Buy-to-let acquisition Gantt chart template: from purchase to first rent

An editable Gantt chart for buying a rental property: survey, finance, completion, licensing checks, refurbishment, safety certificates, furnishing, letting launch and first tenant, with dependencies and milestones.

Use this template

What the buy-to-let acquisition gantt chart template: from purchase to first rent process is

A purchase for letting has two phases that behave differently. Before completion you are waiting on other people: the surveyor, the lender, the searches and the solicitor. After completion you own a property that earns nothing, and every working day of refurbishment, certification and marketing is a day without rent. A timeline helps because it shows what can be prepared early, so that the post-completion phase starts with quotes, a rent figure and a listing plan already in hand.

This template has five groups: Purchase and finance, Checks and registration, Refurbishment, Compliance and furnishing, and Letting. It has 24 tasks and five milestones, and a total length of 54 working days in the illustrative numbers. **Agree the purchase and instruct the solicitor** (2 working days) is the only starting task. Three paths leave it at once. The finance path runs **Apply for the buy-to-let mortgage** (2), **Lender valuation and underwriting** (12) and the milestone **Mortgage offer received**. The legal path is **Searches and legal enquiries** (10). The survey path is **Commission the survey** (4) and **Review the survey and confirm the price** (2). All three must be finished before **Exchange contracts** (1), which leads to **Wait for the agreed completion date** (5) and the milestone **Completion**.

Some work after completion can be prepared before it. **Get refurbishment quotes** (4) starts once the survey is reviewed, and **Set the rent and prepare the listing** (2) starts at the same point. **Carry out the refurbishment** (12) needs both the quotes and **Completion**. After the milestone **Refurbishment complete**, **Safety inspections and energy assessment** (4) and **Furnish and equip** (4) run side by side, and **Landlord insurance and utilities** (2) starts from completion. All of these feed **Photograph and advertise** (2).

The longest wait is the one that is easiest to forget. **Check licensing and registration needs for the area** (2) starts at the beginning, because it costs nothing to find out early. But **Apply for any licence or registration** (2) can only start after **Completion**, and **Wait for the licence or registration decision** (20) is a plain wait. In the illustrative numbers that wait ends at working day 44, which is later than the furnished home would otherwise be ready on day 40, so the plan shows the licence as the task holding **Viewings, referencing and tenancy agreement** (10) and the milestone **First tenant moves in**. Whether a licence or registration is needed at all, what it takes and how long it takes differ by country, region and property. The plan holds your own durations, and the numbers here are illustrative.

A timeline schedules the work. It does not assess a purchase, a lender's decision or whether a property can be let. For related plans, see /templates/tenant-application-screening-process for the referencing steps and /templates/tenant-move-in-inspection-process for the first inspection. For how a plan can be read around a fixed completion date, see /guides/property-portfolio-calendar-gantt-chart.

What this flowchart covers

In this template

  • Five groups, Purchase and finance, Checks and registration, Refurbishment, Compliance and furnishing and Letting, with 24 tasks and five milestones: "Mortgage offer received", "Completion", "Licence or registration in place", "Refurbishment complete" and "First tenant moves in".
  • Three paths into exchange: finance, searches and the survey all lead to "Exchange contracts".
  • Preparation before you own the property: "Get refurbishment quotes" and "Set the rent and prepare the listing" start after "Review the survey and confirm the price".
  • A registration wait: "Wait for the licence or registration decision" starts only after "Apply for any licence or registration", which needs "Completion".
  • A launch that waits for four things: "Photograph and advertise" needs the certificates, the furnishing, the insurance and the rent decision.

When to use this template

  • You are buying a property to let and want to see how many working days pass between completion and the first rent.
  • You need to know whether a licence or registration step is what decides the letting date.
  • You buy more than one property a year and want one plan to resize for each.
  • You work with a lender, a solicitor and contractors and want one view of who waits for whom.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Agree the purchase and instruct the solicitorPurchase and finance2
2Commission the surveyPurchase and finance41
3Review the survey and confirm the pricePurchase and finance22
4Apply for the buy-to-let mortgagePurchase and finance21
5Lender valuation and underwritingPurchase and finance124
6Mortgage offer receivedPurchase and financeMilestone5
7Searches and legal enquiriesPurchase and finance101
8Exchange contractsPurchase and finance13, 6, 7
9Wait for the agreed completion datePurchase and finance58
10CompletionPurchase and financeMilestone9
11Check licensing and registration needs for the areaChecks and registration21
12Apply for any licence or registrationChecks and registration210, 11
13Wait for the licence or registration decisionChecks and registration2012
14Licence or registration in placeChecks and registrationMilestone13
15Get refurbishment quotesRefurbishment43
16Carry out the refurbishmentRefurbishment1210, 15
17Refurbishment completeRefurbishmentMilestone16
18Safety inspections and energy assessmentCompliance and furnishing417
19Furnish and equipCompliance and furnishing417
20Landlord insurance and utilitiesCompliance and furnishing210
21Set the rent and prepare the listingLetting23
22Photograph and advertiseLetting218, 19, 20, 21
23Viewings, referencing and tenancy agreementLetting1014, 22
24First tenant moves inLettingMilestone23

How it works

  1. Fix the dates that are real

    Give "Agree the purchase and instruct the solicitor" a fixed Start on the day you begin and "Completion" a fixed Start on the agreed completion date. The plan starts on the earliest fixed Start and is scheduled forward, so a conflict flag on "Completion" tells you the earliest date the finance, survey and legal paths allow.

  2. Set the three pre-completion paths

    Set "Lender valuation and underwriting", "Searches and legal enquiries" and "Commission the survey" from what your lender, solicitor and surveyor tell you. The longest of the three is the one that decides exchange.

  3. Replace the registration wait

    Check what applies where the property is, then set "Wait for the licence or registration decision" to the time you have been told. Rules and processing times differ by country and region, and if nothing applies you can shorten the wait to zero or remove the tasks.

  4. Resize the works

    Set "Get refurbishment quotes" and "Carry out the refurbishment" from your contractor, and set the certificate and furnishing tasks from your own suppliers.

  5. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with the solicitor, broker and contractors, and export a PDF or PNG for the purchase file.

Frequently asked questions

Can the chart tell me when completion will happen?

No. It schedules forward from the durations you enter. If you have an agreed completion date, give "Completion" a fixed Start on it and the chart shows whether the finance, survey and legal paths can be finished by then.

Do I need a licence or registration for my property?

That depends on the country, the region and the property, and the plan does not decide it. The tasks "Check licensing and registration needs for the area" and "Wait for the licence or registration decision" hold your own findings and durations. Remove them if nothing applies.

Why does refurbishment start only after completion?

Because you cannot work on a property you do not own. Quotes and a rent decision can be prepared earlier, and the template starts them early, but "Carry out the refurbishment" waits for "Completion".

What if the mortgage offer is delayed?

Lengthen "Lender valuation and underwriting" and see which dates move. "Exchange contracts" and everything after it move, while the survey, the searches and the quotes do not.

Can I use it for a property I will not refurbish?

Yes. Shorten "Carry out the refurbishment" to the repairs you do need, or remove the refurbishment tasks and connect "Completion" straight to the compliance and furnishing tasks.