How to plan a patient recall drive on a Gantt chart
Plan a patient recall drive on a Gantt chart: the recall list, message wording, sending waves with response waits, extra hygiene sessions that match the replies, phone follow-up and a review of what was booked.
A recall drive fills the diary only if the messages go out in waves and the chairs are ready for the replies. This guide shows how to put the list, the waves, the response waits and the extra sessions on a Gantt chart and see which part sets the finish.
The short version
- Fix the Start of the first task and let the later dates follow from the dependencies.
- Let the list and the wording run side by side and release the first wave from both.
- Give each response wait a plain task with a duration you can change.
- Use start-to-start links so booking and phone follow-up begin while the waits are still running.
- Turn on Critical path to see whether the waves or the extra sessions set the finish.
Send in waves, wait for replies and open chairs to meet them
A recall drive has three streams that must meet. The first is the list of patients who are overdue, cleaned and checked for contact preferences. The second is the wording, written and approved before anything is sent. The third is the capacity: the free recall slots and any extra hygiene sessions that the replies will need. The messages go out in waves, with a response wait after each, so the chairs fill gradually.
A Gantt chart in QueryChart schedules forward from the earliest fixed Start. Give "Set the drive goals and recall rules" a fixed Start on the day you begin. The list stream and the wording stream run side by side, and "Send wave 1 to the longest overdue" waits for both. Each response wait is a plain task with a duration you can change. "Book recalls as replies arrive" starts one day into the first wait, because bookings come in as soon as the first messages are read.
The example below is the patient recall drive template: 24 tasks in five groups. In it the list is ready on day 8 and the messages are approved on day 9, so the first wave goes out on day 10. Wave 1, wave 2 and the final reminder follow with a response wait between each, and the last responses come in on day 26. Phone follow-up starts two days into the second wait. The durations are illustrative and you replace them with your own.
After the example, a flowchart shows the process each recalled patient goes through: the recall and hygiene visit. A Gantt chart says when each wave goes out and cannot draw the choice of reminder channel or the decision about the next interval. Durations in both charts are illustrative. Rules on contacting patients, consent and records differ by country, so the plan holds your durations and your own advisers decide what they are. A timeline schedules the work. It is not dental, medical or legal advice.
For waits and gaps in general see /guides/gantt-chart-buffer-time and /guides/gantt-chart-delays. For the chart itself, see /templates/dental-recall-drive-gantt-chart, and for the process each patient follows, /templates/dental-recall-and-hygiene-visit-process.
A recall drive, built in stages
Twenty-four tasks in five groups. Durations are illustrative working days. Open the spreadsheet panel to see the rows behind each stage.
The patient list
"Set the drive goals and recall rules" (2 working days) leads to "Export the overdue recall list" (1) and "Clean the list of duplicates and leavers" (4). "Check consent and contact preferences" (3) starts two days into the cleaning. "Recall list ready" is a milestone on day 8.
The message wording
"Draft the message wording" (3) starts on day 3, beside the list work. "Dentist approves the wording" (2) and "Build the message templates by recall type" (2) follow, and "Messages approved" is a milestone on day 9.
The sending waves
"Send wave 1 to the longest overdue" (1) waits for both streams and goes out on day 10. "Wave 1 response wait" (5), "Send wave 2" (1), "Wave 2 response wait" (5), "Send the final reminder" (1) and "Last responses come in" (4) follow in order and end on day 26.
Chair capacity
"Count free recall slots" (2) starts on day 3. "Decide on extra hygiene sessions" (1) waits for the first response wait, "Open the extra hygiene sessions" (3) follows and "Extra sessions run" (10) ends on day 29. "Book recalls as replies arrive" (12) starts a day into the first wait.
Follow-up and review
"Phone patients who have not replied" (6) starts two days into the second wait. "Update records for patients who moved or left" (3) and "Count booked and attended recalls" (2) lead to the milestone "Drive review held" on day 31. The extra sessions and the records update both end on day 29, so either can set the review.
The process each recalled patient follows
The recall and hygiene visit as a flowchart. The Gantt chart says when each wave goes out and this chart shows what happens to one patient from the reminder to the next recall.
The recall list
"Recall due list run for the coming month" leads to "Check each patient's recall interval in the record". "Interval set and patient still registered?" sends a No to "Dentist sets the interval or closes the record" and a Yes onward.
Choosing the reminder
"Preferred reminder channel?" has three branches: Text message, Email and Letter or phone call. The first two lead to a message with the booking link and the third to "Post a letter or phone the patient".
When the patient does not book
"Booked within the reminder window?" sends a No to "Send a second reminder and phone the patient". If "Patient reached and booked?" is No, the case goes to "Escalate the overdue patient to the practice manager" and ends at "Recall left open and the attempts recorded".
The visit
A booking leads to "Book the hygiene visit and confirm it", then "Patient arrives and updates the medical history form" and "Clean the teeth and give home care advice".
After the visit
"Findings outside the routine?" sends a Yes to "Alert the dentist to review the findings". "Interval stays the same?" sends a No to "Dentist records the new interval and the reason". Both routes end at "Next recall booked and date recorded".
How it works
Open the recall drive chart
Open the template and replace each duration with what your practice team knows about its own list, its message tool and its diary. Put the person responsible for each task in People.
Fix the first Start
Give "Set the drive goals and recall rules" a fixed Start on the day you begin. The plan is scheduled forward, so every wave date is a result of the chain until you fix one.
Set the response waits
Replace the durations of the response waits with how long your patients take to reply. Hover over a task to see the dates it produces.
Match capacity to the replies
Change the extra hygiene sessions to the number of days your team can staff and watch whether the review date moves.
Find what sets the finish
Turn on Critical path in the View menu. If the messages and the waves are lit, shorten the wording stream or the waits. If the extra sessions are lit, look at when they open.
Share the plan with the team
Share the chart as a link so reception, the hygienists and the manager can see their part and add comments. Export a PDF for people who are not in the chart.
Mistakes to avoid
Sending everything at once
One large send fills the phones and the diary on the same day. Use waves with a response wait between them so the bookings arrive at a pace the team can handle.
Opening extra sessions before the replies are known
Hold the decision until the first response wait has ended, then size the sessions to what has actually been booked.
Leaving the list stream out
Duplicates and leavers waste messages. Give the clean-up and the contact-preference check their own tasks and release the first wave from them.
Using the template durations as facts
Reply times, session lengths and wording approval are illustrative. Rules on contacting patients differ by country, and the chart is not advice.
Open the recall drive Gantt chart
Open the template, fix the first Start and see whether the waves or the extra sessions set the finish.
Related guides
Frequently asked questions
Can QueryChart work backwards from a review date?
No. Scheduling is forward only. Fix the Start of the first task, and fix the Start of the review milestone if a date is already agreed, then read the conflict flag to see whether the chain before it fits.
How do I show waiting for patients to reply?
Add a plain task for the wait and give it a duration. In the example each response wait is 5 working days.
Can booking start while the first wave is still being answered?
Yes. Link the booking task to the response wait with a start-to-start dependency and a lag. In the example booking starts a day into the first wait.
Can I paste my own recall plan?
Yes. Paste your table into the spreadsheet panel with one row per task and the group, duration and dependencies in columns. You can then edit it as a chart.