Factory setup Gantt chart template: empty building to first approved production

An editable Gantt chart for setting up a new factory or production site: permits, building works, long-lead equipment, utilities, installation, commissioning, validation and training, up to the first approved production.

Use this template

What the factory setup gantt chart template: empty building to first approved production process is

Setting up a new production site is a set of jobs that start in different places and meet late. The authority reviews permit applications while the building is prepared. The equipment supplier builds machines for weeks while utilities are run into the hall. Training material is written while the machines are still in transit. Nothing on site can be commissioned until all of it has arrived, so the plan is decided by which stream reaches the installation step last. A timeline shows that stream before you have paid for the wait.

This template has four groups: Site and permits, Equipment and long lead, Installation and utilities, and Commissioning and handover. "Freeze layout and process flow" (4 working days) is the only starting task and feeds three streams at once: "Submit permit applications", "Prepare building and floors" (15) and "Issue equipment purchase orders". "Authority review of applications" (20) leads to the "Permits granted" milestone, which gates "Connect power, air and water" (10), so nothing is energised before the permit is in hand.

The long stream is the equipment. "Manufacture long-lead equipment" (40) is followed by "Factory acceptance test at supplier" (3), "Ship and deliver equipment" (10) and the "Equipment on site" milestone. With the illustrative durations, this stream and not the permit review decides the date, so the chart shows where slack exists on the permit side and where it does not on the equipment side. "Position and anchor equipment" (8) waits for both the floor works and "Equipment on site", and "Connect equipment to utilities" (6) waits for that and for the "Utilities ready" milestone.

Commissioning starts only once the machines are connected. "Run equipment commissioning" (8) is followed by "Validate process and first samples" (10). "Write operating procedures" (6) starts after the factory acceptance test, while the machines are still being shipped, and "Train operators and maintenance staff" (8) starts 4 days after commissioning starts so staff train on a running machine. "First production approved" waits for validation and training, and "Hand over to production" (3) closes the plan. All durations are illustrative.

A timeline schedules the work. It does not obtain a permit, qualify equipment or make the site compliant, and the approval at the end follows your own quality system. For one machine in detail, see /templates/equipment-installation-gantt. For the volume build-up after the first approved run, see /templates/production-ramp-up-gantt. For the building project itself, see /templates/construction-gantt-chart.

What this flowchart covers

In this template

  • Four groups, Site and permits, Equipment and long lead, Installation and utilities and Commissioning and handover, with 20 tasks and four milestones: "Permits granted", "Equipment on site", "Utilities ready" and "First production approved".
  • Three streams from one decision: "Freeze layout and process flow" leads to "Submit permit applications", "Prepare building and floors" and "Issue equipment purchase orders".
  • A 40-day "Manufacture long-lead equipment" task followed by "Factory acceptance test at supplier", "Ship and deliver equipment" and "Equipment on site".
  • A permit gate in front of utilities: "Permits granted" leads to "Connect power, air and water", which ends in "Utilities ready".
  • A commissioning group in which "Train operators and maintenance staff" starts 4 days after "Run equipment commissioning" starts and "First production approved" waits for validation and training.

When to use this template

  • You are opening a new plant, line or production site and need one plan that spans permits, building, equipment and people.
  • You want to see whether the permit review, the equipment lead time or the building works decides the first-production date.
  • A sponsor needs first production by a date and you want to compare the finish date with the date you need.
  • You want a skeleton that engineering, production, quality and the project manager can each adapt to their part.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Freeze layout and process flowSite and permits4
2Submit permit applicationsSite and permits31
3Authority review of applicationsSite and permits202
4Permits grantedSite and permitsMilestone3
5Prepare building and floorsSite and permits151
6Issue equipment purchase ordersEquipment and long lead31
7Manufacture long-lead equipmentEquipment and long lead406
8Factory acceptance test at supplierEquipment and long lead37
9Ship and deliver equipmentEquipment and long lead108
10Equipment on siteEquipment and long leadMilestone9
11Connect power, air and waterInstallation and utilities104, 5SS+3
12Utilities readyInstallation and utilitiesMilestone11
13Position and anchor equipmentInstallation and utilities85, 10
14Connect equipment to utilitiesInstallation and utilities612, 13
15Run equipment commissioningCommissioning and handover814
16Validate process and first samplesCommissioning and handover1015
17Write operating proceduresCommissioning and handover68
18Train operators and maintenance staffCommissioning and handover815SS+4, 17
19First production approvedCommissioning and handoverMilestone16, 18
20Hand over to productionCommissioning and handover319

How it works

  1. Fix the layout first

    Keep "Freeze layout and process flow" as the single starting task. Everything else waits for it, so a late change to the layout moves permits, floor works and purchase orders together.

  2. Replace the long-lead duration

    Set "Manufacture long-lead equipment" to the lead time your supplier has quoted. It is the longest task in the chart, so check its length before any other.

  3. Check the permit gate

    "Authority review of applications" is waiting time you do not control. Set it from the authority's stated review time and see whether "Permits granted" arrives before "Prepare building and floors" finishes.

  4. Join the streams at installation

    "Position and anchor equipment" waits for the floor works and "Equipment on site". Add your own steps, such as crane booking or a supplier's installation crew.

  5. Overlap training with commissioning

    "Train operators and maintenance staff" is linked start-to-start with a lag of 4 days to "Run equipment commissioning". Change the lag to how soon your staff can work on the machine.

  6. Add owners, share and export

    Put the responsible person in People, share the chart with engineering, production and quality, and export a PDF or CSV for the project file when you need a copy.

Frequently asked questions

How is this different from an equipment installation Gantt chart?

That template plans one machine. This one plans the whole site, so permits, building works, utilities and training run beside the equipment and meet it at installation. For one machine, see /templates/equipment-installation-gantt.

Where does production ramp-up fit?

After "Hand over to production". This chart stops at the first approved production, and the build-up in volume is a separate plan. See /templates/production-ramp-up-gantt.

Does the chart get the permits or approve the equipment?

No. It schedules the work. Permits come from the authority, and validation and approval follow your own quality system and are recorded there. The chart shows when each step is meant to happen.

Are the durations realistic for my industry?

They are illustrative. Lead times, permit reviews and validation lengths differ widely between industries and countries, so replace each with your own figure and read the finish date from the chart.

Can I show which task decides the finish date?

Yes. Turn on the critical path under View to highlight the chain that decides the end. For the method, see /guides/gantt-chart-dependencies.

Part of

QueryChart features for this process

Use this template

More in Operations process templates

Browse all Operations process templates