How to plan a seasonal vaccination campaign on a Gantt chart
Plan a seasonal clinic campaign on a Gantt chart: the supplier lead time, a reminder cascade, extra clinic days, the clinics themselves and the follow-up of animals that did not attend, with the campaign start as the gate.
A campaign starts on a date that the clinic announces, but the order for stock has a lead time that the clinic does not control. This guide shows how to plan the lead time, the reminders and the clinic days on one Gantt chart and see which of them sets the start.
The short version
- Put the supplier lead time in a plain wait task with the duration you are quoted.
- Link the final reminder to the delivery check as well as to the earlier reminders.
- Give the bookings wait its own task so the second reminder has something to follow.
- Use a finish-to-finish link when records are updated through the clinics and not after them.
- Fix the campaign opening if it is announced and read the conflict flag.
Start from the stock lead time, then fit the reminders around it
A seasonal campaign has a public date and a private chain behind it. The public date is when the extra clinic days open. The chain is the animals to be listed, a target to be set, an order to be placed, a supplier lead time to be waited out and a delivery to be checked. Reminders that go out before the stock is confirmed promise appointments the clinic may not be able to keep, so the reminders are linked to the delivery as well as to the list.
A Gantt chart in QueryChart schedules forward from the earliest fixed Start. Fix the Start of "List the animals due a vaccine" on the day you begin, give "Wait for supplier lead time" the duration your supplier quotes and let "Campaign opens" follow. If the opening date is already announced, fix the Start of the milestone and read the conflict flag: if the chain cannot reach it, the plan shows the clash. The reminder strand is a cascade of small tasks, with "Wait for bookings to come in" as a plain wait and "Remind those who have not booked" as the second touch.
The example below is the vaccination campaign template: 22 tasks in five groups. "Send the final text reminder" needs both the delivery check and the second reminder, so a late delivery holds it. "Update records and certificates" ends 1 working day after "Run the campaign clinics", using a finish-to-finish link, because records are updated through the clinics and not after them. The follow-up of animals that did not attend starts only when the clinics close.
After the example, a flowchart shows the recall process that sits behind the reminders. A Gantt chart can schedule the reminder tasks but it cannot draw the second reminder, the letter and the phone call as branches. Durations in both are illustrative. Vaccine schedules, intervals and stock handling are decided by your vets and your supplier, and this guide does not state any of them. A timeline schedules the work. It is not veterinary advice and does not make a campaign effective.
For reading a late supplier through the plan, see /guides/gantt-chart-delays, and for the waits between tasks, /guides/gantt-chart-buffer-time. For a project with a different date driver, see /guides/practice-integration-gantt-chart.
A seasonal campaign, built in stages
Twenty-two tasks in five groups. Durations are illustrative working days. Open the spreadsheet panel to see the rows behind each stage.
The order and the supplier lead time
"List the animals due a vaccine" (2 working days) leads to "Set targets and campaign dates" (1) and "Place the vaccine order" (1). "Wait for supplier lead time" (12) is a plain wait with the duration your supplier quotes, and "Check and store the delivery" (1) closes it. Fix the Start of the first task on the day you begin.
The reminder cascade
"Write the reminder message" (2) and "Build the reminder send list" (2) lead to "Send the first reminder" (1) and "Wait for bookings to come in" (5). "Remind those who have not booked" (1) follows, and "Send the final text reminder" (1) also waits for the delivery check, so a late delivery holds it.
Extra clinic days and the opening
"Plan the extra clinic days" (2) and "Rota staff and rooms for extra days" (3) run beside the order. "Campaign opens" is a milestone that waits for the delivery check, the first reminder and the rota. If the opening date is announced, fix its Start and read the conflict flag.
The clinics and the records
"Run the campaign clinics" (15) starts at the opening. "Update records and certificates" (14) is linked finish-to-finish with a 1 day lag, so it ends 1 working day after the clinics. "Campaign clinics close" is the milestone that starts the follow-up.
Follow-up and review
"List the animals that did not attend" (1) leads to "Phone or message non-attenders" (5). "Book catch-up appointments" (5) starts 2 working days into the calls. "Review results against targets" (2) and "Campaign reviewed" close the plan. The longest chain adds up to 43 working days.
The recall behind the reminders
The vaccination recall process as a flowchart. The Gantt chart gives the reminders and the follow-up a duration and this chart shows the branches.
Who is on the list
"Monthly recall run begins" leads to "Pull the list of patients due next month" and "Patient active and owner contact details current?". A No goes to "Mark the contact for a check at the next visit", which closes the patient out of this run. The first task on the Gantt chart, "List the animals due a vaccine", is where this list is made.
The first and second reminder
"Send the first reminder by SMS or email" leads to "Booked within the first wait period?". A No sends "Send the second reminder by the owner's other channel" and then "Booked after the second reminder?". On the Gantt chart these are "Send the first reminder", "Wait for bookings to come in" and "Remind those who have not booked".
The letter, the call and the escalation
A second No leads to "Post a letter that explains the risk of a lapse" and "Owner reached by phone call?". If nobody is reached, "Practice Manager reviews the case and decides how to proceed". The Gantt chart folds this into the follow-up group, where "Phone or message non-attenders" gets a duration.
The visit and the record
"Owner attends with the pet" leads to "Fit for vaccination on the day?". A No means "Postpone and rebook the visit". Otherwise "Give the vaccine and complete the vaccination card" and "Update the record and set the next due date" end at "Patient up to date and next recall scheduled". Whether and when a patient is fit is a clinical decision for your vets.
How it works
Open the campaign chart
Open the vaccination campaign template and replace each duration with what your supplier, rota and vets tell you. Put the person responsible for each task in People.
Set the supplier lead time
Replace the duration of "Wait for supplier lead time" with the lead time you have been quoted, and fix the Start of "List the animals due a vaccine" on the day you begin.
Link the reminders to the delivery
Check that "Send the final text reminder" is linked to "Check and store the delivery" as well as to the earlier reminders, so no reminder promises a slot the clinic cannot fill.
Read the opening against the announcement
If "Campaign opens" has been announced, fix its Start and read the conflict flag. Turn on Critical path to see whether the order or the rota sets the date.
Add the follow-up
Keep the follow-up group linked to "Campaign clinics close". Start the catch-up bookings part way into the phone calls with a start-to-start link.
Share the plan with the team
Share the chart as a link so reception, nurses and vets can see their tasks and add comments. Export a PDF for the practice noticeboard.
Mistakes to avoid
Sending reminders before the stock is confirmed
A reminder linked only to the list can go out before the delivery is checked. Link the final reminder to the delivery.
Forgetting the lead time grows in busy seasons
A quoted lead time is a quote. Add a margin to the wait task or ask the supplier for a date, then read the finish.
Leaving the follow-up out of the plan
Animals that did not attend are the work that takes most chasing. Give it its own group and durations.
Assuming the chart is clinical advice
QueryChart schedules the tasks. It does not decide intervals, schedules or fitness to vaccinate, which belong to your vets.
Open the vaccination campaign Gantt chart
Open the template, enter your supplier lead time and see whether the campaign can open on the date you announced.
Related guides
Frequently asked questions
Can QueryChart work backwards from the campaign start?
No. Scheduling is forward only. Fix the Start of the first task, fix the Start of "Campaign opens" if it is announced, and read the conflict flag.
How do I show the second reminder?
Give "Wait for bookings to come in" a duration and follow it with "Remind those who have not booked". A Gantt chart cannot draw the branch, so the flowchart in the guide shows it.
What does finish-to-finish mean here?
The records task finishes 1 working day after the clinics finish, but it starts earlier. The link keeps the two tasks ending together.
Can I paste my own campaign plan?
Yes. Paste your table into the spreadsheet panel with one row per task and the group, duration and dependencies in columns.