and "New tenancy begins".
  • The notice period as a plain wait: "Notice period runs" has a duration and no work, and "Update the listing details and rent" and "Agree viewing access with the outgoing tenant" run alongside it.
  • A repair path in strict order, from "Move-out inspection" to "Carry out the repairs", with the owner's approval as its own task.
  • A letting path that can finish early: "Viewings" follows "Advertise the home" and the chain ends at "Collect deposit and first rent" while the home is still being repaired.
  • A join at "Move-in day and key handover", which waits for both "Home ready to let" and "Collect deposit and first rent".

When to use this template

  • You manage rental homes and want a reusable plan for each time a tenant leaves.
  • You want to see how many working days of void period come from repairs and how many from marketing and referencing.
  • A next tenant has an earliest move-in date and you need to know whether the home can be ready by then.
  • You hand turnover work to a letting team or contractors and want one plan they can all open.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Confirm the notice and the end dateNotice and move-out1
2Notice period runsNotice and move-out151
3Tenancy endsNotice and move-outMilestone2
4Agree viewing access with the outgoing tenantNotice and move-out11
5Move-out inspectionInspection and repairs13
6Record damage and meter readingsInspection and repairs15
7Scope the repairsInspection and repairs16
8Get contractor quotesInspection and repairs37
9Owner approves the repair costsInspection and repairs18
10Carry out the repairsInspection and repairs69
11Repairs completeInspection and repairsMilestone10
12Deep cleanClean and ready211
13Safety checks and certificatesClean and ready211
14Final photographs and key setClean and ready112, 13
15Home ready to letClean and readyMilestone14
16Update the listing details and rentRelisting and viewings21
17Advertise the homeRelisting and viewings14, 16
18ViewingsRelisting and viewings817SS+1
19Applicant chosenRelisting and viewingsMilestone18
20Reference and affordability checksReferencing and move-in519
21Sign the tenancy agreementReferencing and move-in220
22Collect deposit and first rentReferencing and move-in121
23Move-in day and key handoverReferencing and move-in115, 22
24New tenancy beginsReferencing and move-inMilestone23

How it works

  1. Fix the dates that are real

    Give "Confirm the notice and the end date" a fixed Start on the day notice arrives and give "Move-in day and key handover" a fixed Start on the next tenant's earliest day. The plan starts on the earliest fixed Start and is scheduled forward, so a conflict flag on the move-in task tells you the earliest date the repairs and referencing allow.

  2. Replace the notice wait

    Set "Notice period runs" to the working days between notice and the end of the tenancy. Notice periods differ by country and by tenancy, so the plan holds your own number.

  3. Resize the repairs

    Set "Get contractor quotes", "Owner approves the repair costs" and "Carry out the repairs" from your own contractors. These are the tasks most likely to decide the void period.

  4. Check the letting path

    Set "Viewings" and "Reference and affordability checks" from how long they take for your homes. If the letting path finishes well before "Home ready to let", marketing is not what limits the turnover.

  5. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with the owner and contractors, and export a PDF or PNG for the property file.

Frequently asked questions

How do I see the void period on the chart?

It runs from the milestone "Tenancy ends" to the milestone "New tenancy begins". In the illustrative numbers that is 17 working days. Change a task on the repair path and the end of the gap moves with it.

Can I start marketing before the tenant leaves?

Yes, and the template does. "Update the listing details and rent" and "Agree viewing access with the outgoing tenant" start right after "Confirm the notice and the end date". Whether you may advertise or hold viewings during a notice period depends on your country and the tenancy, so check your own rules.

Does the plan tell me how long a notice period must be?

No. Notice periods and the rules around them differ by country and tenancy. The plan holds the number you enter in "Notice period runs" and moves the dates after it.

What if the next tenant can only move in on a fixed date?

Give "Move-in day and key handover" a fixed Start on that date. The chart schedules forward, so if the repairs and checks cannot be finished by then, the task shows a conflict and the earliest date its dependencies allow.

Can I use it for a student let or a holiday let?

Yes. Resize the tasks, remove the referencing tasks that do not apply and add any changeover step you need. For routine maintenance requests see /templates/rental-maintenance-request-process.