Managing agent handover Gantt chart template: due diligence to cut-over
An editable Gantt chart for moving a rental portfolio to a new managing agent: due diligence, notices, data and deposit transfer, parallel running and cut-over, with dependencies and milestones.
What the managing agent handover gantt chart template: due diligence to cut-over process is
A handover to a new managing agent has more waiting than working. The outgoing agent's notice period has to run, tenants and contractors have to be told, and the records and held funds have to be checked before anything is switched. A timeline shows which waits run side by side and what the cut-over date really depends on.
This template has five groups: Due diligence, Notices, Data and money, Parallel running and Cut-over. It has 21 tasks and four milestones, and a total length of 41 working days in the illustrative numbers. "Request portfolio records from the outgoing agent" (2 working days) is the only starting task. It leads to "Review leases, certificates and contractor list" (6) and "Reconcile the rent roll and arrears" (4), and then to the first milestone, "Due diligence complete".
From that milestone three paths open at once. In Notices, "Serve notice on the outgoing agent" (1) leads to "Outgoing agent's notice period" (15), the longest wait in the plan. "Draft tenant and contractor letters" (2) leads to "Tenant notice period" (10) and "Re-appoint contractors" (5). In Data and money, "Export tenancy and ledger data" (3) leads to "Load and check data in the new system" (5), which leads to "Transfer deposits and held funds" (4). "Set up collection accounts" (3) runs beside them.
The parallel run is a start-to-start link. "Run both systems side by side" (10) starts once the data is loaded and the collection accounts exist, and "Compare rent receipts and fix differences" (5) starts 5 working days into it, so comparison begins while the run is still going. "Parallel run signed off" waits for the comparison and for "Transfer deposits and held funds". The milestone "Ready to cut over" then waits for four things: the parallel run, the outgoing agent's notice period, the tenant notice period and "Re-appoint contractors". In the illustrative numbers the parallel run is the last of the four to finish, 2 working days after the outgoing agent's notice period, and the plan shows how much slack the others have. How long notice must be, and how deposits must be moved or protected, differ by country and tenancy, so the plan holds your own durations and none of those rules.
After the milestone come "Switch rent collection and the repairs line" (2), "Outgoing agent's final statement" (5), "Close open handover items" (4) and the milestone "Handover complete". A timeline schedules the handover. It does not check that a notice is valid or that a transfer is complete. Keep those checks in your own records. For related work, see /templates/tenant-move-in-inspection-process for baseline inspections, /templates/security-deposit-return-process for deposits and /templates/rental-maintenance-request-process for the repairs line. For milestones that wait on several paths, see /guides/gantt-chart-milestones.
What this flowchart covers
In this template
- Five groups, Due diligence, Notices, Data and money, Parallel running and Cut-over, with 21 tasks and four milestones: "Due diligence complete", "Parallel run signed off", "Ready to cut over" and "Handover complete".
- Notice waits that run side by side: "Outgoing agent's notice period", "Tenant notice period" and "Re-appoint contractors" all start after "Due diligence complete".
- A data path: "Export tenancy and ledger data", "Load and check data in the new system" and "Transfer deposits and held funds".
- An overlapping comparison: "Compare rent receipts and fix differences" starts 5 working days into "Run both systems side by side".
- A cut-over gate: "Ready to cut over" waits for four paths before "Switch rent collection and the repairs line" can begin.
When to use this template
- You are moving a portfolio from one managing agent to another, in either direction.
- You need to see which of several notice periods sets the earliest cut-over.
- You want to run old and new systems together for a while and plan when to compare them.
- You need to tell an owner when the switch will happen and what it depends on.
The plan, task by task
Every task in the chart with its length in working days and what it waits for. A dependency is a step number; SS is start-to-start, FF is finish-to-finish, and +n is a lag in working days.
| # | Task | Group | Working days | Depends on |
|---|---|---|---|---|
| 1 | Request portfolio records from the outgoing agent | Due diligence | 2 | |
| 2 | Review leases, certificates and contractor list | Due diligence | 6 | 1 |
| 3 | Reconcile the rent roll and arrears | Due diligence | 4 | 2 |
| 4 | Due diligence complete | Due diligence | Milestone | 3 |
| 5 | Serve notice on the outgoing agent | Notices | 1 | 4 |
| 6 | Outgoing agent's notice period | Notices | 15 | 5 |
| 7 | Draft tenant and contractor letters | Notices | 2 | 4 |
| 8 | Tenant notice period | Notices | 10 | 7 |
| 9 | Re-appoint contractors | Notices | 5 | 7 |
| 10 | Export tenancy and ledger data | Data and money | 3 | 3 |
| 11 | Load and check data in the new system | Data and money | 5 | 10 |
| 12 | Transfer deposits and held funds | Data and money | 4 | 11 |
| 13 | Set up collection accounts | Data and money | 3 | 4 |
| 14 | Run both systems side by side | Parallel running | 10 | 11, 13 |
| 15 | Compare rent receipts and fix differences | Parallel running | 5 | 14SS+5 |
| 16 | Parallel run signed off | Parallel running | Milestone | 12, 15 |
| 17 | Ready to cut over | Cut-over | Milestone | 6, 8, 9, 16 |
| 18 | Switch rent collection and the repairs line | Cut-over | 2 | 17 |
| 19 | Outgoing agent's final statement | Cut-over | 5 | 18 |
| 20 | Close open handover items | Cut-over | 4 | 19 |
| 21 | Handover complete | Cut-over | Milestone | 20 |
How it works
Run due diligence first
Set "Request portfolio records from the outgoing agent" from how quickly the agent will respond, and resize the two review tasks from the size of the portfolio. Nothing else starts until "Due diligence complete".
Replace the notice waits
Set "Outgoing agent's notice period" and "Tenant notice period" to the periods in your own agreements and tenancies. They differ by country and contract, so use your own figures.
Size the data work
Set the export, load and deposit tasks from how many tenancies you hold and how clean the records are. If deposits are held in a scheme, add a task for each step of moving them.
Plan the parallel run
Set "Run both systems side by side" to the weeks you want, and adjust the 5-day start-to-start link on "Compare rent receipts and fix differences" to when the first receipts can be compared.
Check the cut-over
Look at "Ready to cut over" and find which of its four predecessors is last. If you have a fixed date, give "Switch rent collection and the repairs line" a fixed Start and watch for a conflict flag. Scheduling runs forward from the earliest fixed Start.
Add owners, share and export
Put the person responsible for each task in People, share the chart as a link with the owner and the new agent, and export a PDF or PNG for the handover file.
Frequently asked questions
Can the chart find the cut-over date for me?
It schedules forward from the dates you set. The date "Ready to cut over" gets is the earliest one that all four of its predecessors allow. If you need a particular date, fix the switch task there and the chart flags a conflict if the earlier work cannot finish in time.
Does it know how long notice has to be?
No. Notice periods differ by country and contract. Enter the periods from your own agreements.
Do I need the parallel run?
No. Delete the three tasks in Parallel running and link "Transfer deposits and held funds" straight to "Ready to cut over". Many teams keep it for the first rent cycle because it catches differences before tenants do.
Can I paste my portfolio into the chart?
There is no file upload and no import from project software. Paste your table of tasks and durations into the spreadsheet view. Dates in ambiguous formats are read in the order your interface language uses.
What if the outgoing agent is slow to hand over records?
Lengthen "Request portfolio records from the outgoing agent" and see what moves. Everything after "Due diligence complete" moves with it. See /guides/gantt-chart-dependencies for how delays pass along a chain.