Hotel annual deep clean Gantt chart template: room blocks and contractors

An editable Gantt chart for a hotel's annual deep clean and preventive maintenance in a quiet period: scheduling, specialist contractors, room blocks, public areas, inspection and handback, with dependencies and milestones.

Use this template

What the hotel annual deep clean gantt chart template: room blocks and contractors process is

A deep clean and maintenance period is a trade-off between access and revenue. Rooms taken out of sale cannot earn, and rooms still on sale cannot be worked on. Specialist contractors have their own calendars, so the booking happens long before the work. A timeline helps because it shows how much of the plan is preparation, how much is the window itself and what must be finished before rooms return to sale.

This template has five groups: Planning, Room blocks, Public areas, Specialist contractors and Inspection and handback. It has 22 tasks and three milestones, and a total length of 43 working days in the illustrative numbers. **Choose the low-occupancy window** (2 working days) leads to **Agree the scope and checklist** (3), then **Brief housekeeping, engineering and front office** (1). In parallel, **Request quotes from specialist contractors** (4), **Choose and book the contractors** (2) and **Wait for the contractors to mobilise** (10) run up to the milestone **Window opens**. In the illustrative numbers the contractor wait sets that milestone, and the briefing is finished long before it.

Between **Window opens** and **Handed back to operations** is the part that earns its place in the plan: 20 working days in the illustrative numbers. Rooms are worked in three blocks. **Deep clean rooms, block 1** (6) starts at the window, **Deep clean rooms, block 2** (6) starts 4 working days into block 1, and **Deep clean rooms, block 3** (6) starts 4 working days into block 2, so the crew moves on while the rooms behind it are finished. **Preventive maintenance in rooms** (5) starts 2 working days into the first block. Public areas run on their own: **Deep clean the lobby, restaurant and bar** (5) and **Service meeting rooms and corridors** (4), which starts 1 working day after it. The contractors work from the same milestone: **Carpet and upholstery cleaning** (6), **Kitchen extraction cleaning** (3) and **Lift and fire system servicing** (4).

Everything meets at **Inspect rooms and public areas** (3), which needs the third block, the maintenance, the public areas and all three contractor tasks. In this version the last room block is what holds the inspection. **Fix snags from the inspection** (3) leads to **Handed back to operations**, then **Return rooms and areas to sale** (1) and **Record findings for next year** (2), and both lead to **Deep clean closed**. All durations are illustrative. The plan holds your own: which maintenance has to happen, how often and under which certificate or inspection rule differs by country and by property, so keep those requirements as tasks or notes with their own owners.

A timeline schedules the work. It does not allocate people across blocks or level the load between teams, and it does not check that the work meets any standard. For related plans, see /templates/hotel-pre-opening-gantt-chart for a launch plan with its own inspection stage, /templates/equipment-installation-gantt for contractor work with a handover, and /templates/hotel-room-turnaround-housekeeping-process for the daily room routine this deep clean interrupts.

What this flowchart covers

In this template

  • Five groups, Planning, Room blocks, Public areas, Specialist contractors and Inspection and handback, with 22 tasks and three milestones: "Window opens", "Handed back to operations" and "Deep clean closed".
  • A contractor lead time shown as work you can see: "Request quotes from specialist contractors", "Choose and book the contractors" and "Wait for the contractors to mobilise", which decides "Window opens".
  • Three room blocks that overlap by start-to-start links, so "Deep clean rooms, block 2" starts 4 working days into block 1 and block 3 the same into block 2.
  • Specialist tasks that run beside the rooms: "Carpet and upholstery cleaning", "Kitchen extraction cleaning" and "Lift and fire system servicing".
  • A handback that closes the loop: "Inspect rooms and public areas", "Fix snags from the inspection", "Return rooms and areas to sale" and "Record findings for next year".

When to use this template

  • You close part of the hotel each year for a deep clean and maintenance and want one plan to resize for each window.
  • You need to check whether the contractors' lead time fits before the quiet period starts.
  • You want to decide how many room blocks to use and how far to overlap them.
  • You want inspection and handback planned as steps, so rooms do not go back on sale on hope.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Choose the low-occupancy windowPlanning2
2Agree the scope and checklistPlanning31
3Brief housekeeping, engineering and front officePlanning12
4Request quotes from specialist contractorsSpecialist contractors42
5Choose and book the contractorsSpecialist contractors24
6Wait for the contractors to mobiliseSpecialist contractors105
7Window opensPlanningMilestone3, 6
8Carpet and upholstery cleaningSpecialist contractors67
9Kitchen extraction cleaningSpecialist contractors37
10Lift and fire system servicingSpecialist contractors47
11Deep clean rooms, block 1Room blocks67
12Deep clean rooms, block 2Room blocks611SS+4
13Deep clean rooms, block 3Room blocks612SS+4
14Preventive maintenance in roomsRoom blocks511SS+2
15Deep clean the lobby, restaurant and barPublic areas57
16Service meeting rooms and corridorsPublic areas415SS+1
17Inspect rooms and public areasInspection and handback38, 9, 10, 13, 14, 16
18Fix snags from the inspectionInspection and handback317
19Handed back to operationsInspection and handbackMilestone18
20Return rooms and areas to saleInspection and handback119
21Record findings for next yearInspection and handback218
22Deep clean closedInspection and handbackMilestone20, 21

How it works

  1. Fix the dates that are real

    Give "Choose the low-occupancy window" a fixed Start on the day you begin, and give "Window opens" a fixed Start on the first day of the quiet period. The plan starts on the earliest fixed Start and is scheduled forward, so a conflict flag on the window shows the earliest date its dependencies allow.

  2. Replace the contractor wait

    Set "Request quotes from specialist contractors", "Choose and book the contractors" and "Wait for the contractors to mobilise" from what your contractors quote. If the wait is the longest part of the plan, start it earlier.

  3. Resize the room blocks

    Set the three block tasks from your own room count and crew size, and adjust the 4-day start-to-start links to how quickly the crew moves on. Use fewer or more blocks by deleting or copying a task.

  4. Check the inspection gate

    Set "Inspect rooms and public areas" and "Fix snags from the inspection" from how your own inspections run, and check which task holds the inspection.

  5. Plan the return to sale

    Set "Return rooms and areas to sale" to the time front office and revenue need to reopen the inventory.

  6. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with housekeeping, engineering and the contractors, and export a PDF or PNG for the maintenance file.

Frequently asked questions

Does the chart tell me which maintenance I need?

No. It schedules the tasks you give it. Which maintenance is required, how often and under which rules differs by country and property, so put your own requirements in as tasks or notes with the durations you actually need.

Does it level the workload between teams?

No. The chart schedules each task from its links and does not move work to balance people. Use the start-to-start links to show how a crew moves from block to block, and add owners in People.

My quiet period has fixed dates. How do I check it fits?

Give "Choose the low-occupancy window" a fixed Start and "Window opens" a fixed Start on the first day of the period. The chart schedules forward from the earliest fixed Start. If the contractor lead time cannot fit before then, "Window opens" shows a conflict and the earliest date its dependencies allow.

Can I add more floors or wings?

Yes. Copy a block task for each floor or wing and link each into "Inspect rooms and public areas". See /guides/rolling-room-refurbishment-gantt-chart for taking rooms out in blocks over a longer programme.