Hotel room refresh programme Gantt chart template: blocks and lead times
An editable Gantt chart for refreshing hotel rooms block by block while the hotel stays open: furniture lead times as waits, rooms out of inventory, trades in sequence, snagging and rooms returned to sale.
What the hotel room refresh programme gantt chart template: blocks and lead times process is
Refreshing rooms floor by floor is not a normal building project, because the hotel keeps selling the rooms you have not touched. Revenue depends on how many rooms are out of order at any moment, and that is set by the order in which you take blocks out and return them. A timeline helps because it shows the whole sequence, including the weeks when a block of rooms is empty and waiting for something.
This template has six groups: Plan and approvals, Furniture lead time, Block 1 rooms, Block 2 rooms, Block 3 rooms and Close-out. It has 24 tasks and five milestones, and a total length of 69 working days in the illustrative numbers. "Agree scope and room sequence" (3 working days) is the only starting task. It leads to "Approve budget and trade quotes" (4) and "Set the inventory plan with revenue" (2), and both must finish before the milestone "Refresh programme approved". Then "Order furniture and soft furnishings" (2) starts two waits that run side by side: "Block 1 furniture made and shipped" (20) and "Blocks 2 and 3 furniture made and shipped" (32).
The date driver is the order of the blocks. "Take block 1 rooms out of inventory" (1) waits for the approval and starts 12 working days into the block 1 furniture wait, using a start-to-start link, so the rooms leave sale while the furniture is still being made instead of on the day of approval. Then "Strip out and make good block 1" (4) and "Decorate and lay flooring in block 1" (6) follow in sequence. "Fit furniture in block 1" (3) needs both the decorating and the shipment. In the illustrative numbers the decorating ends on working day 32 and the shipment on day 29, so the trades set the pace. If the shipment slips past the decorating, the plan shows the rooms standing empty and you can see how many days that costs.
After "Fit furniture in block 1" come "Snag block 1 rooms" (2) and the milestone "Block 1 returned to sale". Only then does "Take block 2 rooms out of inventory" begin, and block 3 follows block 2 in the same way, so never more than one block is out of order. The longer furniture wait for blocks 2 and 3 finishes on working day 41, well before "Fit furniture in block 2" can start on day 47. That gap is slack you can use if the shipment is late. "Final walk-through and handback" (2) closes the programme after "Block 3 returned to sale". All durations are illustrative: replace them with your contractors' times and your suppliers' quoted lead times.
A timeline schedules the work. It does not count rooms or crews, and it does not know how many rooms are in a block, so a larger block needs longer tasks that you enter yourself. Noise rules, guest notice and any permits differ by country and by property, so keep them as tasks or notes with their own owners. For related plans, see /templates/hotel-room-turnaround-housekeeping-process for the daily room flow that the returned rooms rejoin, /templates/renovation-gantt for a fuller building project and /templates/hotel-pre-opening-gantt-chart for opening a property. For how the room blocks are laid out, see /guides/rolling-room-refurbishment-gantt-chart and /guides/gantt-chart-dependencies.
What this flowchart covers
In this template
- Six groups, Plan and approvals, Furniture lead time, Block 1 rooms, Block 2 rooms, Block 3 rooms and Close-out, with 24 tasks and five milestones: "Refresh programme approved", "Block 1 returned to sale", "Block 2 returned to sale", "Block 3 returned to sale" and the final handback.
- Two furniture waits as plain tasks: "Block 1 furniture made and shipped" (20 working days) and "Blocks 2 and 3 furniture made and shipped" (32), both started by "Order furniture and soft furnishings".
- A start-to-start link so that "Take block 1 rooms out of inventory" begins 12 working days into the first furniture wait, which keeps rooms in sale for as long as the plan allows.
- A strict block sequence: "Take block 2 rooms out of inventory" waits for "Block 1 returned to sale", and "Take block 3 rooms out of inventory" waits for "Block 2 returned to sale".
- Trades in sequence inside each block, from stripping out through decorating and fitting furniture to "Snag block 1 rooms" and its twins for blocks 2 and 3.
When to use this template
- You refresh rooms while the hotel stays open and need to show how many rooms are out of order and for how long.
- Furniture or soft furnishings have long lead times and you want to see how late a delivery can be before a block is held up.
- You report to an owner or a brand and want one plan that shows each block returning to sale on a date.
- You are deciding whether to run blocks one after another or to take more rooms out at once, and want to see the effect on the end date.
The plan, task by task
Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.
| # | Task | Group | Working days | Depends on |
|---|---|---|---|---|
| 1 | Agree scope and room sequence | Plan and approvals | 3 | |
| 2 | Approve budget and trade quotes | Plan and approvals | 4 | 1 |
| 3 | Set the inventory plan with revenue | Plan and approvals | 2 | 1 |
| 4 | Refresh programme approved | Plan and approvals | Milestone | 2, 3 |
| 5 | Order furniture and soft furnishings | Furniture lead time | 2 | 4 |
| 6 | Block 1 furniture made and shipped | Furniture lead time | 20 | 5 |
| 7 | Blocks 2 and 3 furniture made and shipped | Furniture lead time | 32 | 5 |
| 8 | Take block 1 rooms out of inventory | Block 1 rooms | 1 | 4, 6SS+12 |
| 9 | Strip out and make good block 1 | Block 1 rooms | 4 | 8 |
| 10 | Decorate and lay flooring in block 1 | Block 1 rooms | 6 | 9 |
| 11 | Fit furniture in block 1 | Block 1 rooms | 3 | 6, 10 |
| 12 | Snag block 1 rooms | Block 1 rooms | 2 | 11 |
| 13 | Block 1 returned to sale | Block 1 rooms | Milestone | 12 |
| 14 | Take block 2 rooms out of inventory | Block 2 rooms | 1 | 13 |
| 15 | Strip out and decorate block 2 | Block 2 rooms | 9 | 14 |
| 16 | Fit furniture in block 2 | Block 2 rooms | 3 | 7, 15 |
| 17 | Snag block 2 rooms | Block 2 rooms | 2 | 16 |
| 18 | Block 2 returned to sale | Block 2 rooms | Milestone | 17 |
| 19 | Take block 3 rooms out of inventory | Block 3 rooms | 1 | 18 |
| 20 | Strip out and decorate block 3 | Block 3 rooms | 9 | 19 |
| 21 | Fit furniture in block 3 | Block 3 rooms | 3 | 20 |
| 22 | Snag block 3 rooms | Block 3 rooms | 2 | 21 |
| 23 | Block 3 returned to sale | Block 3 rooms | Milestone | 22 |
| 24 | Final walk-through and handback | Close-out | 2 | 23 |
How it works
Set the block sizes
Decide how many rooms each block holds, then set the strip out, decorating and fitting tasks of each block to the time your contractors give for that many rooms. Rename the blocks to floors or wings if that is how your team talks about them.
Enter the furniture lead times
Set "Block 1 furniture made and shipped" and "Blocks 2 and 3 furniture made and shipped" to the lead times your suppliers quote. If one delivery covers every block, delete the second wait and link "Fit furniture in block 2" to the first.
Tune when block 1 leaves sale
Adjust the 12-day start-to-start link on "Take block 1 rooms out of inventory" until the rooms come out as late as the trades and the delivery allow. The goal is a block that leaves inventory when the work can begin and not before.
Fix the dates that are real
Give "Agree scope and room sequence" a fixed Start on the day you begin. If an owner or a brand needs a block back by a certain day, give the matching milestone a fixed Start. The plan is scheduled forward from the earliest fixed Start, so a conflict flag shows the earliest date the work allows.
Check the inventory plan
Read the dates of the three "Take block ... rooms out of inventory" tasks and the three "returned to sale" milestones with your revenue team. Move the blocks to avoid your busiest weeks by lengthening a task or adding a wait before it.
Add owners, share and export
Put the person responsible for each task in People, share the chart as a link with contractors and the owner, and export a PDF or PNG for the project file.
Frequently asked questions
Can the chart tell me how much revenue the programme costs?
No. It shows the dates on which each block leaves and returns to sale. It does not count rooms, rates or cost, so take those dates to your revenue team and work out the effect there.
My supplier gave me a delivery date, not a lead time. What do I enter?
Enter the number of working days from the order to that date as the duration of the furniture task. The chart schedules forward from the order, so if the order moves, the delivery moves with it, and you can then compare the result with the supplier's date.
Can I refresh more than one block at the same time?
Yes. Remove the link from "Block 1 returned to sale" to "Take block 2 rooms out of inventory" and link the second block to "Refresh programme approved" instead. The plan then runs both blocks together, and you can see the shorter end date against the larger number of rooms out of order.
Does it handle permits, noise rules or guest notice?
The plan holds the durations you give it and nothing else. Rules and notice periods differ by country and by property, so add them as tasks or notes with their own owners and durations.
What if the hotel has more or fewer than three blocks?
Copy the five tasks of a block to add one, or delete a block you do not need. Link the first task of each block to the "returned to sale" milestone of the block before it. See /guides/gantt-chart-dependencies for how links behave when you rearrange them.