How to plan a rolling room refurbishment on a Gantt chart
Plan a rolling room refurbishment on a Gantt chart: furniture lead times as plain waits, rooms taken out of inventory in blocks, trades in sequence, snagging and each block returned to sale while the hotel stays open.
A hotel that refreshes its rooms while staying open can only lose a few rooms at a time. This guide shows how to put the blocks, the furniture lead times and the snagging on a Gantt chart and see which wait sets the finish.
The short version
- Fix the Start of the first task and let the later dates follow from the dependencies.
- Give each furniture lead time a plain wait task with a duration you replace with the supplier's quote.
- End every block with a milestone that returns the rooms to sale and release the next block from it.
- Use a start-to-start link so the strip-out runs while the first furniture order is being made.
- Turn on Critical path to see whether the furniture waits or the block sequence sets the finish.
Take rooms out in blocks and let the furniture wait run beside the work
A rolling refurbishment has two clocks. The first is the rooms: each block leaves inventory, is stripped, decorated, furnished and snagged, and then goes back on sale so the hotel keeps earning. The second is the furniture, which is made and shipped by someone else on a lead time that the hotel does not control. The plan works when the room work for one block overlaps the furniture wait for the next.
A Gantt chart in QueryChart schedules forward from the earliest fixed Start. Give "Agree scope and room sequence" a fixed Start on the day you begin. "Refresh programme approved" is a milestone that gathers the budget and the inventory plan, and the furniture order waits for it. Each block then follows the same pattern: "Take block 1 rooms out of inventory", the trades, the furniture, "Snag block 1 rooms" and a milestone, "Block 1 returned to sale", that releases the next block. Blocks run one after another because the hotel can only spare so many rooms at once.
The example below is the hotel room refresh programme template: 24 tasks in six groups. The furniture lead times are plain wait tasks, "Block 1 furniture made and shipped" and "Blocks 2 and 3 furniture made and shipped", with illustrative durations that you replace with the supplier's quote. "Take block 1 rooms out of inventory" uses a start-to-start link to the first furniture wait, so the rooms are stripped while the furniture is being made. "Fit furniture in block 1" needs both the decorating and the delivery.
After the example, a flowchart shows the process that every refreshed room goes back into: the room turnaround. A Gantt chart says when each block is ready to sell and cannot draw the inspection loops and the deep clean decisions inside that process. Durations in both charts are illustrative. Contractor sequences, fire and safety checks and the number of rooms a hotel can spare differ by property and country, so the plan holds your durations and your own advisers decide what they are. A timeline schedules the work. It is not building, safety or legal advice.
For waits and gaps in general see /guides/gantt-chart-buffer-time and /guides/gantt-chart-delays. For a neighbouring project, see /guides/renovation-gantt-chart and /templates/hotel-room-refresh-programme-gantt-chart, and for the process that handles each room afterwards, /templates/hotel-room-turnaround-housekeeping-process.
A room refresh programme, built in stages
Twenty-four tasks in six groups. Durations are illustrative working days. Open the spreadsheet panel to see the rows behind each stage.
Plan and approvals
"Agree scope and room sequence" (3 working days) leads to "Approve budget and trade quotes" (4) and "Set the inventory plan with revenue" (2), which run side by side. "Refresh programme approved" is a milestone on day 7. Fix the Start of the first task on the day you begin.
The furniture lead times
"Order furniture and soft furnishings" (2) waits for the milestone. "Block 1 furniture made and shipped" (20) and "Blocks 2 and 3 furniture made and shipped" (32) are plain waits with illustrative durations. The longer one finishes on day 41, which is why the second and third blocks are never held up by furniture in this example.
Block 1, the first rooms back
"Take block 1 rooms out of inventory" (1) starts alongside the first furniture wait. "Strip out and make good block 1" (4) and "Decorate and lay flooring in block 1" (6) follow, and "Fit furniture in block 1" (3) needs both the decorating and the delivery. "Snag block 1 rooms" (2) leads to the milestone "Block 1 returned to sale" on day 34.
Block 2
"Take block 2 rooms out of inventory" (1) waits for block 1 to return. "Strip out and decorate block 2" (9) ends on day 44 and "Fit furniture in block 2" (3) also needs the long furniture wait, so it starts when the decorating ends. "Snag block 2 rooms" (2) leads to "Block 2 returned to sale".
Block 3 and the handback
"Take block 3 rooms out of inventory" (1) waits for block 2. "Strip out and decorate block 3" (9), "Fit furniture in block 3" (3) and "Snag block 3 rooms" (2) follow in order, and "Block 3 returned to sale" leads to "Final walk-through and handback" (2). The longest chain adds up to 66 working days and is set by the blocks one after another.
The process each refreshed room returns to
The room turnaround as a flowchart. The Gantt chart says when a block comes back and this chart shows how each room is cleaned, checked and released.
Checkout and the first look
"Guest checks out" leads to "Set the room to Vacant Dirty in the system" and "Strip the bed and look for items left behind". "Anything left behind?" sends a Yes to "Bag and log the item for the lost property store". Rooms from a new block follow the same route the first time a guest stays in them.
Cleaning and defects
"Clean the bathroom, make the bed and restock" is followed by "Defect found: leak, stain or broken fitting?". A Yes leads to "Raise a maintenance ticket and tag the room" and "Assess and repair, then update the ticket". If "Room usable after the repair?" is No, the room ends at "Room set Out of Order and reported to the Executive Housekeeper". Snagging in the refurbishment plan catches the same kind of defect earlier.
Inspection
"Mark the room Cleaned and request inspection" leads to "Inspection passed?". A No sends "Return the room with the points to redo" back to the cleaning step. A Yes leads to "Set the room to Inspected and Ready".
Arrival and the deep clean
"Arriving guest waiting for this room?" sends a Yes to "Room goes straight to the arriving guest". Otherwise "Room due a deep clean this cycle?" decides between "Schedule the deep clean and block the room for those days" and "Room ready and back in sellable stock". Whether and how often your hotel deep cleans a room is your own policy.
How it works
Open the room refresh chart
Open the template and replace each duration with what your contractors, your suppliers and your revenue team tell you. Put the person responsible for each task in People.
Fix the first Start
Give "Agree scope and room sequence" a fixed Start on the day you begin. The plan is scheduled forward, so every block date is a result of the chain until you fix one.
Set the furniture waits
Replace the durations of the two furniture wait tasks with your supplier's quote. Hover over a task to see the dates it produces.
Size the blocks
Decide how many rooms each block holds with your revenue team. A bigger block shortens the programme but takes more rooms out of sale at once, so change the block tasks and watch the finish.
Find what sets the finish
Turn on Critical path in the View menu. If a furniture wait is lit, ask the supplier about earlier delivery or split the order. If the block tasks are lit, look at the trade durations.
Share the plan with the trades
Share the chart as a link so each trade and the front office can see their block and add comments. Export a PDF for people who are not in the chart.
Mistakes to avoid
Treating furniture as a task the hotel does
A furniture order is a wait. Give it a plain wait task with the supplier's duration so a late delivery shows up as a late block.
Returning rooms to sale without a milestone
If no milestone marks each block as back on sale, the revenue team has no date to load inventory against. End every block with one.
Taking all the rooms out at once
One long block is easy to plan and costs the most rooms. Keep the blocks small enough to match what the hotel can spare.
Using the template durations as facts
Trade times, lead times and snagging are illustrative. Safety checks and contractor rules differ by property and country, and the chart is not advice.
Open the room refresh Gantt chart
Open the template, fix the first Start and see whether the furniture or the blocks set the finish.
Related guides
Frequently asked questions
Can QueryChart work backwards from a reopening date?
No. Scheduling is forward only. Fix the Start of the first task, and fix the Start of a block milestone if a date is already agreed, then read the conflict flag to see whether the chain before it fits.
How do I show furniture that takes weeks to arrive?
Add a plain task for the wait and give it the supplier's duration. In the example the first furniture wait is 20 working days and the second is 32.
Can the strip-out start while the furniture is being made?
Yes. Link the strip-out to the furniture order with a start-to-start dependency. In the example block 1 rooms leave inventory when the first furniture wait starts.
Can I paste my own refurbishment plan?
Yes. Paste your table into the spreadsheet panel with one row per task and the group, duration and dependencies in columns. You can then edit it as a chart.