Volunteer recruitment drive Gantt chart template: waves and cohorts

An editable Gantt chart for an annual volunteer drive: role descriptions, three overlapping outreach waves, information sessions, reference and check waits, inductions in two cohorts and first shifts, with milestones.

Use this template

What the volunteer recruitment drive gantt chart template: waves and cohorts process is

The hard part of recruiting volunteers is rarely the advert. It is the gap between someone saying yes and that person being ready for a first shift. In that gap sit the information session, the request for references and checks and the wait for the answers, which depends on other people. A timeline helps because it shows how much of the drive is waiting and lets you keep the next wave of outreach going while the last group is still being cleared.

This template has five groups: Plan and roles, Outreach waves, Sign-up and checks, Induction cohorts and First shifts and review. It has 24 tasks and four milestones, and a total length of 33 working days in the illustrative numbers. **Agree roles and numbers needed** (2 working days) leads to **Write role descriptions and the sign-up form** (3) and then to the milestone **Drive ready to launch**. From there the three outreach waves overlap on purpose. **Outreach wave 1: past volunteers and supporters** (4) is followed by **Outreach wave 2: schools, employers and local groups** (5) with a start-to-start link 3 working days in, and **Outreach wave 3: social media and local press** (5) follows wave 2 the same way.

Each wave feeds an information session. **Information session round 1** and **Information session round 2** (2 working days each) start 2 working days into the wave that fills them, and both wait for **Book information session dates and venues** (2). After a session, the people who want to go ahead get **Send reference and check requests, cohort 1** or **Send reference and check requests, cohort 2** (1 each), and then the long wait: **Wait for references and checks, cohort 1** and **Wait for references and checks, cohort 2** (10 each). The two cohorts are cleared by the milestones **Cohort 1 cleared** and **Cohort 2 cleared**, so the first cohort can be inducted and begin buddy shifts while the second is still waiting. That overlap is the point of the template.

**Induction session, cohort 1** and **Induction session, cohort 2** (2 each) each need their cohort cleared and **Plan induction sessions and trainers** (4), which is prepared while outreach is running. **Buddy shifts, cohort 1** and **Buddy shifts, cohort 2** (5 each) follow, then **Add both cohorts to the rota** (2) and the milestone **Volunteers on the rota**. **Drive review and thank-you** (3) closes the drive once the second cohort's shifts are done. In the illustrative numbers the path through the second cohort's checks is the longest, so a delay to the first cohort's references costs nothing until it grows past the gap between the cohorts. All durations are illustrative: replace them with how long your references and checks take.

A timeline schedules the work. It does not decide which checks your food bank needs for each role, and what is required differs by country and by the work a volunteer does, so keep those requirements as tasks or notes with their own owners. For related plans, see /templates/volunteer-recruitment-and-onboarding-process for the flowchart of the same journey, /templates/volunteer-shift-scheduling-and-cover-process for the rota afterwards and /templates/fundraising-campaign-gantt-chart for another plan built from overlapping waves. For how start-to-start links and milestones work, see /guides/gantt-chart-dependencies and /guides/gantt-chart-milestones.

What this flowchart covers

In this template

  • Five groups, Plan and roles, Outreach waves, Sign-up and checks, Induction cohorts and First shifts and review, with 24 tasks and four milestones: "Drive ready to launch", "Cohort 1 cleared", "Cohort 2 cleared" and "Volunteers on the rota".
  • Three outreach waves that overlap through start-to-start links of 3 working days, so wave 2 and wave 3 begin before the previous wave has finished.
  • Two cohorts with their own waits: "Wait for references and checks, cohort 1" and "Wait for references and checks, cohort 2" are separate tasks, each followed by its own induction and buddy shifts.
  • Two information session rounds that start 2 working days into the wave that fills them, and a "Welcome calls and sign-up follow-up" task that runs alongside the sessions.
  • A "Drive review and thank-you" task that waits for the second cohort's buddy shifts, so the review sees the whole drive.

When to use this template

  • You run a volunteer drive once or twice a year and want a plan you can resize each time.
  • References and checks take a variable time and you want to see how late a cohort can be cleared before the first shifts slip.
  • You recruit in groups and want to know whether to start the next wave of outreach now or wait for the last wave to finish.
  • You need to show trustees or a funder when new volunteers will be on the rota.

The plan, task by task

Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.

#TaskGroupWorking daysDepends on
1Agree roles and numbers neededPlan and roles2
2Write role descriptions and the sign-up formPlan and roles31
3Drive ready to launchPlan and rolesMilestone2
4Outreach wave 1: past volunteers and supportersOutreach waves43
5Outreach wave 2: schools, employers and local groupsOutreach waves54SS+3
6Outreach wave 3: social media and local pressOutreach waves55SS+3
7Book information session dates and venuesSign-up and checks23
8Information session round 1Sign-up and checks24SS+2, 7
9Information session round 2Sign-up and checks25SS+2, 7
10Welcome calls and sign-up follow-upSign-up and checks108SS+1
11Send reference and check requests, cohort 1Sign-up and checks18
12Wait for references and checks, cohort 1Sign-up and checks1011
13Cohort 1 clearedSign-up and checksMilestone12
14Send reference and check requests, cohort 2Sign-up and checks19
15Wait for references and checks, cohort 2Sign-up and checks1014
16Cohort 2 clearedSign-up and checksMilestone15
17Plan induction sessions and trainersInduction cohorts43
18Induction session, cohort 1Induction cohorts213, 17
19Induction session, cohort 2Induction cohorts216, 17
20Buddy shifts, cohort 1First shifts and review518
21Buddy shifts, cohort 2First shifts and review519
22Add both cohorts to the rotaFirst shifts and review220, 21
23Volunteers on the rotaFirst shifts and reviewMilestone22
24Drive review and thank-youFirst shifts and review36, 10, 21

How it works

  1. Give the drive a start date

    Give "Agree roles and numbers needed" a fixed Start on the day you begin. The plan is scheduled forward from the earliest fixed Start. If a launch date is already announced, give "Outreach wave 1: past volunteers and supporters" a fixed Start as well and check the milestone "Drive ready to launch" for a conflict flag.

  2. Set the waves to your reach

    Resize the three outreach tasks to the time each channel really needs, and change the 3-day start-to-start links to how soon after one wave starts the next can begin without splitting your attention.

  3. Replace the check waits

    Set "Wait for references and checks, cohort 1" and "Wait for references and checks, cohort 2" from how long yours take in practice. Use the longest recent case if you want a cautious plan.

  4. Size the cohorts

    Set the two induction sessions and the buddy shifts to your own length. If you only have one cohort, delete the cohort 2 tasks and the milestone.

  5. Add owners, share and export

    Put the person responsible for each task in People, share the chart as a link with the volunteer coordinator and trustees, and export a PDF or PNG for the meeting. To start from your own list, paste your table into the sheet.

Frequently asked questions

Why are there two cohorts instead of one wait?

Because people say yes at different times. The first information session produces the first group, which can be cleared and inducted while the second group is still waiting. Splitting the wait in two lets the plan show that overlap and shows which cohort sets the end date.

Does the plan say which checks I need?

No. What is required differs by country and by the role a volunteer does, and the plan holds your own durations for the wait. Keep any requirement as a task or a note next to the wait, with its own owner.

How is this different from an onboarding plan for new staff?

This one is built around outreach waves and cohort inductions: a group of people is recruited in stages and joins in two batches. A staff onboarding plan follows one person through a fixed sequence. For that, see /templates/new-clinician-onboarding-gantt-chart.

What if the first wave brings too many people?

Lengthen "Welcome calls and sign-up follow-up" and the two request tasks, and see which dates move. If the cohort is too large for one induction, add a second induction task and link it from the same milestone.

Can I use the chart to find the latest date to start?

The chart schedules forward from the start you give it, so it will not work backwards from a date. Give the launch task a fixed Start and read the earliest date the dependencies allow for "Volunteers on the rota", then move the start until that date suits you.